Re: Status of CLPOA work for Arrangement of rehabilitation and resettlement of

beneficiaries at different area of KMC


D.G./TP&DD
Dy.C.E.(C) /TP&DD
EE( C)/TP&DD
The work order for the above stated work was issued on 25.4.2017. CLPOA in its letter dated
30.10.2017 has submitted report which is attached herewith. Some activities have been done which
are given below:
Sl. Work assignment Work done % of
No. work
done
1 Survey as well as Survey of beneficiaries has been started at 0
preparation of lease deed of Br.-XV office but after few days due to
220 nos. beneficiaries at local disturbance survey work has been
Gardenreach stopped. It was decided that 218 DU’s
will be handed over on 17.4.2018 but due
to administrative cause hand over process
has been stopped.
2 Preparation of lease deed of PAN card, Adhar card etc. of beneficiaries 50
10 nos. beneficiaries at have been prepared.
Nonadanga (Ward-107)
3 Preparation of lease deed of PAN card, Adhar card etc. of beneficiaries 50
14 nos. beneficiaries at have been prepared.
Sampa Mirza Nagar‘
(Maheshtala Municipality)
4 Preparation of lease deed of CLPOA was present during hand over of 25
30 nos. beneficiaries at dwelling units to beneficiaries.
Banerjeepara (Ward-127)
Over all % of work done=(125*100/400)
=31.25
From the above table it is seen that beneficiaries survey works of Nonadanga (Ward-107) & Sampa
Mirza Nagar‘ (Maheshtala Municipality) have been completed but not a single lease deed has been
prepared.
A sum of (Rs.185880*0.3125)=Rs.58087/- may be given to CLPOA for their work if approve by
D.G./TP&DD.
This is for your information and further order pl.