You are on page 1of 98

WELL CONTROL

EXERCISE # 1
1. What mud weight is required to balance a formation pressure of 2930 psi at 5420 ft
TVD?

___________ppg

2. If the fluid level dropped 550 ft in a 9600 deep hole containing 10.6 ppg mud, what would
the hydrostatic at bottom be?

___________psi

3. Bottom hole pressure is reduced the most by gas cut drilling mud when:

a. The gas is near the surface


b. The gas is at or near the bottom
c. The gas is about halfway up the well bore
d. All are about the same

4. After a round trip at 8960 ft with 10.9 ppg mud, we kick the pump in and start to circulate.
An increase in flow was noticed and the well was shut in with 0 psi on the drill pipe and
300 psi on the casing. What kill mud is required? (no float in the drill string)

___________ppg

5. What was most probable in causing the influx or well kick in the last question?

a. Abnormal pressure was encountered


b. The mud weight was not high enough to contain formation pressure
c. It was swabbed in or the hole was not properly filled while pulling out
d. It is impossible to tell

6. Which of the following circumstances would increase the chance of swabbing in a kick?

a. High pulling speed


b. Mud properties with high viscosity and high gels
c. Tight annulus BHA/hole clearance
d. Mud density in use is close to formation pressure

7. In which of the following cases would you be most likely to swab in a kick?

a. When the bit is pulled up into the casing


b. When the first few stands are being pulled off bottom
c. About half way up the well
WELL CONTROL

8. When drilling with 10.3 ppg mud at 11600 ft TVD the annular loss is estimated at 195 psi.
What is the BHCP?

_________psi

9. You are pulling out of hole. Two x 93 ft stands of 8" drill collars have been stood back in
the derrick. The displacement is 0.0538 bbls. / ft. According to your Assistant Driller, 10
bbls should be pumped into the well. It only takes 10 bbls to fill the hole. (Answer yes or
no to each question)

a) Are the calculations correct?


b) Have you taken a 5 bbls influx?
c) All Ok, keep going

10. You have taken a kick and shut the well in. The active tank while drilling contained 250
bbls. And the mud return line to the pits contains 25 bbls.
The tank now contains 300 bbls. How many barrels of mud have been displaced from the
well?

a) 0 bbls
b) 25 bbls
c) 50 bbls
d) 275 bbls

11. The Fracture Gradient of an open hole formation at 3680 ft. is 0.618 psi/ft. The drilling
mud currently in use is 9.8 ppg. Approximately how much Surface Casing Pressure can
be applied to the well before this formation breaks down?

a) 350 psi
b) 2275 psi
c) 630 psi
d) 400 psi

12. A gas kick is being circulated out. At the time the gas reaches the casing shoe (4250 ft.
TVD), the pressure at the top of the bubble is 3000 psi. If the original mud weight is 12
ppg, what is the casing pressure at the surface? (Hole TVD 7000ft)

a) 348 psi
b) 442 psi
c) 1368 psi
d) 2625 psi
WELL CONTROL

Questions 13-14 are based on the following information:

13 3/8” surface casing is set and cemented at 4250 ft. (TVD). The cement is drilled out
together with 15 ft. of new hole, using a 11 ppg mud. A leak off test pressure of 800 psi is
determined. (Hole TVD 7000ft)

13. What is the formation fracture gradient?

a) 0.188 psi / ft
b) 0.686 psi / ft
c) 0.760 psi / ft
d) 0.384 psi / ft

14. What is the maximum allowable annular surface pressure for 12.3 ppg mud in use at
7350ft. TVD :

a) 373 psi
b) 511 psi
c) 884 psi
d) 1982 psi

15. How often should the MAASP be recalculated?

a) After every bit change


b) After a change in mud weight
c) After every 500 ft. drilled

16. Calculate the equivalent circulating density in the following circumstances:

Circulating pressure = 3100 psi

Pressure losses:
Surface equipment = 20 psi
Drill string = 930 psi
Nozzles = 1800 psi
Annulus = 350 psi

Drilled depth: 12,300 ft. (11,500 ft. TVD)


Mud weight: 11.4 ppg

ECD is:

a) 10.8 ppg
b) 12.0 ppg
c) 11.4 ppg
d) 12.3 ppg
WELL CONTROL

17. Drill pipe capacity = 0.0178 bbls/ft


Drill pipe metal displacement = 0.0082 bbls/ft
Average stand length = 93 ft

Calculate :

a) Mud required to fill the hole per stand when pulled „dry‟ (bbls per stand)

b) Mud required to fill the hole per stand when pulled „wet‟ (bbls per stand)

18. You are determining your kill rate pressure and bringing your pump rate up to a pre-
determined 30 SPM by holding the shut in casing pressure constant. You have got a kick
in the well of 220 psi shut in drill pipe pressure. At 30 SPM your drill pipe circulating
pressure is 1060 psi. Calculate the slow circulating rate pressure loss.

a) 700 psi
b) 770 psi
c) 800 psi
d) 840 psi

19. Overburden pressure is:

a. the pressure exerted at any given depth by the weight of the rocks and
sediments.
b. the pressure exerted at any given depth by the weight of the sediments, or
rocks and the weight of the fluids that fill the pore spaces in the rock.
c. the pressure exerted at any given depth by the weight of the rocks.
d. the pressure exerted at any given depth by the weight of the fluid in the pore
space of the rocks.

20. Of all the pressure losses in the circulating system, which one acts only on the
borehole?

A. The pressure loss across the nozzles.


B. The pressure loss in the surface lines.
C. The pressure loss in the drill stem.
D. The pressure loss in the annulus
WELL CONTROL

21. At the start of a trip out of the hole for a bit change, the first 20 x 93 ft stands of
pipe are pulled from the hole wet with no fill up. Using the following data calculate
the reduction in bottom hole pressure?

DP. Metal Displacement = .00764 bbls/ft


DP. Capacity = .01776 bbls/ft
Casing Capacity = .0758 bbls/ft
Mud Weight = 10 ppg

A. 48 psi
B. 483 psi
C. 600 psi
D. 683 psi

22. At the start of a trip out of the hole for a bit change, the first 10 x 93 ft stands of pipe are
pulled from the hole dry with no fill up. Using the following data calculate the reduction in
bottom hole pressure?

DP. Metal Displacement = .00764 bbls/ft


DP. Capacity = .01776 bbls/ft
Casing Capacity = .0758 bbls/ft
Mud Weight = 12 ppg

A. 650 psi
B. 6 psi
C. 65 psi
D. 130 psi

23. Select the two things that are needed to accurately determine an Initial Circulating
Pressure?

A. drilling pump pressure and mud weight


B. shut in drill pipe pressure and mud weight
C. slow circulating rate pressure and final circulating pressure
D. slow circulating rate pressure and shut in drill pipe pressure

24. Select the three things that are needed to accurately determine a Final Circulating
Pressure?

A. drilling pump pressure, drilling mud weight and kill mud weight
B. shut in drill pipe pressure, drilling mud and kill mud weight
C. slow circulating rate pressure, drilling mud weight and kill mud weight
D. slow circulating rate pressure, drilling mud weight and final circulating pressure
WELL CONTROL

25. The Drillers Method of Well Control normally requires how many circulations to kill
a well?

A. one circulation
B. two circulations
C. three circulations
D. four circulations

26. The Drillers Method of Well Control will normally result in:

A. a higher bottom hole pressure than the wait and weight method.
B. a lower bottom hole pressure than the wait and weight method.
C. a higher surface pressure than the wait and weight method
D. a lower surface pressure than the wait and weight method.

27. During a well-killing operation, a common way to bring the pump up to kill rate
without changing bottom hole pressure is to:

A. keep SIDP constant at the original shut-in value by opening the choke.

B. keep SIDP constant at the original shut-in value by opening the choke
and bringing the pump up to kill-rate speed.

C. keep SICP constant at the original shut-in value by opening the choke
and bringing the pump up to kill-rate speed. ensure that casing pressure
and standpipe pressure rise consistently together.

28. The usable accumulator fluid for a 10 gallon accumulator bottle on a 3,000 psi
system with 1,000 psi precharge is approximately:

A. 9 gallons.
B. 7 gallons.
C. 5 gallons.
D. 3 gallons
WELL CONTROL

29. Use the following well data to calculate the different influx heights:

Drill collar length: 700 ft


DC - OH Capacity .0292 bbl/ft
DP - OH Capacity .0459 bbl/ft

Kick size (bbls) Height (ft)

a. 10 ________
b. 20 ________
c. 30 ________
d. 40 ________

30. Using the following data, calculate the influx gradients:

SICP SIDPP Mud Wt Height of Influx Answer


800 720 11.5 400
950 600 10.6 840
680 550 10.2 350

31. Using the following well data calculate Kill mud weights:

SICP (psi) SIDPP (psi) Mud Wt (ppg) TVD (ft) Answer


600 450 10 9500
850 690 11 12000
780 570 10.5 11200
700 300 14 13000

32. Using the following well data calculate the Annular Pressure Losses:

BHCP (psi) Mud Wt (ppg) Depth TVD (ft) Answer


6000 11.6 9450
2600 9.8 5000
5700 10 10000

33. Using the following data, calculate the new pump pressure:

Old pump pressure Old Mud weight New mud Weight Answer
2500 16 17.5
1700 10 14
WELL CONTROL

34. Using the following data, calculate the new pressure:

Old SPM Old pressure New SPM Answer


40 200 80
20 400 55
35. Convert the following pressure gradient to mud weight:

Gradient (psi/ft) Mud Wt (ppg)


.56
.81

36. Change the ECD to BHCD:

ECD (ppg) Depth TVD (ft) BHCD (psi)


12.5 8000
10.2 11400
9.4 12500

37. What would be the annular velocity around the drill collars:

Pump output (bbl/min) DC – OH capacity Annular Velocity


(bbl/ft) (ft/min)
6 0.3

38. What would be the annular velocity around the drill pipe if the pump output is 6 bbl/min
and the DP – OH capacity is .0459 bbl/ft ?

Answer: ft/min
WELL CONTROL

39. At the start of a trip out of the hole for a bit change, the first 10 x 93 ft stands of drill pipe
are pulled from the hole wet.
Using the following data, calculate the reduction in bottom hole pressure.

Mud weight: 12 ppg


Casing capacity: .0758 bbl/ft
DP capacity: .01776 bbl/ft
DP metal displacement: .00764 bbl/ft

Answer: psi

40. At the start of a trip out of the hole for a bit change, the first 20 x 93 ft stands of drill pipe
are pulled from the hole dry.
Using the following data, calculate the reduction in bottom hole pressure.

Mud weight: 12 ppg


Casing capacity: .0758 bbl/ft
DP capacity: .01776 bbl/ft
DP metal displacement: .00764 bbl/ft

Answer: psi

41. While tripping out of the hole, the trip tank is turned off and a flow check is made when
the drill collars are at the rotary table.
The last 400 feet of drill collar are pulled from the hole dry with no fill up.
Using the following data answer the questions below:

DC metal displacement: .054 bbl/ft


DC capacity: .00768 bbl/ft
Casing capacity: .0758 bbl/ft
Mud weight: 12 ppg

a. What is the maximum level drop in the annulus?

Answer: ft

b. What is the reduction in bottom hole pressure?

Answer: psi
WELL CONTROL

42. Using the following data, calculate the loss in hydrostatic pressure if the casing was not
kept full and the float failed while running casing in the hole.

Casing capacity Annular capacity Differential height Mud Wt Anwser (psi)


.0754 bbl/ft .067 bbl/ft 1000 ft 10
.0754 bbl/ft .067 bbl/ft 800 ft 12

Formula : Mud gradient x Differencial Height x Casing capacity


(Casing capacity + Annular capacity)

43. An influx in oil based mud is not possible to detect when it is first occurring because gas
going into solution will cause no associated pit increase at the surface.

