PROGRESS KONTRAKTOR

PERUM CIRUASLAND

DEVELOPER PT. RUCITA INDAH SEJAHTERA 30 Desember 2019


KONTRAKTOR PT. BUMI CITRA SENTOSA
LOKASI KERJA CLUSTER GOLD TAHAP 2 DEDI / AGUS
JUMLAH UNIT 2 UNIT TYPE 36 COUPLE
TYPE 36
C7
NO. URAIAN PEKERJAAN 16 17

BOBOT (%) PROGRESS PRESTASI BOBOT (%) PROGRESS PRESTASI

I PEK. PERSIAPAN & GALIAN TANAH


1 PAS . BOUPLANK + UITSET 0.00% 0.00% 0.00% 0.54% 100.00% 0.54%
2 GALIAN+URUG KEMBALI TANAH PONDASI 0.00% 0.00% 0.00% 0.33% 100.00% 0.33%
3 URUGAN TANAH + PEMADATAN LANTAI 0.24% 50.00% 0.12% 0.22% 100.00% 0.22%
4 URUGAN PASIR BAWAH PONDASI & LANTAI 0.16% 50.00% 0.08% 0.30% 100.00% 0.30%
II PEK. STRUKTUR BETON
1 PONDASI 50X50 CM 0.00% 0.00% 0.00% 1.29% 100.00% 1.29%
2 PONDASI 80X80 CM 0.00% 0.00% 0.00% 1.37% 100.00% 1.37%
3 SLOOF BETON 10X15 CM 0.00% 0.00% 0.00% 1.71% 100.00% 1.71%
4 SLOOF BETON 10X20 CM 0.00% 0.00% 0.00% 1.97% 100.00% 1.97%
5 KOLOM BETON 10XL0 CM 2.09% 100.00% 2.09% 1.90% 100.00% 1.90%
6 KOLOM BETON L0X20 CM 2.20% 100.00% 2.20% 2.00% 100.00% 2.00%
7 BALOK BETON 10X15 CM 1.88% 100.00% 1.88% 1.71% 100.00% 1.71%
8 BALOK BETON 10X20 CM 2.17% 100.00% 2.17% 1.97% 100.00% 1.97%
9 KANOPI BETON T=10 CM 1.80% 80.00% 1.44% 1.63% 100.00% 1.63%
10 TALANG BETON T=L0CM 1.88% 80.00% 1.50% 1.71% 100.00% 1.71%
11 MEJA DAPUR BETON 0.72% 0.00% 0.00% 0.66% 0.00% 0.00%
12 RABAT BETON CARPORT 0.71% 0.00% 0.00% 0.65% 100.00% 0.65%
III PEK PASANGAN & PLESTERAN
1 PAS. DINDING HEBEL 20X60X 10 CM 17.26% 100.00% 17.26% 15.69% 100.00% 15.69%
2 PLESTER ACI DINDING 12.72% 0.00% 0.00% 11.55% 100.00% 11.55%
3 PAS. KERAMIK LANTAI 60X60 CM 4.62% 0.00% 0.00% 4.20% 100.00% 4.20%
4 PAS. KERAMIK LANTAI KM 25X25 CM 0.40% 0.00% 0.00% 0.36% 0.00% 0.00%
5 PAS. KERAMIK DINDING KM 25X40 CM 2.01% 0.00% 0.00% 1.83% 100.00% 1.83%
6 PAS. SEMEN NAT KERARNIK 0.12% 0.00% 0.00% 0.11% 0.00% 0.00%
7 PAS. BATU ALAM 1.65% 0.00% 0.00% 1.50% 0.00% 0.00%
IV PEK. KUSEN PINTU & JENDELA
1 PAS. KUSEN ALLUMUNIUM LENGKAP 10.53% 0.00% 0.00% 9.58% 0.00% 0.00%
2 PAS. DAUN PINTU SEMI PANEL 4.21% 0.00% 0.00% 3.83% 0.00% 0.00%
3 PAS. ENGSEL PINTU 4" 0.32% 0.00% 0.00% 0.29% 0.00% 0.00%
4 PAS. KUNCI & HANDLE PINTU UTAMA 0.20% 0.00% 0.00% 0.18% 0.00% 0.00%
5 PAS. KUNCI PINTU BESAR 0.38% 0.00% 0.00% 0.34% 0.00% 0.00%
6 PAS. PINTU PVC LENGKAP 0.53% 0.00% 0.00% 0.48% 0.00% 0.00%
V PEK. ATAP & PLAFOND
1 PAS. RANGKA BAJA RINGAN ATAP GENTENG 4.93% 100.00% 4.93% 4.48% 100.00% 4.48%
2 PAS. PENUTUP ATAP GENTENG FLAT BETON 2.67% 80.00% 2.14% 2.43% 100.00% 2.43%
3 PAS. NOK GENTENG BETON 1.41% 0.00% 0.00% 1.28% 100.00% 1.28%
4 PAS. LISTPLANK GRC 8MM LEBAR 20CM 0.88% 100.00% 0.88% 0.80% 100.00% 0.80%
5 PAS. RANGKA BAJA RINGAN & ATAP SPANDEK 1.47% 0.00% 0.00% 1.34% 100.00% 1.34%
6 PAS. PLAFOND GYPSUM RANGKA HOLLO 4.45% 0.00% 0.00% 4.04% 100.00% 4.04%
VI PEK. INSTALASI AIR & SANITAIR 0.00% 0.00%
1 PAS. PIPA AIR BERSIH PVC ½' ' AW 0.58% 0.00% 0.00% 0.53% 100.00% 0.53%
2 PAS. PIPA AIR BUANGAN CLOSET PVC 4" D 0.00% 0.00% 0.00% 0.60% 100.00% 0.60%
3 PAS. PIPA AIR BUANGAN KOTOR PVC 4" D 0.00% 0.00% 0.00% 1.14% 100.00% 1.14%
4 PAS. PIPA AIR TALANGPVC 2" 0 1.23% 100.00% 1.23% 1.12% 100.00% 1.12%
5 PAS. CLOSET DUDUK 1.45% 0.00% 0.00% 1.32% 0.00% 0.00%
6 PAS. KITCHEN SINK L LUBANG 0.16% 0.00% 0.00% 0.15% 0.00% 0.00%
7 PAS. KRAN TEMBOK TAMAN 0.11% 0.00% 0.00% 0.10% 0.00% 0.00%
8 PAS. KRAN TEMBOK DOUBLE KM. MANDI 0.11% 0.00% 0.00% 0.10% 0.00% 0.00%
9 PAS. STOP KRAN TEMBOK CLOSET & ZETBANK 0.07% 0.00% 0.00% 0.06% 0.00% 0.00%
10 PAS. KRAN ANGSA MEJA 0.16% 0.00% 0.00% 0.14% 0.00% 0.00%
11 PAS. HANDSHOWER 0.14% 0.00% 0.00% 0.13% 0.00% 0.00%
12 PAS. HAND ZET BANK 0.10% 0.00% 0.00% 0.09% 0.00% 0.00%
13 PAS. FLOOR DRAIN 0.05% 0.00% 0.00% 0.05% 0.00% 0.00%
14 BUAT BAK KONTROL 40X40 CM 0.32% 0.00% 0.00% 0.29% 0.00% 0.00%
15 SUMUR BOR 15 M 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 PAS. PIPA PVC 2" AW CASING SUMUR 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 PAS. POMPA AIR LISTRIK 100W 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
18 PAS. PIPA SEDOT LENGKAP 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 PAS. BIO SEPTICTANK 1.84% 100.00% 1.84% 1.68% 100.00% 1.68%
TYPE 36
C7
NO. URAIAN PEKERJAAN 16 17

