More than the cost, track regrading work to be taken up under running
traffic, this may lead to unsafe condition and accident prone. In addition traffic
will run at restricted speed for a period of 4 months. During these four months
all the traffic has to pass under Stop Dead and Proceed with S.R of 20 Kmph.
This will affect the punctuality of trains very badly because of heavy traffic and
prestigious trains running on this line such as Rajadhani express , Duronto
express and goods traffic towards Guntakal/Wadi, the justification for not
regrading to flatter than 1 in 260 was certified by the concerned
CE/Construction, who is executing the project.
(G.Brahmananda Reddy)
Chief Engineer (P&D)/SCR,
Secunderabad
Sub: Guntakal Division – Doubling of track between Guntakal – Kalluru Jn (41
Kms) – Proposed Yard arrangements at Venkatampalli station yard–
Condonation of Infringing Gradients – reg.
JUSTIFICATION
----------------------
Total cost =Rs. 931.40Lakhs
---------------------
More than the cost, track to be carried out under traffic conditions, this
may lead to unsafe condition and accident prone. The process demand
imposition of speed restriction such as Stop Dead and Proceed with 20 Kmph
for a period of 4 months. This will affect the punctuality of trains very badly
and this section is passing prestigious trains like Rajadhani & Doronto
express and also heavy mineral goods traffic towards Guntakal / Wadi.
(Rakesh Yadav)
Chief Engineer/C-I/SC
Secunderabad
CHECKLIST FOR APPLICATION FOR THE CONDONATION OF INFRINGEMENT TO
THE SCHEDULE OF DIMENSIONS (INCLUDING RE CASES)
(Rakesh Yadav)
Chief Engineer/C-I/SC
Secunderabad
Office of the
Chief Administrative officer
Rail Nirman Nilayam,
South Central Railway
Secunderabad-500 071
(Rakesh Yadav)
Chief Engineer/C-I/SC
Secunderabad