TRUE or FALSE

44. When a kick is taken in oil based mud and the well pressure have stabilized, the SICP
will be:

a. Higher than the same kick in water – based mud


b. Lower than the same kick in water – based mud
c. The casing pressure would read the same in oil or water – based mud

45. Gas that is in solution will migrate in the annulus in a vertical well at the same rate as
free gas.

TRUE or FALSE

46. When drilling a deep high pressure high temperature well using oil base mud, a gas
condensate influx enters the well bore undetected.
If the critical bubble pressure was about 800 psi, how far from the surface would it be
when it started to break out and become free gas if the mud weight in use is 12 ppg.

a. 800 ft
b. 1282 ft
c. 9600 ft
d. 2182 ft
WELL CONTROL

EXERCISE # 2
1. Which gauge must be used to read drill pipe pressure while taking SCR‟s?

a. drill pipe gauge on driller‟s panel


b. casing gauge on driller‟s panel
c. drill pipe gauge at the choke panel
d. casing gauge at the choke panel

2. A 13 3/8 casing is set at 3126 ft TVD, drilled out and tested with 10.2 ppg mud to
670 psi surface pressure. What is the formation fracture gradient calculated from
the test?

a. 0.564 psi/ft
b. 0.678 psi/ft
c. 0.74 psi/ft
d. 0.841 psi/ft

3. What would be the MAASP with 11.4 ppg mud in the hole? (use data from Q-2)

a. 400 psi
b. 461 psi
c. 500 psi
d. 560 psi

4. What mud weight would have a MAASP of 250 psi? (use data from Q-2)

a. 11.56 ppg
b. 12.69 ppg
c. 11.85 ppg
d. 12.21 ppg

5. What happen to MAASP as MW increases?

a. increase
b. decrease
c. stay the same
d. impossible to say

6. What do you consider as essential for an accurate formation test? (4 answers)

a. a list of mud additives


b. a known mud yield point
c. accurate TVD for the casing shoe
d. Small volume, high pressure pump
e. The same known mud weight in and out
f. Cement recipe
g. An accurate surface pressure gauge
h. A long open hole section
WELL CONTROL

7. What is the mud weight that we would expect to use to balance normal formation
pressure?

a. 7.56 ppg
b. 8.00 ppg
c. 8.94 ppg
d. 10.2 ppg

8. What is primary well control?

a. the use of drilling fluid to balance formation


b. the use of BOP to secure the well
c. the use of annular preventer to close the well
d. the use of cement plug

9. Swabbing will cause the loss of primary well control?

a. true
b. false

10. When drilling top hole, which of the following are considered to be good drilling
practices? (3 answers)

a. ROP will be maximised


b. MW must be with .5 ppg of plan
c. Pump out of hole while tripping
d. Drill a pilot hole
e. Pump a slug before tripping
f. Control ROP
g. Minimise losses to 15 bbl/hr

11. If the level of 12.5 ppg mud fell by 560 ft in a 6543 ft TVD well, what would be the
reduction in BHP?

a. 364 psi
b. 244 psi
c. 448 psi
d. 732 psi

12. What is the reduction in bottom hole pressure if a 5 bbl lightweight pill of 7.5 ppg is
spotted around 4 ¾ drill collars (total length 460 ft) in a 6 1/8 hole containing OBM
of 11.9 ppg?

a. 50 psi
b. 120 psi
c. 95 psi
d. 79 psi
WELL CONTROL

13. Every kick should be handled as a gas kick?

a. true
b. false

14. For a Soft shut-in, the choke is left closed while drilling

a. true
c. false

15. Calculate the rate of gas migration if SIDDP has increased by 50 psi in 15
minutes? MW: 10.5 ppg MD: 7500 ft TVD:7000 ft

a. 366 ft/hr
b. 455 ft/hr
c. 244 ft/hr
d. 575 ft/hr

16. What is the casing pressure when a 5 bbl gas bubble at 2200 psi in 11.6 ppg mud
reaches the casing shoe at 3126 ft TVD?

a. 569 psi
b. 314 psi
c. 456 psi
d. 297 psi

17. A 9000 ft well is shut in with 200 psi SICP and 0 PSI SIDPP. What is the KMW if
OMW is 11.6 ppg?

a. 12.4 ppg
b. 12.03 ppg
c. 12.4 ppg
d. 11.6 ppg

18. W&W method gives lower shoe pressure in all cases

a. true
b. false

19. W&W method results in a lower shoe pressure if drill string volume is less than the
open hole volume minus the influx volume?

a. true
b. false
WELL CONTROL

20. Surface pressures are always lower if the W&W method is used compared to the
Driller‟s method?

a. true
b. false

Answer true or false for these statements on the W&W method:

21. Casing pressure must be kept constant during the second circulation

a. true
b. false

22. The pumps are brought up to speed keeping the drill pipe pressure constant

a. true
b. false

23. Surface annulus pressure is lower than with the driller‟s method

a. true
b. false

24. Bottom hole pressure is maintained constant

a. true
b. false

25. The well is dead when you have reached FCP

a. true
b. false

26. SIDPP should be zero once you have reached FCP

a. true
b. false

27. The W&W method is preferred if rapid gas migration is expected

a. true
b. false

28. The W&W is preferred as MAASP is critical and open capacity is greater than the
drill string capacity

a. true
b. false
WELL CONTROL

29. The choke operator maintain drill pipe pressure constant while circulating KMW
from surface to bit. What happen to BHP?

a. increase
b. decrease
c. stay the same

30. What is the BHCP if the MW is 10 ppg, TVD: 12500ft and APL: 400 psi?

a. 6200 psi
b. 6900 psi
c. 7300 psi
d. 7700 psi

31. The poorboy degasser (mud/gas separator) is identified by its design


dimensions. Which two of the given dimensions determine the operating
limit of the pressure build up in the separator?

a Body height.
b Inlet line inside diameter.
c Vent pipe inside diameter.
d Height of the U-tube.
e Inside diameter of the U-tube.
f Vent pipe height.
g Body inside diameter.

32. You are using a cup type tester. The mandrel outside diameter is 6 3/4"
and the casing inside diameter is 12.615".
Calculate the tension force created on the drill pipe above the cup tester
when a 3000 psi test pressure is applied.

a 267,000 lbs
b 167,500 lbs
c 67,500 lbs

33. A larger pit gain will give a higher SIDPP, resulting in a higher kill mud weight.

a. True
b. Maybe
c. Sometimes
d. False
e. Always
WELL CONTROL

34. A larger pit gain will result in higher SIDPP and SICP.

a. True
b. Maybe
c. Sometimes
d. False
e. Always

35. A larger pit gain will result in a higher SICP, but theSIDPP will remain the same if
the kick is big or small.

a. True
b. Maybe
c. Sometimes
d. False
e. Always

36. After circulating out a kick using the driller's method, is the SICP and SIDPP about
the same?

a. Only if the influx is a fluid.


b. Never
c. Yes
d. No
e. Only if the influx was gas.

37. When killing a well using the wait and weight method, what will happen to the mud
pit volume the moment the gas is passing through the choke?

a. The pit volume starts increasing.


b. The pit volume starts to drop.
c. The pit volume will stay the same from now on.
d. The pit volume will rise and fall erratically.
e. The pit volume should not be monitored when killing.

38. What is the value of the Maximum Allowable Annular Surface Pressure usually
determined by?

a. The maximum bottom hole pressure that can be sustained.


b. The slow circulating rate.
c. The formation strength at the casing shoe.
d. The temperature of the influx fluid.
e. The annular pressure loss.
WELL CONTROL

39. When killing a well using the driller's method, what would happen to the mud pit
volume during the second circulation?

a. The pit volume decreases.


b. The pit volume stays the same.
c. Increase only due to added weight material.
d. Increase initially and decreases in the end.
e. Decreases at first and increases in the end.

40. What action would you take if while circulating out a kick the choke line parted?

a. Stop pump and close the choke.


b. Stop pump and close the HCR.
c. Continue to kill if the influx is past the shoe.
d. Stop the pump and close the shear rams.
e. Start killing with the volumetric method.

41. Whilst circulating out a kick the mud pump fails. What is the first thing to do?

a. Fix the pump as soon as possible.


b. Change over to the other pump.
c. Shut the well in.
d. Start diverting.
e. Start bullheading.

42. If total losses occurred while drilling with water based mud, what would you do?

a. Continue drilling blind.


b. Stop drilling, fill the hole with water.
c. Stop drilling, shut the well in.
d. Spot a hivis pill acroos the shoe.
e. Set a barite plug.

43. On a surface stack; what would happen if when bringing the pump up to kill speed
the casing pressure was allowed to increase above the shut in casing pressure?

a. BHP would possibly exceed formation fracture gradient.


b. BHP would cause more influx to enter the well bore.
c. It doesn't matter at all if SIDPP is constant.
d. It is OK if SIDPP also rises the same amount.
e. Only while using wait and weight method does it matter.
WELL CONTROL

44. Mud weight is 12.5 ppg. SIDPP=800 psi, SICP=1025 psi. The annulus capacity is
.0292 bbl/ft. The influx volume is 12 bbl.
What is the gradient of the influx?

a. .1520 psi/ft
b. .1502 psi/ft
c. .1205 psi/ft
d. .1025 psi/ft
e. .0521 psi/ft

45. TD=12000', MW in the hole=13.5 ppg, Pitgain 50 bbl, SIDPP=600 psi. Ann. cap.
with 450' of DC= .0778 bbl/ft. DP/OH cap= .1215 bbl/ft. Influx gradient = .1 psi/ft
What is the SICP?

a. 642 psi
b. 945 psi
c. 573 psi
d. 580 psi
e. 752

46. SIDPP increases with the size of the kick.

a. True
b. False

47. A driller is circulating a kick out and has reached hisfinal circulating pressure of 850
psi with 30 SPM. If this driller speeds the pump up to 35 SPM, and the
toolpusher keeps 850 psi on the drillpipe by adjusting the choke, the bottom hole
pressure will:

a. Decrease by 307 psi


b. Increase by 253 psi
c. Stay constant at 850 psi
d. Increase by 140 psi
e. Decrease by 405 psi

48. Which of the following functions is activated by the manifold pressure of the
accumulator unit?

a. Ram preventers only.


b. Hydrauliccally operated choke and kill line valves.
c. Rams and hydraulic operated choke and kill line valves.
d. Annular preventers
e. All stack functions.
WELL CONTROL

A deviated hole has a measured depth of 12,320 ft. (TVD 10429 ft). 9 5/8”, 47 lb/ft.
casing in set at a measured depth of 9750 ft. (9200 ft. TVD). 11.4 ppg mud is in use when the
well kicks and is closed in.

Shut in Drill Pipe Pressure : 750 psi


Shut in Casing Pressure: 1050 psi
Kick volume: 15 bbls.

Pre- recorded information is as follows :


Fracture mud weight = 14.4 ppg
Capacity of 19.5 lbs. Drill pipe = 0.01776 bbl/ft.
Capacity of 9 5/8” J55 casing = 0.0732 bbl/ft.
Slow Circulating Rate Pressure = 850 psi

49. The maximum allowable annular surface pressure is rounded off to :

a) 1370 psi
b) 1480 psi
c) 1435 psi
d) 1415 psi
50. The kill mud weight required to balance the formation pressure is:

a) 13.1 ppg
b) 12.6 ppg
c) 12.8 ppg
d) 12.2 ppg
51. The kill mud weight with a Safety Margin of 100 psi is:

a) 13.4 ppg
b) 13.0 ppg
c) 12.4 ppg
d) 11.8 ppg

52. The initial circulating pressure is:

a) 1400 psi
b) 1600 psi
c) 1900 psi

53. The final circulating pressure (using kill mud weight with a 100 psi Safety Margin is) :

a) 850 psi
b) 970 psi
c) 920 psi
d) 1050 psi
WELL CONTROL

54. The Fracture Gradient of an open hole formation at 3680 ft. is 0.618 psi/ft. The drilling
mud currently in use is 9.8 ppg. Approximately how much Surface Casing Pressure can be
applied to the well before this formation breaks down?

a) 350 psi
b) 2275 psi
c) 630 psi
d) 400 psi

55. In the area where local legislation requires that BOP equipment must be rated so that
maximum anticipated formation pressures do not exceed 75% of BOP equipment pressure
ratings, what is the Minimum Acceptable rating for equipment to be used in drilling Normally
Pressured Formation to 16,000 ft. TVD?

a) 2,000 psi BOP Equipment


b) 3,000 psi BOP Equipment
c) 5,000 psi BOP Equipment
d) 10,000 psi BOP Equipment
e) 15,000 psi BOP Equipment
WELL CONTROL

EXERCISE # 3

Use the Well Data to answer the questions. Each question has only one correct
answer.