BOBOT (%) PROGRESS PRESTASI BOBOT (%) PROGRESS PRESTASI

VII PEK. INSTALASI LISTRIK


1 PAS. INSTALASI TITIK LAMPU 0.63% 0.00% 0.00% 0.57% 0.00% 0.00%
2 PAS. INSTALASI TITIK LAMPU BATU ALAM 0.16% 0.00% 0.00% 0.14% 0.00% 0.00%
3 PAS. SAKLAR DOUBLE & ENGKEL 0.37% 0.00% 0.00% 0.34% 0.00% 0.00%
4 PAS. INSTALASI TITIK STOP KONTAK 0.40% 0.00% 0.00% 0.36% 0.00% 0.00%
5 PAS. STOP KONTAK 0.16% 0.00% 0.00% 0.14% 0.00% 0.00%
6 PAS. FITTING DOWNLIGHT 4" 0.42% 0.00% 0.00% 0.38% 0.00% 0.00%
7 PAS. BOX SEKRING 2 GROUP & MCB 4A 0.20% 0.00% 0.00% 0.18% 0.00% 0.00%
VIII PEK. PENGECATAN
1 CAT TEMBOK DALAM, PLAFOND & DINDING LUAR 6.36% 0.00% 0.00% 5.78% 0.00% 0.00%
2 CAT DAUN PINTU 0.30% 0.00% 0.00% 0.28% 0.00% 0.00%
3 CAT LISTPLANK 0.07% 0.00% 0.00% 0.06% 0.00% 0.00%
100.00% 39.76% 100.00% 72.01%
MINGGU LALU 39.76% MINGGU LALU 65.30%
DEVIASI 0.00% DEVIASI 6.71%
SISA PEKERJAAN 60.24% SISA PEKERJAAN 27.99%

WALANTAKA - SERANG, 30 Desember 2019


PT. GAPURA CIPTA SEJAHTERA PT. RUCITA INDAH SEJAHTERA

CONTRACTOR PELAKSANA SITE MANAGER GENERAL MANAGER