Professional Documents
Culture Documents
INTRODUCTION TO CONSTRUCTION
DRAWINGS
3.1 Introduction:
Drawing is the language of engineers. An engineer must be well conversant with drawings.
Drawings represent reduced shape of structure and the owner will be able to see what is going
to happen. The drawings are prepared as per the requirements of the owner. In case of public
buildings, the functional aspects are studied and accordingly the drawings are prepared as per
the recommendations laid down in National Building Code (N.B.C) or as per the Indian
standard specifications. Any modifications like additions or omissions can be suggested from
a study of the drawings before actual construction of the structure is started. Drawings
provide a language with specific data to Architects, Engineers and workman at the site to
construct the structure accordingly.
In case of public buildings, bridges or any other civil engineering works, it is essential to
workout different items of construction with their quantities for estimating the total cost of
construction project. For this purpose, drawings of different parts and different views are
essential so that approval of work from the sanctioning authority can be obtained. Further, the
detailed drawing form as an essential contract document, when the work is handed over to a
contractor. Hence, it is necessary to prepare detailed drawings which will inform the
contractor, the exact information which he needs during the construction of different items of
work.
The building of any structure is described by a set of related drawings that give the Builder a
complete, sequential, graphic description of each phase of the construction process. In most
cases, a set of drawings begins by showing the location, boundaries, contours, and
outstanding physical features of the construction site and its adjoining areas. Succeeding
drawings give instructions for the excavation and disposition of existing ground; construction
of the foundations and superstructure; installation of utilities, such as plumbing, heating,
lighting, air conditioning, interior and exterior finishes; and whatever else is required to
complete the structure.
The engineer works with the architect to decide what materials to use in the structure and the
construction methods to follow. The engineer determines the loads that supporting members
will carry and the strength qualities the members must have to bear the loads. The engineer
also designs the mechanical systems of the structure, such as the lighting, heating, and
plumbing systems. The end result is the architectural and engineering design sketches. These
sketches guide draftsmen in preparing the construction drawings.
Generally, construction or "working" drawings furnish enough information for the Builder to
complete an entire project and incorporate all three main groups of drawings-architectural,
electrical, and mechanical. In drawings for simple structures, this grouping may be hard to
discern because the same single drawing may contain both the electrical and mechanical
layouts. In complicated structures, however, a combination of layouts is not possible because
of overcrowding. In this case, the floor plan may be traced over and over for drawings for the
electrical and mechanical layouts.
All or any one of the three types of drawings gives you enough information to complete a
project. The specific one to use depends on the nature of construction involved. The
construction drawing furnishes enough information for the particular tradesman to complete a
project, whether architectural, electrical, or mechanical. Normally, construction drawings
include the detail drawings, assembly drawings, bill of materials, and the specifications.
A detail drawing shows a particular item on a larger scale than that of the general drawing in
which the item appears. Or, it may show an item too small to appear at all on a general
drawing. An assembly drawing is either an exterior or sectional view of an object showing
the details in the proper relationship to one another. Assembly drawings are usually drawn to
a smaller scale from the dimensions of the detail drawings. This provides a check on the
accuracy of the design drawings and often discloses errors.
Conventional signs are used to represent the particular item in the drawing. For example
stone masonry, brick masonry and concrete are indicated by standard conventional signs.
They are only represented in the section i.e., when the materials are cut by any imaginary
plane.
Similarly conventional symbols are provided to indicate doors, windows, their fixing,
movement of shutters when they are closed or opened, various water supply and sanitary
fixtures like tap, wash basin, W.C, urinals, kitchen sink, shower etc. Symbols are also used to
indicate the position of electrical fittings like, lamp, switch, power socket, fan, etc. To
indicate positions of furniture in drawing room, bed room, suitable symbols are used.
The Bureau of Indian Standards (B.I.S) has recommended conventional signs and symbols in
order to:
Plan Symbols
ARCHITECTURAL SYMBOLS
Symbol Definition
Extension lines
5 or 5 Partition type
A Window type
05 Door number
05 Room number
2 Revision marker
3 Refer to note #3
100'-0"
Elevation marker
1 Interior elevations
1,2,3 & 4 can be
4 A-5 2 seen on drawing A-5.
Direction of triangle
3 indicates elevation.