WELL DATA

Well Depth 10,000 ft TVD


10,000 ft MD
Marine riser 800 ft
Choke line 820 ft capacity = 0.0087 bbls/ft
Bit size 8.5”
Drill Pipe 5” OD. 19.5 lbs/ft
Capacity = 0.01776 bbls/ft
HWDP 5” OD. 50 lbs/ft x 850 ft
Capacity = .0088 bbls/ft
Drill Collars 61/2” x 213/16” x 750 ft
Capacity = 0.00768 bbls/ft
Casing 95/8”, 47 lb/ft. P110 8.681” ID
100% Internal yield = 10,900 psi
Set at 7,500 ft TVD
Mud weight in use 15 ppg.
Pump output 0.119 bbls/stk

PUMP PRESSURE

While Drilling 2600 psi at 90 spm (APL = 310 psi)


Slow Pump Rate Up Riser 270 psi at 30 spm (APL = 75 psi)
Slow Pump Rate Up CL 360 psi at 30 spm

ANNULAR VOLUMES

Drill pipe - Casing Drill pipe - Casing = 0.0505 bbls/ft


Drill pipe - Open hole = 0.0459 bbls/ft
Drill collars - Open hole = 0.0292 bbls/ft
Drill pipe – riser = 0.336 bbls/ft
Active surface volume = 320 bbls

WELL CONTROL DATA

SIDPP SIDPP = 500 psi


SICP = 720 psi
GAIN = 10 bbls
FRACTURE GRADIENT AT SHOE = .91psi/ft
WELL CONTROL

1. What is the total capacity of the drill string?

A. 150 bbls
B. 162 bbls
C. 197 bbls
D. 180 bbls

2. Calculate the total annular capacity with the pipe on bottom while controling
the well?

A. 482.2 bbls
B. 446.5 bbls
C. 547.5 bbls
D. 627.6 bbls

3. What is the surface to bit time with the pump running at 80 spm?

A. 17 minutes
B. 25 minutes
C. 32 minutes
D. 39 minutes

4. Calculate bit to surface time (bottoms up) at 80 spm?

A. 58.5 minutes
B. 46.8 minutes
C. 60.3 minutes
D. 51.5 minutes

5. What kill mud is required to balance formation pressure?

A. 13.4 ppg
B. 13.0 ppg
C. 12.4 ppg
D. 16.0 ppg

6. The ICP (initial circulating pressure) at 30 spm will be approximately?

A. 270 psi
B. 770 psi
C. 990 psi
D. 1200 psi
WELL CONTROL

7. The FCP (final circulating pressure) at 30 spm will be approximately?

A. approximately 800 psi


B. approximately 390 psi
C. approximately 500 psi
D. approximately 290 psi

8. After reaching FCP it is decided to increase the pump speed to 40 spm.


What would happen to BHP if the drill pipe pressure is held constant at the
original FCP value?

A. increase by about 225 psi


B. decrease by about 225 psi
C. remain constant because drill pipe pressure was not changed
D. increase by about 500 psi

9. What is the hydrostatic pressure at the bottom of the hole before the kick?

A. 5800 psi
B. 6800 psi
C. 7800 psi
D. 6240 psi

10. What is the ECD on bottom while drilling?

A. 15.0 ppg
B. 15.5 ppg
C. 16.0 ppg
D. 16.5 ppg

11. At 80 spm what is the annular velocity around the drill collars?

A. 412 ft/min
B. 210 ft/min
C. 506 ft/min
D. 321 ft/min

12. What is the maximum allowable mud weight?

A. 17.5 ppg
B. 16.5 ppg
C. 18.0 ppg
D. 19.0 ppg
WELL CONTROL

13. What is the approximate length of the influx?

A. 1027 ft
B. 850 ft
C. 653 ft
D. 342 ft

14. The gradient of the influx is about?

A. .137 psi/ft
B. .320 psi/ft
C. .465 psi/ft
D. .433 psi/ft

15. How many strokes to go from ICP to FCP?

A. 1282 stks
B. 1363 stks
C. 1680 stks
D. 1538 stks

16. How many strokes will it require to go from bit to shoe?

A. 5364 stks
B. 4122 stks
C. 1658 stks
D. 858 stks

17. How long will it take to go from bit to shoe at a pump speed of 30 spm?

A. about 214 minutes


B. about 29 minutes
C. about 157 minutes
D. about 55 minutes

18. At 30 spm what is shoe to surface travel time?

A. about 96 minutes
B. about 34 minutes
C. about 214 minutes
D. about 76 minutes
WELL CONTROL

19. If the casing shoe is tested with 12.5 ppg mud in the hole, how much
pressure is applied at the surface to give a fracture gradient of .91 psi/ft?

A. 1250 psi
B. 1500 psi
C. 2000 psi
D. 1950 psi

20. What would be the new MAASP once the well has been killed?

A. 685 psi
B. 1638 psi
C. 700 psi
D. 585 psi

21. At 30 spm how long will it take to pump kill mud to the bit?

A. 157 mins
B. 214 mins
C. 45 mins
D. 76 mins

22. If a 100 psi safety margin is included in the kill mud weight, what would the
new kill weight be?

A. 15.5 ppg
B. 16.0 ppg
C. 15.4 ppg
D. 16.2 ppg

23. What would be the approximate pressure step down from ICP to FCP in
psi/100 strokes.

A. 30 psi/100 stks
B. 35 psi/100 stks
C. 50 psi/100 stks
D. 66 psi/100 stks
WELL CONTROL

Answer the following gauge questions as the well is killed using the Drillers
method.
TO TA L S TR O K E S
90 0 1000 1 100 900 10 00 1100
80 0 1200
50 800 1 200
70 0 1300 700 13 00
600 6 00
PSI 1400 PSI 14 00
5 00 15 00 5 00 1 500
400 160 0 4 00 1600

3 00 1700 300 1 700


200 1 800 200 18 00
1 00 1900 10 0 1 900
PUMP SPEED
D R ILLP IP E P R E S S U R E 30 C A S IN G P R E S S U R E

770 630

C H O KE
O P EN P O S IT IO N C LO S E

24. The kill operation has started. This is what the choke control console shows.
What should you do?

A. open the choke a little


B. close the choke a little
C. increase the pump speed
D. decrease the pump speed
E. nothing everything looks alright
F. Possible plugged nozzle
G. Possible choke wash out
H. Possible choke plugging

TO T A L S TR O K E S
900 100 0 1 100 900 100 0 11 00
800 120 0
580 800 120 0
70 0 130 0 70 0 130 0

60 0 60 0
PSI 140 0
PSI 1400
5 00 1500 5 00 1 500

40 0 16 00 40 0 160 0

300 170 0 300 170 0


2 00 1800 2 00 1 800
1 00 1 900 100 1 900
PUMP SPEED

D R ILLP IP E P R E S S U R E 30 C A S IN G P R E S S U R E

600 600

CH O KE
O PE N P O S ITIO N C LO S E

25. Pit room calls up to confirm a .5 bbl rise in the level. What should you do?
A. open the choke a little
B. close the choke a little
C. increase the pump speed
D. decrease the pump speed
E. nothing everything looks alright
WELL CONTROL

TO TA L STR O KES
900 1000 1100 900 1000 1100
8 00 1200
3250 800 1200
700 1 300 700 1300
600 600
P SI 1400
PS I 1400
500 1500 500 1500

400 1600 400 1600

300 1700 300 1700


200 1800 200 1800
100 1900 100 1900
PU M P SPEED
D R ILLP IPE PR E SSU R E 30 CASIN G PR ESSU R E

770 1 0 20

CH OK E
O PEN PO SITIO N C LOS E

26. The pit levels are still reported to be increasing slightly. This is what you see
on the panel.

A. open the choke a little


B. close the choke a little
C. increase the pump speed
D. decrease the pump speed
E. nothing everything looks alright
WELL CONTROL

EXERCISE # 4

1. Most kicks have been caused by the failure of drilling crews to:

a. Properly install and test BOP equipment


b. Keep mud weight high enough
c. Make sure that hole takes the proper amount of fluid during a trip

2. What is the correct action if the hole does not take the proper amount of fluid while
tripping out of the hole?

a. Observe, watch for flow, and if there is none, pull out of hole
b. Stop, spot a high viscosity pill, then pump out of hole
c. Go back to bottom, circulate bottoms up and evaluate the problem
d. Check for gas cut mud at the surface

3. The most important rule in well control is to:

a. Know how to take SIDPP with a float in the string


b. Shut the well in quickly and properly with the least amount of gain
c. Circulate the kick out using constant circulating pressure and pump strokes
d. Hold 200 psi extra back pressure with the hydraulic choke while circulating out
the kick

4. A large percentage of all kicks have been caused by:

a. Abnormally pressured formations


b. People not reacting or handling situations properly
c. BOP equipment failure
d. Lost circulation

5. The mud weight required in the hole to balance normal formation pressure would have to
be:

a. 8.3 ppg
b. 10.3 ppg
c. 8.9 ppg
d. 9.5 ppg

6. Mud monitoring equipment such as P.V.T. and pit alarm systems, trip tanks and trip
records should be used:

a. Any time the well is open


b. Any time fluid is circulated through the mud pit
c. When abnormal formation is expected
d. When drilling 12 ¼ hole
WELL CONTROL

7. Every kick should be handled as a gas kick

a. True
b. False

8. The first reliable indication that a kick is in progress is:

a. No warning
b. An increase in pump pressure
c. An increase in mud flow, mud volume and a decrease in pump pressure
d. Reduced drilling rate

9. When a gas kick is being circulated up a well, the surface pit volume will:

a. increase
b. decrease
c. stay the same

10. Final circulating pressure is reached when:

a. The influx is circulated out


b. Kill mud has made a complete circulation
c. Kill mud has made a bottom-up
d. Kill mud reaches the bit

11. Mark the statements below "true" or "false" when drilling with a float valve in the string.

a) Surge pressure is reduced.

 True
 False

b) Reverse circulation is possible.

 True
 False

c) Flow back through the drillstring often occurs after pumping a slug.

 True
 False

d) Shut-in drillpipe pressure can be taken without starting the pumps.

 True
 False
WELL CONTROL

12. What is the primary function of the choke in the overall BOP system?

a) To divert contaminant to burning pit.


b) To hold back pressure while circulating up kick.
c) To divert fluid to the mud tank.
d) To prevent the loss of mud due to expansion of gas.
e) To close the well in softly.

13. While testing the BOP stack, it is noticed that hydraulic oil is leaking from the weep hole
on the upper rams. Which one of the following best describes the proper action to be taken?

a) Energize plastic seal and repair BOP at next scheduled maintenance.


b) A primary seal is leaking, secure the well and repair the seal.
c) The rams packer is leaking due to wear. Change the worn packer.
d) Do nothing. The seal requires a slight leak for lubrication purpose.

14. Why should the side outlet below a test plug be kept in the open position while testing a
surface BOP stack?

a) Because of potential damage to casing/open hole.


b) Because the test will create extreme hook load.
c) Otherwise reverse circulation will be needed to release the plug

15. Which three of the following conditions in the well increase the risk of exceeding the
MAASP during the well kill operation?

a) Long open hole section.


b) Large difference between formation breakdown pressure and mud hydrostatic
pressure.
c) Small influx.
d) Short open hole section.
e) Large influx.
f) Small difference between formation breakdown pressure and mud hydrostatic
pressure.

Questions 16-18 are base on the following information:

13 3/8” surface casing is set and cemented at 3126 ft. (TVD) The cement is drilled out
together with 15 ft. of new hole, using a 10.2 ppg. mud. A Leak Off Pressure of 670 psi is
determined.

16. What is the formation fracture gradient?


a) 0.619 psi/ft
b) 0.837 psi/ft
c) 0.745 psi/ft
d) 0.530 psi/ft.
WELL CONTROL

17. What is the Maximum Allowable Annular Surface Pressure for 11.4 ppg mud used at
6500 ft TVD.

a) 865 psi
b) 474 psi
c) 449 psi
d) 563 psi

18. How often should the MAASP be recalculated?

a) After every bit change


b) After a change in mud weight
c) After every 500 ft. drilled

19. A gas kick is being circulated out. At the time the gas reaches the casing shoe (3126 ft
TVD) the pressure at the top of the bubble is 2200 psi. If the original mud weight is 11.6
ppg.
What is the casing pressure at surface.

a) 314 psi
b) 442 psi
c) 542 psi
d) 506 psi

20. The Fracture Gradient of an open hole formation at 3680 ft. is 0.618 psi/ft. The drilling
mud currently in use is 9.8 ppg. Approximately how much Surface Casing Pressure can be
applied to the well before this formation breaks down?

a) 350 psi
b) 2275 psi
c) 630 psi
d) 400 psi

21. What is primary well control?

a) The slow Circulating Rate Pressure used in the kill process.


b) The used of Mud hydrostatic to balance fluid pressures in the formation.
c) The use of Blow Out Preventers to close in a well that is flowing.
d) The use of Pit Volume and Flow Rate measuring devices to recognize the kick.

