Professional Documents
Culture Documents
Original 3 PDF
Original 3 PDF
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
1- Plan Cost Management (Planning Process)
- Only How you can plan and manage and control Cost
- The key benefit of this process is that it provides guidance and direction on How the project costs will
be managed throughout the project. This process is performed once or at predefined points in the
project
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
1- Plan Cost Management (Planning Process)
OUTPUTS
A- Level of accuracy
I- Rough Order of Magnitude Estimate (ROM) (Initiating Phase).... (+75% to -25%)
II- Budget Estimate (Planning Phase)……………………………….…. (+25% to -10%)
III- Definite Estimate (Executing & Closing Phases)………… (+10% to -5%) OR (±10%)
B- Units of measure
C- Control thresholds
D- Rules of performance measurement (CV & CPI & EVM as shown in Ch 7 Later)
E- Reporting formats
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
2- Estimate Costs (Planning Process)
Developing an approximation of the cost of resources needed to complete project work. The key
benefit of this process is that it determines the monetary resources required for the project. This
process is performed periodically throughout the project as needed.
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
2- Estimate Costs (Planning Process)
T&T
1- Analogous Estimating:
- Estimating the Duration or Cost of an activity or a project using Historical Data from Similar Project.
- Fast Estimating, Low Accuracy, Low Cost
- Used in case limited information
2- Parametric Estimating:
- Estimating the Duration or Cost of an activity or a project using Historical data & Other Variables as
square foot in construction or Any Unit Rate like m2 time or cost.
3- Bottom-Up Estimating:
- Estimating the Duration or Cost of an activity or a project by Aggregating the estimates of the
lower level components of the WBS.
- High Accuracy
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
2- Estimate Costs (Planning Process)
T&T
4- Three-Point Estimating:
- Estimating the Duration or Cost of an activity or a project using Three Approximate estimations.
- Considering Uncertainty & Risk
- Triangle Distribution Formula (Linear) Beta (Pert) Distribution Formula (Curve) )(اكثر دقة
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
2- Estimate Costs (Planning Process)
1- Reserve Analysis:
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
3- Determine Budget (Planning Process)
Creating a schedule model for project execution and monitoring and controlling. The key benefit of
this process is that it generates a schedule model with planned dates for completing project activities.
This process is Performed throughout the project.
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
3- Determine Budget (Planning Process)
T&T
هي ضبط مراحل تنفيذ المشروع واالنفاق علي مراحل صرف التمويل
Funding Limit االجابة تكون اما...... لو ذكر ان المالك سيوقف المشروع نتيجة مشكلة تمويل او نقص في االموال:سؤال مهم
Reconciliation OR Reschedule the Project Activities
OUTPUTS
1- Cost Baseline:
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
4- Control Cost (M&C Process)
Monitoring the status of the project to update the project Cost & managing changes to the Cost
baseline. The key benefit of this process is that the Cost baseline is maintained throughout the project.
This process is Performed throughout the project.
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
4- Control Cost (M&C Process)
Evaluate the Variation to Schedule & Cost Baselines using performance measurements
A- Planned Value (PV) قيمة ماهو مخطط له بالمشروع عند زمن معين
B- Earned Value (EV) قيمة ما تم تنفيذه واعتماده بمستخلص بالمشروع عند زمن معين
C- Actual Cost (AC) قيمة فعلية لما تم صرفه بالمشروع عند زمن معين
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
4- Control Cost (M&C Process)
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
4- Control Cost (M&C Process) BAC… Budget At Completion
ETC.… Estimate To Completion
T&T (Data Analysis)
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
4- Control Cost (M&C Process)
T&T
A measure of the cost performance that must be achieved with the remaining resources in order to
meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work
to the budget available.
Remaining Works (BAC – EV) >1 Harder to Complete (Bad)
TCPI =
Remaining Fund (BAC – AC) OR (EAC – AC)
<1 Easier to Complete (Good)
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Chapter 7 – Cost Management
4- Control Cost (M&C Process)
T&T
ETC = EAC – AC
The difference between the budget at completion and the estimate at completion.
0 On Planned Cost
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com
Dr. Ahmed AbdelHady - PMP Preparation Course (6th Edition)
Chapter Pages – PMBOK 6th Edition Status
1- Introduction 1 - 36 Done
2- Projects Environment 37 - 50 Done
3- PM Roles 51 - 68 Done
4- Integration 69 - 128 Done
5- Scope 129 - 172 Done
6- Schedule 173 - 230 Done
7- Cost 231 - 270 Done
8- Quality 271 - 306 Not Yet
9- Resource 307 - 358 Not Yet
10- Communication 359- 394 Not Yet
11- Risk 395- 458 Not Yet
12- Procurement 459- 502 Not Yet
13- Stakeholder 503 - 536 Not Yet
Dr. Ahmed AbdelHady - PMP Course 6th Edition – 00966-541541970 – 002-01093674327 – Ahmedah251@gmail.com