Professional Documents
Culture Documents
The project on Newly proposed building complex for Attorney general which is located near
the supreme court Colombo-12 was the place that I have been transferred to carry on my
training. The whole electrical part was given to the Electrical division of Tudawe Engineering
Services (pvt) Ltd. Under the Electrical part, laying slab/wall conduits, drawing electrical
cables, fabricating panel boards, fixing them and powering up the building with electricity,
monitoring the consumption of electricity, testing the wiring and electricity supply for any
leakage or for any other defects were crucial steps of the whole project. During my training
period I got to see and experience these activities which are done in order to power up a large
building (In this case a building complex consisting of 12 floors). During this 12 week I had
the opportunity to perform and supervise the conduit laying on slab level and wall level,
perform and supervise the electrical cable laying, see and experience a panel board fabrication,
experience a panel board fixing, experience a cable dressing inside a panel board, experience
a main panel board linkage with 3 phase C.E.B electricity distribution.
The main focus of exposing into above mentioned activities was to sense how the theoretical
knowledge (that has been studied in these 2 years) has implemented practically and get the idea
how those things are performed under a good quality and get the maximum harvest of profit.
During the linkage of main panel board with cables from National grid, one of the laws
(IB<=IN<=IZ>=1.45*I2) which has been used to calculate resistivity of current carrying 240mm2
Cu/Xlpe/PVC cable was examined. Furthermore, during the training period, various methods
of Human Resource Management were learnt from the trainee supervisors.
Acknowledgement
It is a great pleasure for me to acknowledge the assistance and contributions of all the people
who helped me to make my industrial training a success. My training would not have been so
successful, without the dedicated assistance given by those individuals.
I would like to give my special thanks to Mr. Amal Tudawe (C.E.O of Tudawe Engineering
Services (pvt) Ltd.), Eng. Dilan Fernando (Site Engineer for A.G.D’s new office complex
project) and all the officials of Industrial Training Division and NAITA for supervising me
during the training period.
I would also like to thank Mr. R. Sudagar (Engineering Assistant and trainee inspector) Mr.
Buddhika Rathnayake (Engineering Assistant and trainee inspector) and all other Officials of
Electrical Division of Tudawe Engineering Services for the assistance and guidance they have
given. At Sri Lanka Institute of Information Technology, I would like to thank Training
Engineer, Dr. Chulantha Kulasekare for providing necessary facilities, lectures and sharing
their knowledge with me.
Finally I would like to thank every individual (who I have not mentioned names above) who
gave me even the slightest support (even by words) to make my Industrial training a success.
Table 01
Table 02
Table 03
Table 04
Table 05
Table 06
Table 07
Table 08
Table 09
Contents
Abstract
Acknowledgement
List of figures
List of tables
1. Introduction
1.1.Vision and mission
1.2.Company Background/history
1.3.Management
2. Training experience
2.1.Summary of duties
2.2.Projects involved
2.3.Problems encountered and approach of solving
3. Conclusion
References
Appendices
1.0 Introduction
Mission:
To offer timely delivery of quality construction and services at a competitive cost through
motivated staff, superior technology, efficient systems and sustainable development.
Mr. P. Roger
Talbad
(Sr. Manager -
Engineering)
Mr. IndunilLalaji
(M & E
Coordinator)
Mr. K.
Wijayathilake
(Project Engineer)
Mr. Dilan
Fernando
(Site Engineer)
Mr.
Mr. R. Sudagar BuddhikaRathnay
(Engineer Asst) ake
(Engineer Asst)
Mr. R.L.
Mr. SagaraPerera Mr. Prasad Perera Supervisor/
Jayashinhe
(Site Q.S) (Draughtman) Charge hand
(Store keeper)
Electricians
2.0. Training experience
Neutral Blue
Live Brown
Figure 1:5-core Cu/XLPE/PVC cable
Before doing any part of the power wiring, at first the latest approved drawing must be checked.
Then according to that drawing the wiring must be performed. After checking for the approved
drawing, necessary equipment for drawing power cables through conduits and termination of
them, must be get ready. (Tools used for drawing and termination of cables are listed in Table
02.).
Tool Qty
Torque wrenches 1
Multi meters 1
Insulation testers 1
Tool Qty
Then at the site, looked for any conduit blockage and as there were none, lighting sub circuit
(Figure 02 – sub circuit) wiring was done according to the approved drawing. Finally cleaning
the workplace was carried out.
Figure 2:Sub circuit of a lighting
system(shown by green dotted lines)
Tool Qty
Inspecting and learning about the L.A.N. and telephone cable drawing:
Prior to the L.A.N. and telephone wiring in 4th floor, availability of the latest approved shop
drawing was checked. After getting the latest approved shop drawing, wire specifications
(Category 06 [CAT-06] 100Ω UTP cable) were checked according to the M.A document and
confirmed that the enough cable lengths were available for the whole floor. Tools required for
the work were checked in the stores (Table-05) and checked whether they were operating
accordingly.
Tool Qty
Multi meters 1
Insulation testers 1
But the portioning wall has been fixed without keeping any conduit paths for the cables as the
portioning team hasn’t got any information during their working time. So, after an inspection
the cables were managed to draw from inside the aluminum framework reserved for the main
door. For each and every cable a safe turning radius has been declared in M.A. document from
the manufacture. For CAT-06 the recommended turning radius must be kept accurately in
bends as if somehow a network problem has arisen (because of steep turnings), it will be so
difficult to solve.
Double checking while learning about the technical literature of sunk box fixing:
Two types of sunk boxes (3”×3” and 3”×6”) are attached to concrete walls and partitioned
walls in order to fit the face plates of switches and power socket outlets. Sunk boxes were fixed
mainly in brick walls and partition walls. First of all, approved latest shop drawing was checked
and confirmed its availability. Then in stores, availability of necessary tools (Table-06) was
checked and confirmed. After visiting the floor, sunk boxes fitting on Marshall-Tufflex were
searched and conduit pipes were down run from slab level up to that point. After that according
to the shop drawing places were marked on the wall by using a pencil. After marking all of the
wall openings, wall chasing was started.
First of all, Personal Protective Equipment (PPE) were wore. (Safety eye goggles, Rubber
coated cotton gloves, Overall, Safety shoes, Dust masks, earmuffs). Then by using angle
grinder, wall surface has been damaged (Figure-05) inside of the marked region.
Next, Hammer drill was used to punch the wall until the damaged parts of the wall are
collapsed.
Figure 5:Conduit pipes drawn for
L.A.N. wiring
Afterwards, by applying cement on backside of the sunk box, it was placed in the created hole
and levelled by using a spirit level before cement get dried.
Fixing sunk boxes in partition wall was different from fixing them on a brick wall. The
measurements were given to the partitioning team and necessary holes (for sunk boxes and for
conduit paths) were created by them. During this work, one of our technicians was placed
beside by giving him latest approved shop drawing with necessary measurements.
After fitting the sunk boxes in brick wall, how the measurements had been taken to position
them were double checked. During the task, according to the latest shop drawing the vertical
and horizontal measurements of each and every sunk box was re- checked again by using a
measuring tape.