22. What is meant by Abnormal High Pressure with regard to fluid pressure in the formation?

a) The excess pressure due to circulating mud at high rates.


b) The excess pressure that needs to be applied to cause „leak-off „ into a normally
pressure formation.
c) High density mud used to create a large overbalance.
d) Formation fluid pressure that exceeds normal water hydrostatic pressure.
WELL CONTROL

23. Which factors most influence the rate at which shut in pressures stabilize after the well is
shut in?

a) Gas migration
b) Friction losses
c) Permeability
d) Type of influx

24. While running pipe back into the hole, it is noticed that the normal displacement of mud
into the trip tank is less than calculated. After reaching bottom and commencing circulation,
the return flow meter is observed to reduce from 50% to 42%. A pit loss of 2 bbl. is noted.
What is the most likely cause of these indications?

a) Partial lost circulation has occurred.


b) Total lost circulation has occurred.
c) A kick has been taken.
d) The well has been swabbed.

25. If total losses occurred while drilling with water based mud what would you do?

a) Continue drilling blind.


b) Stop drilling and fill the annulus up with water, from the top until stabilized.
c) Stop drilling, shut the well in and see what happens.

26. Lost circulation during a well control operation is usually detected by:

a) Monitoring the return flow with the flow show.


b) Monitoring the mud volume in the mud tanks.
c) Monitoring the weight indicator.

27. A kick has been taken and it is known that a potential lost circulation zone exists in the
open hole. Select two correct actions which can be taken to minimize pressure in the annulus
during the kill operation.

a) Maintain extra back pressure on the choke for safety.


b) Use the wait and weight method.
c) Choose a lower circulating rate.
d) Choose a higher circulating rate.

28. Which of the following causes of well kicks is totally avoidable and is due to a lack of
alertness by the driller?

a) Lost circulation.
b) Gas cut mud.
c) Not keeping hole full.
d) Abnormal Pressures.
WELL CONTROL

29. Which two of the following cause swabbing?

a) Pulling the pipe too fast.


b) Insufficient trip margin.
c) Improper circulating density.
d) Going into the hole too fast.
e) Failure to slug pipe prior to pulling out of hole.

30. Why is a 20 barrel kick in a small annulus more significant than a 20 barrel kick in a large
annulus?

a) The kill weight mud cannot be calculated as easily.


b) It result in higher annulus pressures, due to the height of the kick.
c) The kicks are usually gas
d) The pipe usually get stuck.

31. Which one of the following is not an indication when a kick may be occurring?

a) Flow rate increase.


b) Increase torque.
c) Pit gain.
d) Gas cut mud.

32. What should the driller do at a drilling break?

a) Circulate bottoms up.


b) Flow check
c) Reduce weight on bit.
d) Increase pump speed.

33. Which two practices are used to maintain primary well control as a precaution when
connection gas is noticed?

a) Pumping a low viscosity pill around bit to assist in reduction of balled bit or
stabilizers.
b) Control drilling rate so that only one slug of connection gas is in the hole at any one
time.
c) Pulling out of the hole to change the bit.
d) Raising Mud yield point.
e) Minimizing the time during a connection when the pumps are off.
WELL CONTROL

34. Of all the following warning signs, which two signs would leave little room for doubt that
the well is kicking?

a) flow line temperature increase.


b) increased rotary torque
c) flow rate increase.
d) decrease drill string weight
e) pit volume gain
f) increased rate of penetration

35. Which of the following statements best describes formation porosity.

a) The ratio of the open spaces to the total volume of rock.


b) The ability of fluid and gas to move within the rock.
c) The presence of sufficient salt water volume to provide gas lift.
d) All of the above

36. While drilling The active tank contained 200 bbls and the mud return line to the pits
contains 20 bbls. After having a kick the tank contains 240 bbls. What is the size of the
influx?.

a) 260 bbls
b) 20 bbls
c) 40 bbls
d) 240 bbls.

37. The driller is tripping pipe out of a 12 ¼” diameter hole. 25x92 ft. stand of 5” pipe have
already been pulled. There are 85 more stands to pull. The calculated metal displacement of
the 9 ½” collars is 0.08 bbls/ft. The capacity of the drill pipe is 0.01776 bbls/ft and the metal
displacement 0.0075 bbls/ft. The trip tank volume has reduced from 27 barrels to 15 barrels.
What action should be taken in this situation?

a) Flow check, if negative continue to pull out of hole.


b) Shut the well in and circulate hole clean.
c) Flow check, if negative displace a 100 ft. heavy slug into annulus and continue to
pull out of hole.
d) Flow check, if negative run back to bottom and monitor returns.
e) Pull remaining stands out of hole.
WELL CONTROL

38. Prior to pulling out of the hole from 10485 ft. TVD, the pipe is full of 10.4 ppg. mud. The
pipe capacity is 0.01776 bbls/ft. A 25 bbls slug weighting 12.0 ppg is pumped into the drill
pipe causing the level to drop some 216 ft. inside the drill pipe.
What is the drop in bottom hole pressure due to pumping the slug into position?

a) 25 psi
b) 0 psi.
c) 117 psi
d) 135 psi.

39. Which of the following possible indications suggest that mud hydrostatic pressure and
formation pressure are almost equal?

a) A drilling break.
b) Connection gas.
c) Large, splintery cuttings.
d) Trip gas.
e) All of above.

40. While pulling out of the hole it is noticed that mud required to fill the hole is less than
calculated. What action must be taken?

a) Flow check, if negative displace a 100 ft. heavy slug into annulus and continue to
pull out of the hole.
b) Flow check, if negative run back to bottom circulate bottoms up and monitor returns.
c) Pull remaining stands out of the hole.
d) Flow check, if negative continue to pull out of the hole.
e) Shut the well in and circulate the hole clean.

41. You are pulling out of hole. Two 93 ft. stands of 8” drill collars have been stood back in
the derrick. The displacement is 0.0549 bbls/ft.
According to your Assistant driller - 5.1 bbls should be pump into the well. It only takes 5
bbls to fill the hole. (Answer “Yes” or “No” to each question.)

a) Are the calculations correct?

Yes No

b) Have you taken a 5 bbls influx?

Yes No

c) All OK, keeps going?

Yes No
WELL CONTROL

42. While tripping out of the hole a kick was taken and a full bore kelly cock was stabbed and
closed. A non return type safety valve was made up on top of the kelly cock prior to stripping
in. (Answer “Yes” or “No” to each question.)

a) Should the kelly cock be closed?

Yes No

b) If the kelly cock is left in the open position, can a wire line be run inside the drill
string?

Yes No

43. From the list of practices shown below, choose the six most likely to lead to an increase in
the size of the influx.

a) Switch off the flow meter alarms.


b) Regular briefing for the derrickman on his duties regarding the monitoring of pit levels.
c) Drilling 20 ft further after a drilling brake, before flow checking.
d) Running regular pit drills for drill crew.
e) Maintaining stab in valves.
f) Testing stab in valves during BOP tests.
g) Excluding the drawworks from the SCR assignment.
h) Keeping air pressure on choke control console at 10 psi.
i) Calling toolpusher to floor prior to shutting in the well.
j) Not holding down master air valve on remote BOP control panel while functioning a
preventer.

44. If flow through the drillpipe occurs while tripping, what should the first action be?

a. Pick up and stab kelly.


b. Run back into bottom.
c. Close the annular preventer.
d. Stab a full opening safety valve, close the valve.

45. Which list below (a, b, c or d) describes how the choke manifold will most likely be set up
for Hard Shut-in while drilling?

BOP Side Outlet HydraulicValve(HCR) Auto Choke


A open closed closed
B open open closed
C closed open open
D closed closed open
WELL CONTROL

46. While drilling along at a steady rate the derrickman asks to slow the mud pumps down so
that the shakers can handle the increase in cuttings coming back in the returns. Which
one of the following would be the safest course of action.

a) Continue at the same rate allowing the excess to bypass the shakers and get caught in
sand traps which can be dumped later.
b) Pick up off bottom and check for flow, if there is not any then circulate bottoms up to
reduce rate so shakers can handle cutting volume, flow check periodically during
circulation.
c) Slow down the mud pump until the shakers can handle the volume of cuttings in the
returns as requested by derrickman.
d) Slow down the drilling rate and the pump rate until the shakers clear up then go back to
the original parameters.
WELL CONTROL

EXERCISE # 5

1. When a kick occurs, why is it important to get the well shut in as soon as possible

a) A larger pit gain will result in a higher SIDPP resulting in a heavier kill mud weight

True or False.

b) A larger pit gain will result in higher SIDPP and SICP

True or False.

c) A larger pit gain will result in higher SICP but SIDPP will stay the same

True or False.

2. A flowing well is closed in. Which two pressure gauge readings might be used to
determine formation pressure?

a) BOP manifold pressure gauge


b) Choke console drill pipe pressure gauge
c) Driller‟s console drill pipe pressure gauge
d) Choke console casing pressure gauge

3. A kick is being circulated out at 30 SPM. The drill pipe pressure reads 550 psi, and
casing pressure 970 psi. It is decided to slow the pumps to 20 SPM while maintaining
970 psi on the casing gauge. How will this affect bottom hole pressure (exclude any
Equivalent Circulating Density [ECD] effect)? Pick one answer.

a) Increase
b) Decrease
c) Stay the same
d) No way of knowing

4. While killing a well, as pump speed is increased, what should happen to casing pressure
in order to keep bottom hole pressure steady?

a) Casing pressure should be held steady during SPM change


b) Casing pressure should be allowed to rise during SPM change
c) Casing pressure should be allowed to fall during SPM change

5. The principle involved in Constant Bottom Hole Pressure methods of well control is to
maintain a bottom hole pressure that is :

a) Equal to the slow circulating rate pressure


b) At least equal to the formation pressure
c) Equal to the shut in drill pipe pressure
d) At least equal to the shut in casing pressure
WELL CONTROL

6. At what point while correctly circulating out a gas kick is it likely that the pressure at the
casing shoe to be at its maximum?

a) At initial shut in
b) When kill mud reaches the bit
c) When kill mud reaches the shoe
d) When top of gas reaches the shoe

7. If Drill pipe Pressure is held constant while displacing the string with kill mud, what will
happen to Bottom Hole Pressure?

a) Increases
b) Remains the same
c) Decreases

8. How is a choke wash-out recognized?

a) Rapid rise in casing pressure with no change in drill pipe pressure


b) Increase in drill pipe pressure with no change in casing pressure
c) Continually having to open choke to maintain drill pipe and casing pressure
d) Continually having to close choke to maintain drill pipe and casing pressure

9. The choke has to be gradually closed due to a string washout. What effect does the
gradual closing of the choke have on the bottom hole pressure?

a) Decreases
b) Increases
c) Stays the same

10. If Bottom Hole Pressure is held constant while circulating the influx out, the pressure on
at the casing shoe will not increase after the influx passes, even though surface pressure on
the annulus continues to rise.

a) True
b) False

Questions 10-18 are based upon the following information :


A well is closed in having taken a 30 bbl gas kick, while drilling 8 ½” hole at 11,000 ft. (TVD)
with 5” drill pipe and 750 ft. of 6 ½” drill collars
Annular capacities
5" DP / 8 ½" Hole, = 0.0459 bbls / ft.
DC /8 ½" Hole, =0.0292 bbls / ft
WELL CONTROL

11. The mud weight is 12.3 ppg and the Shut in Drill Pipe Pressure is 350 psi. Assuming the
gas Pressure Gradient to be 0.115 psi/ft, what will be the approximate Shut in Casing
Pressure:

a) 835 psi
b) 650 psi
c) 975 psi
d) 888 psi

12. While preparing to circulate Kill Mud, the gas bubble begins to migrate. If no action is
taken, what will happen to the pressure in the gas bubble as it rises:

a) Increase
b) Decrease
c) Remain approximately the same

13. What will happen to Bottom hole Pressure?

a) Increase
b) Decrease
c) Remain approximately the same

14. What will happen to Shut in Casing Pressure?

a) Increase
b) Decrease
c) Remain approximately the same

15. What will happen to the pressure on the Casing Seat?

a) Increase
b) Decrease
c) Remain approximately the same

16. If you decide to bleed enough mud to keep the Drill Pipe Pressure constant at 350 psi,
what would the pressure in the bubble do as the gas rises?