09 ConPal Dewalt
PLUMBING PIPING
7/8/05
Vent Chilled drinking DWS
water supply
Combination waste SV
and vent Chilled drinking DWR
3:48 PM
water return
Acid waste AW Hot water
Page 3
Sanitizing hot water
Indirect drain IW supply (180F)
7/8/05
Tempered water Gas – high pressure HG
TWR
return
Compressed air A
Fire line F F
3:48 PM
Wet standpipe Vacuum V
WSP
Page 4
Combination standpipe CSP Oxygen O
7/8/05
Hydrogen H Culvert pipe CP
3:48 PM
Helium HE Clay tile CT
Page 5
DI
7/8/05
Low pressure Fuel oil suction FOS
LPS
steam
High pressure Fuel oil return FOR
HPR
return
3:48 PM
Medium pressure Fuel oil vent FOV
MPR
return
Low pressure Compressed air A
LPR
Page 6
return
Boiler blow off Hot water HW
BD heating supply
Condensate or vacuum VPD Hot water
pump discharge HW
heating return
Feedwater pump PPD
discharge
09 ConPal Dewalt
AIR CONDITIONING PIPING
Refrigerant discharge
7/8/05
RD Make up water MU
3:48 PM
H
Page 7
Condenser water CWR Brine supply
return B
PIPING SYMBOLS
Gate Concentric
reducer
Eccentric
Globe reducer
Solenoid Flow
direction
Lock shield Elbow
looking up
2-Way
automatic Elbow
control looking
down
3-Way
Up/Down
automatic Pipe pitch
control up or down
Gas cock Expansion
joint
Plug cock
Expansion
Flanged loop
joint
Flexible
Union connection
Thermostat T
Cap
Thermostatic
Strainer trap
09 ConPal Dewalt 7/8/05 3:48 PM Page 9
Float and
thermostatic F&T Hose bibb
trap
Elbow
Thermometer
Tee
Pressure
gauge 'Y'
FS OS & Y
Flow gate
switch
P
Pressure
switch Shock
absorber
A Indirect IW
Aquastat waste
Sanitary S
Air vent below grade
Sanitary S
above grade
Meter M
09 ConPal Dewalt 7/8/05 3:48 PM Page 10
Storm Gas-low
below grade ST pressure G
Storm ST Gas-medium MG
above grade pressure
Vent Gas-high
HG
pressure
Combination CWV
Compressed
CA
waste & vent air
Drinking Liquid
DWS petroleum LPG
water supply
gas
Drinking DWR
water return
09 ConPal Dewalt 7/8/05 3:48 PM Page 11
Sidewalk
fire department
Dry standpipe DSP connection
FHR
Combination CSP Fire hose
standpipe rock
Automatic SP Surface
fire sprinkler mounted
fire hose FHC
Upright fire cabinet
sprinkler heads
Fire hydrant
09 ConPal Dewalt 7/8/05 3:48 PM Page 12
Baths
Whirlpool Institutional
or island
Showers
Water Closets
Urinals
Lavatories
Kitchen Sinks
Drinking Fountains or
Electric Water Coolers
DF DF DF
Floor or wall Recessed Semirecessed
Single Double
HW HWT G O
Gas Oil
Heater Tank
09 ConPal Dewalt
MATERIAL INDICATION SYMBOLS
Material Plan Elevation Section
Floor areas
Wood
7/8/05
left blank
Siding Panel Framing Finish
3:48 PM
Face Same as
Brick
plan view
Common Face or common
Page 14
Cut
Stone
Concrete Same as
7/8/05
block plan view
3:48 PM
Earth None None
Page 15
Large scale
Glass
Small scale
Plaster Stud
Same as
7/8/05
Plaster
section
Lath and plaster
3:48 PM
Structural Indicate
steel by note
Page 16
Indicate Show
Sheet metal
by note contour
flashing
09 ConPal Dewalt
Tile
Floor Wall
7/8/05
3:48 PM
9-17
Page 17
Plywood Indicated by note Indicated by note
09 ConPal Dewalt
MATERIAL INDICATION SYMBOLS (cont.)
