Professional Documents
Culture Documents
3
Early Start (ES) is the earliest date a task can
start
Early Finish (EF) is the earliest date a task can
be completed
Late Start (LS) is the latest date a task can start
without delaying the project and date
Late Finish (LF) is the latest date a task can
finish without delaying the project end date
4
0 2 5 6 11 15
A B E
2 1 4
0 0 15 15
Start Finish
0 5 5 11 11 13
D C F
5 6 2
Forward Pass
5
ES=3
ES EF
ES=10
D
Activity A
ES=9
6
0 2 5 6 11 15
A B E
2 1 4
0 0 8 10 11 11 15 15 15
10
Start Finish
0 0 11 13 15 15
0 5 5 11
D C F
5 6 2
0 5 5 11 13 15
Backward Pass
7
LF=3
D LF=10
Activity A
LS LF LF=9
8
The purpose of backward pass is to find the float.
Float is the amount of time an activity can be
delayed or lengthened. Also called slack.
Total float: the amount of time an activity can be
delayed or extended without extending the overall
project’s completion time
9
0 2 5 6 11 15
A B E
2 1 4
0 0 8 10 11 11 15 15 15
10
Start Finish
0 0 11 13 15 15
0 5 5 11
D C F
5 6 2
0 5 5 11 13 15
10
0 2 5 6
A B
2 1
8 10 10 11
ES EF LS LF
0 2 8 10
A Float
Float A
Total Float:
TF= LF - ES – D
TF= LF – (ES+D) = LF-EF
TF= LF-D-ES= LS-ES
12
ES EF
Activity A
LS LF
13
What is the FF for activity A?
0 2 5 6
A B
2 1
8 10 10 11
What would happen if A uses its max float?
(A)EF=LF=10 (B) ES=LS=10
IF the early finish date of activity A =5
the early start date of activity B=5
FF=5-2=3
14
ES EF
Activity A
LS LF
15
Why floats are important in the critical path
method?
If an activity has a TF=0, what does this mean?
Floats determine thee criticality of an activity
Critical activities have the least amount of Float
Floats determine the critical path
16
The critical path is made of activities that cannot
be delayed without delaying the final date of the
project
If an item is on critical path, it has a zero float
The critical path is the path with longest duration
It is possible to have more than one critical path
17
0 2 5 6 11 15
A B E
2 1 4
0 0 8 10 11 11 15 15 15
10
Start Finish
0 0 11 13 15 15
0 5 5 11
D C F
5 6 2
0 5 5 11 13 15
What is the critical path?
What is the length of the critical path?
18
Critical Path Method (CPM)
CPM is a network diagramming technique used
to predict total project duration
A critical path for a project is the series of
activities that determines the earliest time by
which the project can be completed
The critical path is the longest path through the
network diagram and has the least amount of
slack or float
Slack or float is the amount of time an activity
may be delayed without delaying a succeeding
activity or the project finish date
19
Calculating the Critical Path
First develop a good network diagram
Add the duration estimates for all activities on
each path through the network diagram
The longest path is the critical path
If one or more of the activities on the critical path
takes longer than planned, the whole project
schedule will slip unless the project manager
takes corrective action
20