a) Increase
b) Decrease
c) Remain approximately the same
17. What would happen to Bottom Hole Pressure?

a) Increase
b) Decrease
c) Remain approximately the same
WELL CONTROL

18. What would happen to the Shut in Casing Pressure?

a) Increase
b) Decrease
c) Remain approximately the same

19. What would happen to the Pressure on the Casing Seat while the bubble is below the
Casing Shoe?

a) Increase
b) Decrease
c) Remain approximately the same

20. What would happen to the Pressure on the Casing Seat when the bubble is above the
Casing Shoe?

a) Increase
b) Decrease
c) Remain approximately the same

21. A kick is being circulated from a well using the Driller‟s Method; Pumping pressure
having been established as 1000 psi at 30 SPM. During the operation, pressure suddenly
increases to 1350. You are reasonably sure that a Nozzle of the Bit is plugged. What
should you do?

a) Reduce pump pressure to 1000 psi by adjusting the choke


b) Shut the well in and re-establish the pumping pressure
c) Hold casing pressure constant at the value recorded just before the bit plugged
d) (a) and (b) are acceptable courses of action

22. During the well kill operation, slowly but regularly you have had to reduce choke size
because the drill pipe and casing pressures keep dropping with constant pump strokes.
What is the likely cause of this?

a) A bit nozzle is washing out


b) The choke is washing out
c) You have a washed out pump swab

23. An influx is being circulated out using the Driller‟s Method and using 1100 psi at 30
SPM. The operator increases pump speed to 35 SPM, while holding pump pressure
constant.
What happens to Bottom Hole Pressure?

a) Increases
b) Decreases
c) Remains approximately the same
WELL CONTROL

24. Which of the following parameters can be affected by a drill string washout during a well
kill operation?

a) Bottom hole pressure


b) Kick tolerance
c) Formation fracture pressure
d) Slow circulating rate pressure

25. You are killing a well using the Drillers Method, maintaining constant Drill pipe pressure.
The drill pipe pressure begins to drift down, but the casing pressure remains
unchanged. The pump strokes remain constant. You close up your choke slightly, the drill
pipe pressure remains unchanged but the casing pressure goes up. What is the probable
cause for this?

a) Choke is plugging off


b) Bit is plugging off
c) Hole in drill pipe
d) Choke is washing out

26. If regularly and rather slowly, you have to pinch in the choke to maintain drill pipe and
choke pressures while the pump strokes remain constant, you may have:

a) a washed out bit nozzle


b) a washed out choke
c) a pump failure

27. How can a washout at the adjustable choke be recognized?

a) Drill pipe and casing pressures both falling


b) Drill pipe and casing pressures both rising
c) Rapid rise in casing pressure with no change to drill pipe pressure
d) Increase in drill pipe pressure with no change to casing pressure

28. The reason shut in casing pressure is usually higher than the shut in drill pipe pressure
is:

a) The cuttings in the annulus are lighter, therefore creating a lighter hydrostatic in the
annulus.
b) The influx fluid is usually less dense than the existing mud weight.
c) The casing pressure is not necessarily higher, it depends on whether it is an
offshore or land operation.
d) The only difference is in the type of gauges used.
WELL CONTROL

29. After shutting in on a kick, the SIDPP and SICP are observed to be stable for fifteen
minutes. Both, then, start rising slowly by the same amount. Which one of the following
is the probable cause?

a) A further influx is occurring


b) The influx is migrating up the well bore
c) The gauges are faulty
d) The BOP stack is leaking

30. After a round trip at 9854 ft with 10.3 ppg mud, we kick the pump in and start to circulate.
The well kicks and is closed in with 0 psi on the SIDPP and 150 psi on the SICP. There is
no float in the drill string. What kill mud weight is required?

a) 10.3 ppg
b) 11.3 ppg
c) 10.7 ppg
d) No way of knowing

31. Shut in casing pressure is used to calculate

a) Kill weight mud


b) Influx gradient and type when influx volume and well geometry are known
c) Maximum Allowable Annular Surface Pressure
d) Initial circulating pressure

32. A kicking well has been shut in. The drill pipe pressure is „0‟ because there is a non-
return valve (float) in the string. To establish the SIDPP, what action should be taken?

a) Shearing the pipe and reading the SIDPP directly off the casing gauge
b) Pump at kill rate into the drill string with the well shut in. When casing pressure
starts to rise, read the pump pressure. This is the SIDPP.
c) Pump very slowly into the drill pipe with the well shut in. When the pumping
pressure stabilizes, the float has opened. This pumping pressure is the SIDPP.
d) Bring the pump up to the kill rate holding the casing pressure constant by opening
the choke. The pressure shown when the pump is at kill rate is the SIDPP.

33. After circulating out a kick using the driller‟s method (no weight up), are the SICP and
SIDPP about the same?

a. yes
b. no

34. A gas kick is being circulated up the well. What is the surface pit volume most likely to
do?

a) Increase
b) Stay the same
c) Decrease
WELL CONTROL

35. On a surface stack, what would happen if when bringing the pumps up to kill speed, the
casing pressure was allowed to fall below shut in casing pressure?

a) Formation would most probably break down


b) More influx would be let into the well bore
c) It would have no effect on anything

36. For each of the following statements, note whether it relates to the Drillers Method or
the Wait and Weight Method.

a) Minimize pressures generated in the annulus due to gas migration.

Driller W&W

b) Remove influx from well before pumping kill mud

Driller W&W

c) Pump kill mud while circulating influx up the annulus

Driller W&W

d) Maintain Drill Pipe pressure constant for 1 st circulation

Driller W&W

37. Which one of the following actions taken while stripping into the hole will help to maintain
an acceptable bottom hole pressure?

a) Pumping a volume of mud into the well, equal to the drill pipe closed end
displacement at regular intervals
b) Bleeding off the drill pipe steel displacement at regular intervals
c) Pumping a volume of mud into the well, equal to the drill pipe steel displacement, at
regular intervals
d) Bleeding off the drill pipe closed end displacement at regular intervals

38. Which of the following statements is true?

a) There is no difference between using the Drillers method and the Wait and Weight
method
b) If the kill mud is being circulated up the annulus before the kick has reached the
shoe then Wait and Weight method will reduce the risk of breaking down the formation
compared to using the Drillers method
c) The Wait and Weight method should always be used because the pressure against
the open hole will always be lower when using the Drillers method
WELL CONTROL

39. Mud weight increase required to kill a kick should be based upon :

a) shut in drill pipe pressure


b) shut in casing pressure
c) original mud weight plus slow circulation rate pressure losses
d) shut in casing pressure minus shut in drill pipe pressure

40. How is the Initial Circulating Pressure found on a land rig or a jack-up, when the slow
pump rate circulating pressure is not known but a kick has been taken?

a) Circulate at desired strokes per minute to circulate out the kick, but hold 200 psi
back pressure on drill pipe side with choke
b) Add 400 psi to casing pressure and bring pump up to kill rate while using the choke
to keep the casing pressure +400 constant
c) Bring pump strokes up to kill rate while keeping casing pressure constant by
manipulating the choke, observed pump pressure is ICP
d) Add 1000 psi to shut in drill pipe pressure and circulate out the kick

41. Having completed the first circulation of the Driller‟s Method, the well is shut in. Should
casing pressure be:

a) Less than Shut in Drill Pipe Pressure


b) Equal to Shut in Drill Pipe Pressure
c) Greater than Shut in Drill Pipe Pressure

42. On the second circulation of the Driller‟s method, if the casing pressure was held
constant until the kill mud reached Surface, what would happen to the bottom hole
pressure?

a) Increase
b) Decrease
c) Stay the same

43. Using Wait and Weight method, if the drill pipe pressure drops below the line of the
graph as the kill mud goes down, what happens to the bottom hole pressure?

a) Increases
b) Decreases
c) Stays the same
WELL CONTROL

44. You have taken a kick with a non-return valve (float) in the drill string. After shutting the
well in properly, it is best to :

a) Use the annulus pressure to calculate the kill weight mud


b) Start raising the mud weight 1 ppg per circulation until the well is dead
c) Use either the rig pump or cementing unit pump to increase pressure in 100 psi
increments until a change is seen on casing gauge
d) Pump slowly into the drill pipe. When the pump pressure stabilizes, the float is
open. The pumping pressure is the SIDPP used to calculate kill mud

45. A well is being killed using the Driller‟s Method.


Original shut-in drill pipe pressure = 500 psi
Original shut-in casing pressure = 900 psi

After the first circulation, the well is shut in and pressures allowed to stabilize. They then
read :

Shut-in drill pipe pressure = 500 psi


Shut-in casing pressure = 650 psi

It is decided not to spend any more time cleaning the hole


Which one of the following actions should be taken

a) Prepare to use the Wait and Weight method


b) Bull-head the annulus until shut-in casing pressure is reduced to 500 psi
c) Reverse circulate until shut-in casing pressure is reduced to 500 psi
d) Continue with second circulation of Drillers Method (holding casing pressure
constant until mud reaches the bit)

46. If the slow pump circulating pressure was not known, and a kick has been taken with the
well closed in, how would you find the ICP?
a) Bring pump up to the desired rate, while holding the casing pressure 150 psi above
the original SICP
b) Bring pump up to desired rate, but hold 200 psi back pressure on the drill pipe
c) Bring pump up to the desired rate holding casing pressure constant by manipulating
the hydraulic choke
d) Circulate at desired kill rate but hold casing pressure 100 psi below MAASP

47. The correct gauge to use for calculating the kill weight mud is :
a) the gauge on the choke and kill manifold
b) the drill pipe pressure gauge on the drillers console
c) the casing gauge on the drillers console
d) the drill pipe gauge on the remote auto choke panel
e) the casing gauge on the remote auto choke panel
WELL CONTROL

EXERCISE # 6

1. What is the primary function of the weep hole (drain hole, vent hole) on a ram type BOP?
a) To show that ram body rubber is leaking.
b) To show that the primary mud seal on the piston rod is leaking.
c) To show that the Bonnet seals are leaking.
d) To show that the closing chamber operating pressure is too high.

2. You only have one inside BOP with an NC 50 (4”1/2 IF) lower pin connection on your rig
but the drill string consist of 5” HWDP, and 8” collars. Which one of the following
crossovers would you have on the drill floor in case of kick while tripping?
a) 6-5/8” reg. Box X 7-5/8” reg. Pin
b) NC50 (4-1/2” IF) Pin X 6-5/8” reg. Pin
c) NC50 (4-1/2” IF) Box X 7-5/8” reg. Pin
d) NC50 (4-1/2” IF) Box X 6-5/8” reg. Pin

3. Two types of valves may be used in the drill string:


Type 1 Non return, stab in safety valve or inside BOP
Type 2 Fully opening stab in Kelly cock valve or fully opening safety valve
Indicate in the table which statement describes the valves.

Type 1 Type 2
Requires the use of key to close
Must not run in the hole in the close position
Has to be pumped to read “shut-in drill pipe pressure”
Will not allow wireline to be run inside the drill string
Has potential to leak through the open/close key
Easier to stab if strong flow is encountered up the string

4. A BOP stack is configured: Pipe ram / Blind-Shear ram / Pipe ram / Annular, kill and
choke lines are connected under the blind-shear rams. Is it possible to kill a well using the
Driller's method if;
a) The upper pipe rams are closed?
b) The blind shear rams are closed?
c) The lower pipe rams are closed?

5. A BOP stack is configured: Pipe ram / pipe ram / Blind-Shear ram / Annular, kill and
choke lines are connected under the blind-shear rams.
a) Can you repair the side outlets with pipe in the hole?
b) Can you repair the outlets with no pipe in the hole?
c) Is it possible to shut in with drill pipe in the hole and circulate through the drill pipe?
d) Can you change blind rams to pipe rams and kill the well?

6. A BOP stack is configured: Drilling spool / Pipe ram / Blind-Shear ram / Annular, kill and
choke lines are connected to the drilling spool.

a) With drill pipe in hole, can we repair the side outlets?


b) With no drill pipe in the hole, can you shut in and repair the Drilling spool?
c) With drill pipe in hole, can you circulate through the Drilling spool?
WELL CONTROL

7. The kill line should enter a stack so that

a) The well can be circulated if the blind rams are in use.


b) The well can be circulated if the pipe rams are being used.
c) Both the above.