7/8/05
Batt None Same as plan
insulation
3:48 PM
Rigid None Same as plan
insulation
Page 18
Small scale
Glass
Large scale
09 ConPal Dewalt
Gypsum Same as plan
wallboard
7/8/05
Acoustical None
3:48 PM
Page 19
Ceramic Same as plan
wall tile
Property Fence
line
Center
line
Concrete
Building
Sand
Window
Brick
Door
Paving —
Gravel
pattern
Rock
random
Wall
Water
Stone
wall
Hedge Swamp
09 ConPal Dewalt 7/8/05 3:48 PM Page 21
Slope up Grass
down
Steps
Ground
up cover
down
Benchmark EI.00.0
Trees —
Topographic
contours
deciduous evergreen
10
Shrubs —
5
deciduous evergreen
Herbaceous
plants Contour lines —
(flowers)
unaltered
altered
Same
variety
proposed
09 ConPal Dewalt
MATERIALS SYMBOLS
Earthworks
7/8/05
Concrete
3:48 PM
Cast-in-place/precast Lightweight Sand/mortar/
plaster/cut stone
Masonry
Page 22
Adobe/rammed earth Common/face Fire brick
7/8/05
Metal
3:48 PM
Aluminum Brass/bronze Steel/other metals
Wood
Page 23
Finish Rough Blocking
7/8/05
Insulation
3:48 PM
Batt/loose fill Rigid Spray/foam
Finishes
Page 24
Acoustical tile Ceramic tile – large scale Ceramic tile – small scale
7/8/05
Plan and Section Indications
Partition Indications
3:48 PM
Wood stud Metal stud Special finish face
Elevation Indications
Page 25
Brick Ceramic tile Concrete/plaster
Double hung
windows
7/8/05
3:48 PM
Casement
windows
Page 26
indicates
window
hinge
Slider
09 ConPal Dewalt 7/8/05 3:48 PM Page 27
Exterior
Interior
Bifold
door
door
door
09 ConPal Dewalt
WINDOW AND DOOR SYMBOLS (cont.)
7/8/05
Alternate double Alternate frame
hung window wall symbols
3:48 PM
Page 28
Double unit Awning and Fixed glass
casement windows hopper Door
Partition
7/8/05
Alternate
position
Openings in Masonry Wall
3:48 PM
Interior door Double Arch Pocket
Page 29
action door sliding door
Graphic Symbols
The symbols shown are those that seem to be the most
common and acceptable, judged by the frequency of use
by the architectural offices surveyed. This list can and
should be expanded by each office to include symbols
generally used by it, but not indicated here. Adoption of
these symbols as standard practice is desirable to improve
communication in the industry.
Up 17R
Stair direction symbol
111/2 T
N North point
to be placed on each
floor plan, generally in
lower right hand corner
of drawings
C C
A-3 Indicates drawing sheet A-3
on which section is shown
3 7
A-1 A-5
II
A-3
5 9
A-8 A-4
Detail References
09 ConPal Dewalt
DRAWING CONVENTIONS AND SYMBOLS (cont.)
7/8/05
461.0' Existing point 7 Wall section or elevation
elevation (plan) A-11 Reference drawing number
3:48 PM
8 Existing contours 7 Detail
26 elevation noted on
high side A-12 Reference drawing number
Page 32
0 New contours
32 elevation noted on 1302 Room/space number
high side
7/8/05
Level line
control point or
datum
3:48 PM
3 Revision
N
Project north
Page 33
h
ort
E Window type (magnetic north arrow
gn
used on plot site plan only)
Ma
123 Door number
B (if more than one door
per room subscript letters
are used)
09 ConPal Dewalt 7/8/05 3:48 PM Page 34
Dotted line
Hidden, future or existing construction to be removed
Break line
To break off parts of drawing
Linework
6' 2"
63/4"
26' 8" 2" Dot
5' 4"
1
/2"
Accent
Horizontal Vertical
Dimension Lines