Professional Documents
Culture Documents
1 Remote controller 1
G
more than 2
10cm R-03 dry battery 2
3 1
Mounting plate
Arrangement of piping
directions 4 1
Drain hose
F
Rear left 1
A 5 Drain-elbow
Left Rear
right
Note:Cooling only units don't have
Drain-elbow
Right C
Below
more than15cm
Please be subject to the actual product purchased , the above picture is just for your reference.
256
340
Drawing of pipe
140 500 140
113.5 633 113.5
1. Carry out, based on the neighboring pillars or lintels, a proper leveling for the plate Fixing the indoor unit body
to be fixed against the wall, then temporarily fasten the plate with one steel nail.
2. Make sure once more the proper level of the plate, by hanging a thread with a
weight from the central top of the plate, then fasten securely the plate with the
attachment steel nail. ● Hang surely the unit body onto the upper notches of the
3. Find the wall hole location A using a measuring tape mounting plate. Move the body from side to side to verify its
secure fixing.
● In order to fix the body onto the mounting plate,hold up
B= 60mm the body aslant from the underside and then put it down
perpendicularly. mounting plate
30mm
A=145mm
Unloading of indoor unit body
Ø60mm(07k-12k)
Ø70mm(18k/24k)
Note When connecting the cable, confirm the terminal number of indoor and
Indoor side Outdoor side outdoor units carefully. If wiring is not correct, proper operation can not
Thickness of wall be carried out and will cause defect.
(Section of wall hole) G Piping hole pipe
2
2
Half union Flare nut Forced fastening without careful centering may
damage the threads and cause a leakage of gas.
1(L) 2 (N)
Liquid side6.35mm(1/4") 18N.m
3G1.0mm Liquid/Gas side9.52mm(3/8") 42 N.m
Gas side 12.7mm(1/2") 55N.m
Spanner Torque wrench
Indoor unit Outdoor unit Gas side 15.88mm(5/8") 60 N.m
Be careful that matters, such as wastes of sands, etc. shall not enter the pipe.
Power cable: 3G1.0mm The standard pipe length is 5m. If it is over 7m, the function of the unit will be
affected. If the pipe has to be lengthened, the refrigerant should be charged,
according to 20 g/m. But the charge of refrigerant must be conducted by profes-
YSCC07FSAADG sional air conditioner engineer. Before adding additional refrigerant, perform air
YSCC09FSAADG purging from the refrigerant pipes and indoor unit using a vacuum pump,then
charge additional refrigerant.
YSCC12FSAADG
CAUTION
Outdoor unit
B Indoor unit
B
A
Indoor unit
A
Outdoor unit
● Max.Elevation: Amax=10m
Outdoor unit ● In case the elevation A is more
than 5m, oil trap shoud be
installed every 5~7m
Oil trap
B ● Max. Length: Bmax=15m
Indoor unit
● In case the pipe length B is
A more than 7m, the refrigerant
should be charged, according
to 20 g/m.
Outdoor unit 2. Open the handle at Iow in gaugemanifold, operate vacuum pump. If the scale-
moves of gause (Iow) reach vacuum condition in a moment, check 1. again.
1 Installation of Outdoor Unit
3. Vacuumize for over 15min.And check the level gauge which should read -0.1MPa
Install according to Drawing for the installation of indoor and outdoor units (76 cm Hg) at Iow pressure side. After the completion of vacuumizing, close the
handle ‘Lo’ in gaugemanifold and stop the operation of the vacuum pump. Check
condition of the scale and hold it for 1-2min. If the scale-moves back in spite of
2 Connection of pipes
tightening, make flaring work again, the return to the beginning of 3 .
● To bend a pipe, give the roundness as large as possible not to crush the pipe ,
and the bending radius should be 30 to 40 mm or longer. 4. Open the valve rod for the 2-way valve to an angle of anticlockwise 90 degrees.
● Connecting the pipe of gas side first makes working easier. After 6 seconds, close the 2-way valve and make the inspection of gas leakage.
● The connection pipe is specialized for R410A.
3
5. No gas leakage? 3 On Drainage
In case of gas leakage, tighten parts of pipe connection. If
leakage stops, then proceed 6. steps ● Please install the drain hose so as to be downward slope without fail.
● Please don’t do the drainage as shown below.
If it does not stop gas leakage, discharge whole refrigerants from the service
port. After flaring work again and vacuumize, fill up prescribed
refrigerant from the gas cylinder. Less than
5cm
6. Detach the charge hose from the service port, open 2-way valve and 3-way. Turn
the valve rod anticlockwiseuntil hitting lightly. It becomes The end is imm- It waves. The gap with the There is the bad
high midway. ersed in water. ground is too smal smell from a ditch
7.To prevent the gas leakage, turn the service port’s cap, the valve rod’s cap for 2-way
valve and 3-way’s a little more than the point where the torque increases suddenly.
● Please pour water in the drain pan of the indoor unit, and confirm that drainage
8. After attaching the each caps, check the gas leakage around the caps. is carried out surely to outdoor.
● In case that the attached drain hose is in a room, please apply heat insulation to
it without fail.
Step 1. Step 2.
2-way valve Liquid Side
3-way valve Gas Side Open
Gaugemanifold(for R410A)
■ Refrigerant charge label
Anti countercurrent joint
Step 3. Contains fluorinated greenhouse gases
covered by the Kyoto Protocol A
Close
Tube(for R410A)
Vacuum pump(for R410A) R410A 1= kg
B
2 2= kg
Step 4. C
2-way valve Step 6. 2-way valve 1
3-way valve
3-way valve 1+2= kg
O D
Open 90
F E
Correct Incorrect
4
2011 Johnson Controls, Inc. www.johnsoncont rols.com Form No. MJHFZHAAB-110412
Johnson Controls reserve the right to change product features without prior notice.