8. Which of the following statements are true concerning Ram Packing Elements?

a) Reciprocating motion of the pipe increases the wear on seals.


b) Closing pipe rams on open hole may damage the elements.
c) The ram packer should normally be checked, and if worn, changed whenever the
bonnet is opened.
d) All of above.

9. What do the term “6BX” stamped on a flange represent?

a) serial number
b) pressure rating
c) type
d) size

10. What is meant by the closing ratio for a ram type BOP?

a) Ratio between closing & opening volume.


b) Ratio between closing & opening time.
c) Ratio of the wellhead pressure to the pressure required to close the BOP.

11. Study the two tables below which contain markings stamped on API flanges and ring
gaskets. Each flange (1,2,3 and 4) mates with one of the ring gaskets (A,B,C or D). Write the
appropriate flange number in the blanks.

Ring Gasket Marking Flange

A -CI API BX154 S304-4


B -OES API R57 D-4
C- OES API RX66 S-4
D -CI API BX153 S316-4

Flange Marking

1. OES API 16-3/4 3M RX66 6A 89 300F PSL3 05/91


2. CI API 3-1/16 15M BX154 CRA 6A 89 250F PSL2 PRL2 08/92
3. OES API 2-9/16 20M BX153 CRA 6A 89 350F PSL4 PRL4 01/94
4. OES API 13-5/8 2M R57 6A 89 250F PSL1 PRL1 11/93

Gasket Flange
A
B
C
D
WELL CONTROL

12. From the list below, identify the ring gaskets that are pressure energized. (Pick four
answers)
a) Type RX
b) Type BX
c) Type AX
d) Type R oval
e) Type R octagonal
f) Type CX

13. Which dimension from the list below is used to identify the “Nominal Flange Size”
a) Throughbore I.D.
b) Flange O.D.
c) Diameter of raised face.
d) O.D. of ring groove.
e) Bolt circle diameter.

14. What is the main function of a diverter?


a) To shut in a shallow kick.
b) To direct fluid a safe distance away from the rig floor.
c) To create a back pressure sufficient to stop formation fluids entering the wellbore.
d) To act as a back up system if the annular preventer fails.

15. In an area where local legislation requires that BOP equipment must be rated so that
maximum anticipated formation pressures do not exceed 75% of BOP equipment pressure
ratings, what is the minimum acceptable rating for equipment to be used in drilling normally
pressure formation to 16000 ft TVD?
a) 2000 psi BOP equipment
b) 3000 psi BOP equipment
c) 5000 psi BOP equipment
d) 10000 psi BOP equipment
e) 15000 psi BOP equipment

16. A BOP stack is configured Pipe Ram / Blind-Shear ram / Pipe Ram / Annular. Use the
table below to calculate the required accumulator volume if company policy is to provide
sufficient volume to close, open and close again all rams and the annular.

Component Volume to Open Volume to close


Annular BOP 27 29
Ram BOP 13 15
WELL CONTROL

17. The following statements relate to the driller‟s remote control BOP control panel located
on the rig floor. Decide if the statements are true or false.

a) If you operate a function without operating the master control valve that function will
not work.

True or False

b) The master control valve on an air operated panel allows air pressure to go to each
function in preparation for you operating the function.

True or False

c) The master control valve must be held depressed while BOP functions are operated.

True or False
d) The master control valve must be depressed for five seconds then released before
operating a BOP function.

True or False

18. The API RP53 states that closing time should not exceed X seconds for annular BOPs
smaller than 18-3/4". What is the value of X?

a) 30 sec.
b) 60 sec.
c) 2 min.
d) 45 sec.

19. Which is the correct definition of the HPU reservoir volume according to API RP53?
a) 2 times usable accumulator volume.
b) 2 times accumulator volume.
b) 5 times total accumulator volume .

20. Which two pressure readings decrease during normal operation of the pipe rams?

a) Manifold pressure
b) Annular pressure
c) Accumulator pressure
c) Precharge pressure

21. When closing the annular preventer from the remote panel, which two gauges show a
reduction in pressure?

a) Manifold pressure
b) Annular pressure
c) Accumulator pressure
d) Air pressure
WELL CONTROL

22. In the case below, identify the most likely problem from the gauge readings
observed on the remote control panel. The annular setting is 900 psi, the manifold setting is
1,500 psi.

a) Everything is OK.
b) Malfunction pressure regulating valve.
c) Malfunction hydro-electric switch
d) Leaking in hydraulic circuit
e) Precharge pressure is to low

23. A BOP operating unit has 8 accumulator bottles, each with a capacity of 10 gallons.
Operating pressure is 3000 psi. Precharge pressure is 1000 psi. What is the total usable
fluid volume when the minimum BOP operating pressure is 1,200 psi?

Answer: gal
24. On a 3000 psi accumulator system, what are the normal operating pressures seen on the
following gauges on the drillers remote control panel?

 Air pressure = psi


 Accumulator pressure, = psi
 Manifold pressure, = psi
 Annular pressure = psi

25. On which two gauges on the remote panel would you expect to see reduction in pressure
when the annular preventer is being closed?

26. If the air pressure on the drillers panel reads 0 psi, which of the following statements is
true?

a) No stack function can be operated from the remote panel.


b) All stack function can be operated from the remote panel.
c) Choke and kill lines can still be operated from the remote panel.
d) The annular preventer can still be operated from the remote panel.

27. Which of the problems below would not stop the BOP from closing?

a) Master control valve was not held down.


b) Four-way valve did not shift position.
c) Closing line in the BOP was blocked.
d) Leak in the hydraulic line to the BOP or in the BOP closing chamber.
e) Air pressure to the panel was lost.
f) A bulb has blown on the remote panel.
WELL CONTROL

28. When drilling, which may be the correct position of the 4-way valves on the BOP
accumulator unit?
a) open
b) close
c) neutral
d) open or closed depending on BOP stack function

29. What is the normal precharge for the accumulator bottles on a 3000 psi accumulator unit?
a) 1000 psi
b) 3000 psi
c) 1200 psi
d) 200 psi
WELL CONTROL

EXERCISE # 7

Use the Well Data to answer the questions.

WELL DATA

Well Depth 8,554 ft TVD


10,500 ft MD
Kick Off Point 4,000 TVD / 4,000 MD
End Of Build 5,447 TVD / 5,667 MD
Bit size 8.5”
Drill Pipe 5” OD. 19.5 lbs/ft
Capacity = 0.01776 bbls/ft
Heviwate 5” OD x 3” ID x 720 ft
Capacity = .00874 bbls/ft
Drill Collars 61/2” x 213/16” x 820 ft
Capacity = 0.0077 bbls/ft
Casing 95/8”, 47 lb/ft. P110 8.681” ID
100% Internal yield = 10,900 psi
Set at 6,175 ft TVD / 6,800 MD
Formation strength test 1,270 psi w/ 10.4 ppg
Mud weight in use 11.5 ppg.
Surface Volume 320 bbls
Pumps National triplex 12-P-160
With 61/2” Liners
Capacity = 0.117 bbls/stk

PUMP PRESSURE

Slow Pump Rate 520 psi at 40 spm

ANNULAR VOLUMES

Drill pipe/HW - Casing = 0.0478 bbls/ft


Drill pipe/HW - Open hole = 0.0447 bbls/ft
Drill collars - Open hole = 0.0292 bbls/ft

WELL CONTROL DATA

SIDPP = 750 psi


SICP = 900 psi
GAIN = 22 bbls

You are recommended to complete a kick sheet to answer the following questions:
WELL CONTROL

1. How many strokes to pump from surface to bit:

2. What is the Initial Circulating Pressure?

3. What is the Final Circulating Pressure?

4. How many strokes to pump from surface to KOP?

5. What is the circulating pressure when kill mud reaches the KOP?

6. How many strokes to pump from surface to the EOB?

7. What is the circulating pressure when kill mud reaches the EOB?

8. Calculate the pressure drop per 100 strokes of kill mud pumped inside the
string from the EOB to the bit?
WELL CONTROL

9. Calculate MAASP after circulation of kill mud?

10. What is the approximate time needed to kill the well?


WELL CONTROL

EXERCISE # 8

Use the Well Data to answer the questions. Each question has only one correct
answer.

WELL DATA

Well Depth 15,700 ft TVD


16,500 ft MD
Marine riser 1700 ft capacity = 0.360 bbls/ft
Choke line 1724 ft capacity = 0.0087 bbls/ft
Bit size 8.5”
Drill Pipe 5” OD. 19.5 lbs/ft
Capacity = 0.01776 bbls/ft
Drill Collars 61/2” x 213/16” x 540 ft
Capacity = 0.008 bbls/ft
Casing 95/8”, 47 lb/ft. P110 8.681” ID
100% Internal yield = 10,900 psi
Set at 14,000 ft TVD – 14,200 ft MD RKB
Mud weight in use 12.4 ppg.
Pump output 0.117 bbls/stk

PUMP PRESSURE

While Drilling 3500 psi at 75 spm (APL = 270 psi)


Slow Pump Rate Up Riser 980 psi at 40 spm (APL = 75 psi)
250 psi at 20 spm (APL = 20 psi)
CLFL with 11 ppg mud 125 psi at 20 spm
500 psi at 40 spm

ANNULAR VOLUMES

Drill pipe - Casing = 0.0489 bbls/ft


Drill pipe - Open hole = 0.0459 bbls/ft
Drill collars - Open hole = 0.0292 bbls/ft
Drill pipe – Riser = 0.336 bbls/ft

WELL CONTROL DATA

SIDPP = 700 psi


SICP = 1150 psi
GAIN = 30 bbls

LEAK OFF TEST DATA

3650 PSI with 11 ppg mud


WELL CONTROL

1. What is the total capacity of the drill string?

a) 288 bbls
b) 162 bbls
c) 335 bbls
d) 456 bbls

2. Calculate the total annular capacity with the pipe on bottom?

a) 722 bbls
b) 443 bbls
c) 987 bbls
d) 323 bbls

3. What is the surface to bit time with the pump running at 40 spm?

a) 61 minutes
b) 25 minutes
c) 87 minutes
d) 54 minutes

4. Calculate bit to surface time (bottoms up) at 40 spm?

a) 155 minutes
b) 234 minutes
c) 60.3 minutes
d) 123 minutes

5. What kill mud is required to balance formation pressure?

a) 13.3 ppg
b) 13.0 ppg
c) 12.4 ppg
d) 16.0 ppg

6. The ICP (initial circulating pressure) at 40 spm will be approximately?

a) 1680 psi
b) 770 psi
c) 2130 psi
d) 1200 psi

7. The FCP (final circulating pressure) at 40 spm will be approximately?

a) approximately 1800 psi


b) approximately 1050 psi
c) approximately 1500 psi
d) approximately 1290 psi
WELL CONTROL

8. After reaching FCP it is decided to increase the pump speed to 50 spm. What
would happen to BHP if the drill pipe pressure is held constant at the original
FCP value?

a) increase by about 590 psi


b) decrease by about 590 psi
c) remain constant because drill pipe pressure was not changed
d) increase by about 500 psi

9. What is formation pressure based on the shut in data?

a) 10,823 psi
b) 6800 psi
c) 7800 psi
d) 6240 psi

10. What is the ECD on bottom while drilling?

a) 12.73 ppg
b) 15.54 ppg
c) 16.03 ppg
d) 16.52 ppg

11. What would be the circulating pressure while drilling if the pump was decreased
to 60 spm?

a) 2240 psi
b) 2800 psi
c) 2100 psi
d) 1860 psi

12. At 75 spm what is the annular velocity around the drill collars?

a) 412 ft/min
b) 210 ft/min
c) 506 ft/min
d) 300 ft/min

13. What is the maximum allowable mud weight?

a) 17.5 ppg
b) 16.0 ppg
c) 18.0 ppg
d) 19.0 ppg
WELL CONTROL

14. What is the approximate length of the influx?

a) 1027 ft
b) 850 ft
c) 653 ft
d) 342 ft

15. The gradient of the influx is about?

a) 0.115 psi/ft
b) 0.320 psi/ft
c) 0.465 psi/ft
d) 0.433 psi/ft

16. How many strokes to go from ICP to FCP?

a) 1282 stks
b) 1363 stks
c) 1680 stks
d) 2461 stks

17. Calculate the MAASP?

a) 2620 psi
b) 2524 psi
c) 2368 psi
d) 1356 psi

18. Not following the the correct pressure schedule, the BHP could be high or low
causing losses or another influx.

a) True
b) False

19. What is the capacity of the choke line:

a) 15 bbls
b) 12 bbls
c) 23 bbls
d) 28 bbls

20. How many strokes are required to displace the riser – annulus

a) 7034 strokes
b) 4882 strokes
c) 3453 strokes
d) 1234 strokes
WELL CONTROL

21. If the well had been shut in with 0 psi on the drill pipe pressure and no float in
the string and a SICP of 300 psi, what mud weight would have required to kill
the well?

a) 12.9 ppg
b) 12.4 ppg
c) 14.5 ppg
d) 15.5 ppg

Answer the following gauge questions as the well is killed using the Drillers
method.
TO TA L STR O KES
90 0 1000 1 100 900 10 00 1100
80 0 1200
1 20 800 1 200
70 0 1300 700 13 00
600 6 00
PSI 1400 PSI 14 00
5 00 15 00 5 00 1 500
400 160 0 4 00 1600

3 00 1700 300 1 700


200 1 800 200 18 00
1 00 1900 10 0 1 900
PU M P SPEED
D R ILLPIPE PR E SSU R E 40 C AS IN G P R ESSU R E

1 6 80 590

C H O KE
O P EN P O S IT IO N C LO S E

22. The kill operation has started. This is what the choke control console shows.
What should you do?

a) open the choke a little


b) close the choke a little
c) nothing everything looks alright
d) Possible plugged nozzle
e) Possible choke plugging

TO T A L S TR O K E S
900 100 0 1 100 900 100 0 11 00
800 120 0
500 800 120 0
70 0 130 0 70 0 130 0

60 0 60 0
PSI 140 0
PSI 1400
5 00 1500 5 00 1 500

40 0 16 00 40 0 160 0

300 170 0 300 170 0


2 00 1800 2 00 1 800
1 00 1 900 100 1 900
PUMP SPEED

D R ILLP IP E P R E S S U R E 40 C A S IN G P R E S S U R E

1620 700

CH O KE
O PE N P O S ITIO N C LO S E
WELL CONTROL

23. Pit room calls up to confirm a .5 bbl rise in the level. What should you do?

a) open the choke a little


b) close the choke a little
c) increase the pump speed
d) decrease the pump speed
e) nothing everything looks alright

TO TA L STR O KES
900 1000 1100 900 1000 1100
8 00 1200
4550 800 1200
700 1 300 700 1300
600 600
P SI 1400
PS I 1400
500 1500 500 1500

400 1600 400 1600

300 1700 300 1700


200 1800 200 1800
100 1900 100 1900
PU M P SPEED
D R ILLP IPE PR E SSU R E 40 CASIN G PR ESSU R E

1 6 80 1 4 80

CH OK E
O PEN PO SITIO N C LOS E

24. The pit levels are still reported to be increasing slightly. This is what you see on
the panel.

a) open the choke a little


b) close the choke a little
c) possible choke washout
d) possible choke plugging
e) nothing everything looks alright

TOTAL STROK ES
90 0 1000 11 00 900 1000 1100
8 00 1200 5600 800 12 00
70 0 1 300 700 1300
600 600
PSI 140 0
PSI 1400
500 1500 50 0 15 00

400 1600 400 1600

300 1 70 0 300 1700


200 1800 200 180 0
100 1 900 100 1900
P UM P SPE ED
DR ILLPIPE PRE SSU RE 40 CASIN G PRESS UR E

1400 1720

CHO KE
OP EN PO SITION CL OSE
WELL CONTROL

25. Experienced a sudden increase in casing pressure over the last 100 strokes.
Gas is venting and pit levels are reported to be falling. What are you going to do
now?

a) open the choke a little


b) close the choke a little
c) possible nozzle plugging
d) possible choke plugging
e) nothing everything looks alright

TO TAL STRO KES

900 1000 1100 900 1000 1100


800 1200
6220 800 1200
700 1300 700 1300
600 600
PSI 1400 PSI 1400
500 1500 500 1500
400 1600 400 1600

300 1700 300 1700


200 1800 200 1800
100 1900 PUMP SPEED 100 1900

D R IL L P IP E P R E S S U R E 40 C A S IN G P R E S S U R E

1680 1 40

CHOKE
OPEN POSITION CLOSE

26. Not hearing anymore gas. How are things going?

a) open the choke a little


b) close the choke a little
c) casing pressure should be 0
d) possible choke wash out
e) good everything looks alright

TO TA L S TR O K E S
90 0 1000 1 100 900 10 00 110 0
80 0 120 0 6300 80 0 1 200
70 0 1300 700 13 00

600 1400 600 14 00


PSI PSI
500 1 500 5 00 150 0

400 160 0 400 1600

3 00 1700 30 0 1 700
200 1 800 200 18 00
1 00 1900 1 00 1 900
PUMP SPEED

D R ILLP IP E P R E S S U R E 00 C A S IN G P R E S S U R E

700 700

C H O KE
O P EN P O S IT IO N C LO S E
WELL CONTROL

27. Shut back in. What should you do?

a) Check MW = 13.3 ppg


b) Check MW = 16 ppg
c) Reset stroke counter
d) Bleed off pressure to 0
e) nothing everything looks alright

TO TA L S TR O K ES
900 1000 1100 900 1000 1100
800 1 200
0000 800 120 0
70 0 1300 700 1 300
600 1400 600 1400
PSI P SI
500 1500 500 1500

400 16 00 400 1600

300 1700 300 170 0


200 1800 200 1800
100 1900 100 1900
PU M P SPEED
D R ILLP IPE PRES SU R E 40 C AS IN G PR ESSU R E

1 7 80 236

CH O K E
O P EN PO SITIO N C LOS E

28. Got the pump to kill speed and have just reset the stroke counters having
pumped the surface line. What should you do?

a) open the choke a little


b) close the choke a little
c) increase the pump speed
d) decrease the pump speed
e) nothing everything looks alright

TOTAL STROK ES
90 0 1000 11 00 900 1000 1100
8 00 1200 250 800 12 00
70 0 1 300 700 1300
600 600
PSI 140 0
PSI 1400
500 1500 50 0 15 00

400 1600 400 1600

300 1 70 0 300 1700


200 1800 200 180 0
100 1 900 100 1900
P UM P SPE ED
DR ILLPIPE PRE SSU RE 40 CASIN G PRESS UR E

1620 140

CHO KE
OP EN PO SITION CL OSE
WELL CONTROL

29. Pump room is on the phone saying pit levels are OK. What are you going to do
now?

a) open the choke a little


b) close the choke a little
c) possible nozzle plugged
d) possible choke plugged
e) nothing everything looks alright

TO TAL STRO KES

900 1000 1100 900 1000 1100


800 1200
980 800 1200
700 1300 700 1300
600 600
PSI 1400 PSI 1400
500 1500 500 1500
400 1600 400 1600

300 1700 300 1700


200 1800 200 1800
100 1900 PUMP SPEED 100 1900

D R IL L P IP E P R E S S U R E 40 C A S IN G P R E S S U R E

1430 1 40

CHOKE
OPEN POSITION CLOSE

30. Drill pipe pressure is falling but casing pressure stay constant. How are things
going?

a) open the choke a little


b) close the choke a little
c) increase the pump speed
d) possible choke wash out
e) good everything looks alright

T O TA L S TR O K E S
90 0 1000 1 100 900 10 00 1100
80 0 1200
1720 800 1 200
70 0 1300 700 13 00
600 6 00
PSI 1400
PSI 14 00

5 00 15 00 5 00 1 500

400 160 0 4 00 1600

3 00 1700 300 1 700


200 1 800 200 18 00
1 00 1900 10 0 1 900
PUMP SPEED

D R ILLP IP E P R E S S U R E 00 C A S IN G P R E S S U R E

220 700

C H O KE
O P EN P O S IT IO N C LO S E
WELL CONTROL

31. Had to shut in because of a pump. What do you thing?

a) Drill pipe pressure is too low


b) Casing pressure is too high
c) Drill pipe pressure is too high
d) Casing pressure is too low
e) Everything looks alright

TO TA L S TR O K ES
900 1000 1100 900 1000 1100
800 1 200
2480 800 120 0
70 0 1300 700 1 300
600 1400 600 1400
PSI P SI
500 1500 500 1500

400 16 00 400 1600

300 1700 300 170 0


200 1800 200 1800
100 1900 100 1900
PU M P SPEED
D R ILLP IPE PRES SU R E 40 C AS IN G PR ESSU R E

1 0 50 130

CH O K E
O P EN PO SITIO N C LOS E

32. Back up to kill speed. Company man wants to know how things are going. What
do you tell him?

a) open the choke a little


b) close the choke a little
c) possible choke plugging
d) possible nozzle plugging
e) nothing everything looks alright
WELL CONTROL

EXERCISE # 9
1. A driller needs to close in a flowing well with drill pipe in a subsea BOP stack. He
Pushes the “Annular Close” button and the pilot light changes, but all gauges and the flow
meter remain static. What is his best option?

a) Change pod and try again.


b) Call and wait for the subsea engineer.
c) Send assistant driller to manually operate the 4-ways valve on the Hydraulic
Control Manifold to close the annular.
d) Close the lower annular preventer.

2. While drilling, an alarm goes off indicating low accumulator pressure and the flow meter
Indicates a rapid loss of fluid. The best course of action is:

a) Stop drilling and shut the well in.


b) Stop drilling and call subsea engineer.
c) Stop drilling and put all function in block one at a time until the flow stops.
d) None of the above.

3. When a function is operated, which of the following is true?

a) SPM valve will operate in both pods.


b) SPM valve will operate only on the active pod.
c) The SPM valve will operate after the function is complete.

4. How much time is allowed for subsea ram type preventer to close in API RP53?

a) 30 seconds
b) 45 seconds
c) 60 seconds
d) 50 seconds

5. From which position in the hydraulic circuit is readback pressure taken?

a) Upstream of the regulator in the pod?


b) The regulator itself?
c) Down stream of the regulator in the pod?

6. What is the principal reason for fitting ram locking devices such as wedgelocks or
Poslocks to a subsea stack?

a) To give additional force when closing in, thus reducing delay times.
b) To lock the ram in the closed position and maintain the shear rams locked
during disconnect.
c) To lock the BOP stack to the well head and lock the lower Marine Riser
Package to the BOP stack.
WELL CONTROL

7. The subsea hydraulic BOP control system is divided into a Control System and a Pilot
System. Which two statements are true with respect to the Pilot System?

a) The fluid in the Pilot System flows continuously while a function on the BOP takes
place.
b) The Pilot System dumps fluid to the sea at every operation of BOP functions.
c) The Pilot System controls the position of all shuttle valves on the BOP stack
directly.
d) The Pilot system is a closed dead-end system.
e) Pilot fluid consists of potable water, water-soluble concentrate and glycol.

8. Which two statements are true with respect to shuttle valves on a subsea stack?

a) The shuttle valves automatically seal any hydraulic leaks in the selected pod.
b) The shuttle valves prevent communication between the selected system and the
redundant system.
c) The shuttle valves are pilots operated.
d) The shuttle valves allow the retrieval of a malfunctioning pod without losing
hydraulic BOP control.

9. What is the purpose of the "Memory Function" on electric control panels?

a) Memory Function indicates a malfunction by giving permanent light on the alarm


panel after an alarm has been acknowledged and the audible alarm has stopped.
b) Memory Function reminds the driller to add anti-freeze fluid when the temperature
drops below a set level.
c) Memory Function indicates the previous position before “Block position” of three
position functions.
d) Memory Function reminds the driller to engage Wedge Locks before hanging off.

10. Which of the following statements is true regarding to the use of “manipulator” type 4-
Ways valve used in subsea hydraulic BOP control systems.

a) If the valve is shifted to the center or “block” position, pressure will be vented from
the line previously pressurised.
b) If the valve is shifted to the center or “block” position, pressure will be trapped in the
line previously pressurised.

11. Name 3 potential causes of riser collapse:


WELL CONTROL

12. What is the purpose of sub-sea stack mounted bottles?

a) to minimize the time to operate any BOP function


b) to maximize the time to operate any BOP function
c) to minimize the time to operate annular type preventer
d) to optimize the time to operate ram type preventer

The drillers BOP panel has gauges for pilot and readback pressure for the manifold
and annular pressure. Answer true or false to the following statements:

13. Pilot pressure and readback pressure should normally be the same.

a) true
b) false

14. Read back pressure is mesured at the output from the sub sea regulator

a) true
b) false

15. Pilot pressure is measured at the out put of the surface regulator

a) true
b) false

Answer true or false in each case to measure Choke Line Friction Loss (CLFL):

16. You can pump down the choke line taking return up the riser.

a) true
b) false

17. You need to know the length of the choke line.

a) true
b) false

18. You can pump down the drill string taking returns through the riser and then close
the annular and take returns through the choke line.

a) true
b) false

19. While pumping down the choke line at 150 gpm taking returns through the riser
with 9 ppg mud in 750 feet water with 60 feet air gap, a stand pipe pressure of 65
psi was recorded. Estimate CLFL:

a) 30 psi
b) 65 psi
c) 351 psi
d) 143 psi
WELL CONTROL

20. What would be the new CLFL if the mud weight is increased to 13.5 ppg (use data
from Q-19)

a) 65 psi
b) 97.5 psi
c) 132 psi
d) 234 psi

21. While pumping down the drill string and up the riser, a circulating pressure of 375
psi was recorded.
The annular was closed and returns taken through a wide open choke, circulating
pressure was now 600 psi. What are the CLFL?

a) 375 psi
b) 975 psi
c) 600 psi
d) 225 psi

22. Calculate the Maximum Allowable Mud Weight with the following data:

Hole size 17 ½”,


Air gap is 80 ft,
Water depth is 220 ft,
Casing shoe is 600 ft RKB, Air gap
Sea water is .455 psi/ft,
Overburden is .65 psi/‟ft,
APL is 10 psi
Well depth
Water depth
a) 8.77 ppg
b) 9.45 ppg
c) 10.7 ppg
d) 11.7 ppg

23. A semi is in 650 ft of water (.445 psi/ft) drilling without a riser. Air gap is 60 ft and
TD / TVD is 1350 ft RKB. What is the BHP during connections?

a) 450 psi
b) 474 psi
c) 550 psi
d) 574 psi
WELL CONTROL

24. What surface volume would 2 bbl of gas trapped in a sub sea BOP at 1900 ft water
depth have if released and allowed to migrate through the riser filled with 12.9 ppg
mud?

a) 45 bbls
b) 93 bbls
c) 157 bbls
d) 173 bbls

Air gap

Well depth
Water depth

25. A semi is drilling top hole with a riser and diverter installed connected to 30” casing.
Air gap is 70 ft, water depth is 1523 ft, sea water is .465 psi/ft, TVD / TD is 2250 ft
RKB and MW is 9.7 ppg.
What would be the reduction in BHP if the riser were lost or removed?

a) 30 psi
b) 65 psi
c) 95 psi
d) no reduction

26. hat increase in mud weight is required to offset this?

a) 1.34 ppg
b) 1.67 ppg
c) 2.23 ppg
d) 2.78 ppg
WELL CONTROL

27. The recommended response time for sub sea BOP is:

Rams to close in less than: seconds

Annular should not exceed: seconds

Time to unlatch LMRP should not exceed: seconds

28. How can gas trapped in a subsea BOP be safely circulated out?

29. By how much would BHP change if a well was inadvertently opened before
displacing riser to kill mud?
MW=10.4 ppg KMW=10.9 ppg water depth=1342 ft

a) 0 psi
b) 35 psi
c) 65 psi
d) 90 psi

30. How many (.115bbl/st) strokes will it take to displace a 16” x 5” riser/drillpipe
annulus (200 ft long)?

a) 290 strokes
b) 390 strokes
c) 490 strokes
d) 190 strokes
WELL CONTROL

31. The following drawing shows components of a subsea hydraulic control system. Each
component has a number. Place the number next to the component in the list provided.
WELL CONTROL

Using the schematic diagram of a hydraulic valve, answer the following question:

32. How many positions can the valve be placed in:

a. 2
b. 3
c. 4
d. 8

33. How many active ports does the valve have?

a. 2
b. 3
c. 4
d. 8
34. Can the valve be operated by:

a. manual function only


b. remote function only
c. air operated only
d. manual or remote function

35. What is the name of this valve?

a. Terminator
b. Selector
c. Manipulator
36. In the center or block position, the valve vents fluid lines
to tank.

a. True
b. false
WELL CONTROL

WELL DATA:

Well depth: 10,657 ft TVD RKB


12,000 ft MD
Air gap
Air gap: 60 ft
Water depth: 2150 ft
Sea water gradient: .445 psi/ft
Mud weight: 13.3 ppg Well depth
Water depth

37. What mud weight increase is required to balance the well if the riser is to be
removed?

a. 2.4 ppg
b. 5.1 ppg
c. 1.3 ppg
d. 13.3 ppg

38. A BOP drill was conducted and the well shut in on the upper annular preventer. If
the choke line is filled with sea water and the fail safe valves are opened, what
would be the the casing pressure read?

a. 545 psi
b. 945 psi
c. 60 psi
d. 245 psi

39. if the riser is lost in bad weather, what would be the bottom hole pressure reduce
by?

a. 350 psi
b. 500 psi
c. 480 psi
d. 571 psi

40. If the riser had a collapse pressure of 500 psi, how far could the mud level fall
before seawater collapses the riser?

a. 1083 ft
b. 1183 ft
c. 1283 ft
d. 1383 ft
WELL CONTROL

41. If a function is made to close the hang off rams and your fluid counter continues to
register fluid movement after the correct closing volume has gone passed, what
would you consider doing? (1 answer)

a. Call the subsea engineer and let him sort it out


b. Close another set of rams
c. Put the operating unit into block position
d. Everything is OK, continue

42. To find ICP, you must add the choke line friction to the slow circulating rate:

a. True
b. False

43. The hydraulic fluid system used to operate the subsea BOP‟s consist of potable
water and additives.

a. True
b. False

44. The rig has an air gap of 80 ft. If the riser has a collapse pressure of 450 psi, how
far would the mud level fall before it collapse if you are working in 1600 ft of .445
psi/ft of sea water?

a. 1091 psi
b. 1191 psi
c. 1291 psi
d. 1391 psi

45. Using the following data, calculate the expanded gas volume that would be at
surface if 2 barrels of gas had remained trapped under the rams and was released
into the riser when the well was opened back up after a successful operation?

Well data:
Choke line length: 1500 ft
Riser length: 1480 ft
Kill mud weight: 12.5 ppg
Drilling mud: 11.2 ppg
Atmospheric pressure: 14.7 psi

a. 113 bbls
b. 123 bbls
c. 133 bbls
d. 143 bbls
WELL CONTROL

46. Calculate the usable fluid in a 10 gallons bottle if the maximum pressure is 3000
psi, the mimimum is 1500 psi and the pre charge is 1000 psi?

a. 5.00 gals
b. 3.34 gals
c. 6.63 gals
d. 1.73 gals

47. If accumulator bottles were taken to the seabed with the same precharge as
surface bottles, what effect would this have on the usable fluid?

a. Increase
b. Decrease
c. Same volume as surface volume
WELL CONTROL

EXERCISE # 10

1. When using the choke to adjust pressure it is the Casing (Annulus) gauge that reacts to
the adjustment before the Drill Pipe Gauge.

a) True
b) False

2. The choke is used to adjust Casing (Annulus) pressure, but to adjust the Drill Pipe
pressure you have to change the pump rate.

a) True
b) False

3. The Casing (Annulus) gauge is always slower to react to any choke adjustment then the
Drill Pipe Pressure.

a) True
b) False

4. The wait and weight method will always result in lower casing shoe pressures.

a) True
b) False

5. The wait and weight will result in lower casing shoe pressure if the open hole volume is
less than the drill pipe capacity.

a) True
b) False

6. The Driller‟s method of well control will result in higher casing shoe pressures if the open
hole volume is less than the drill pipe capacity.

a) True
b) False

7. The Driller‟s method of well control will result in the same pressure on the casing shoe if
the open hole volume is less than the drill pipe capacity.

a) True
b) False
WELL CONTROL

8. Place the following statements in the correct order if you are using the Driller‟s Method.
The well is already shut in.

NOTE : There are 3 INCORRECT statements in the list.

a) Bring pump up to kill speed holding casing pressure constant.

b) Maintain casing pressure constant until kill mud is at the bit.

c) Maintain pumping pressure constant until influx is out.

d) Maintain drill pipe pressure constant until kill mud reaches surface.

e) Shut-in the well and check both SICP and SIDPP are approximately equal.

f) Bring pump up to kill speed holding casing pressure constant.

g) Line up suction to kill mud.

h) Maintain casing pressure constant until kill mud is pumped to surface.

i) Maintain casing pressure constant for complete circulation.

j) Bring pump up to kill speed holding drill pipe pressure constant.

k) Shut in well and check for zero shut in pressure.

Place your answers in order below :

1st __________ 2nd ____________

3rd __________ 4th ____________

5th __________ 6th ____________

7th __________ 8th ____________


WELL CONTROL

9. Place the following statements in the correct order if you are using the Wait and Weight
to kill a well. The well is already shut in.

NOTE : There are 3 INCORRECT statements in the list.

a) Bring pump up to speed holding drill pipe pressure constant.

b) Allow drill pipe pressure to fall from ICP to FCP as kill mud is pumped to bit.

c) Bring pump up to speed holding casing pressure constant

d) Maintain drill pipe pressure constant as kill mud pumped from bit to surface.

e) Allow drill pipe pressure to fall gradually from ICP TO FCP as kill mud is pumped
from suction pit to shaker.

f) Shut down and check the well is dead.

1rst ________

2nd _________

3rd _________

4th _________

10. Which of the following statements are True or False concerning the Wait and Weight
method?

a. In the Wait and Weight method the casing pressure should be kept constant during 2 nd
circulation.

a) True
b) False

b. In the Wait and Weight method , annulus pressures are kept lower than with the Driller‟s
method.

a) True
b) False

c. In the Wait and Weight method there are less calculations compared to the Driller‟s
method.

a) True
b) False
WELL CONTROL

d. Only the Wait and Weight method the drill pipe pressure is held constant throughout.

a) True
b) False

e. In the Wait and Weight method the drill pipe pressure is held constant throughout.

a) True
b) False

f. In the Wait and Weight method the well is dead when you reach FCP.

a) True
b) False

g. In the Wait and Weight method the drill pipe pressure should read zero, after surface to
bit strokes have been pumped if you shut in the well.

a) True
b) False

h. The wait and weight method must be used if insufficient barite is on board.
a) True
b) False

i. The Wait and Weight method does not require you draw a graph or step down chart.

a) True
b) False

j. The Wait and Weight is the preferred method if MAASP is critical and the open hole
capacity is greater the drill string capacity.

a) True
b) False
WELL CONTROL

11. Based on the following information :

a. Will the Wait and Weight method give lower shoe pressures than the Driller‟s
method?

TVD = 10,000 ft
Shoe Depth = 8,830 ft
Surface to Bit Strokes = 1,629 stks
Bit to Shoe strokes = 1,304 stks
Bit to surface = 6,480 stks
SIDPP = 500 psi
SICP = 800 psi
Present Mud Wt. = 10.3 ppg
Kill Mud Wt. = 11.3 ppg
MAASP = 1,300 psi
Pit Gain = 30 bbls

Answer – Yes or No

b. Based upon same information above :

Will the Wait and Weight Method give lower surface pressures than the Driller‟s Method?

Answer – Yes or No

12. Company policy states “when killing a well you will always attempt to kill the well using a
method that minimizes the pressure on the stack and upper casing”.

Which method would you choose?

DRILLERS OR WAIT AND WEIGHT

13. Link the following by matching up the correct number to the correct letter.

1. One circulation lower annulus pressures.


2. Less calculations highest annulus pressures.
3. Most calculations moderate annulus pressures.

A. Driller Method
B. Concurrent Method
C. Wait and Weight method
WELL CONTROL

14. Which of the following statements are true ?

a. Surface line volume will affect the point at which kill mud will increase mud
hydrostatic on bottom.

b. Pump must be brought up to speed holding casing pressure constant

c. Surface line volume does not need to be considered when starting to kill a well

d. Maintain the drill pipe pressure constant when starting up the pump to kill speed.

TRUE STATEMENTS ARE____________________and ___________________________

15. Select one of the following statements that is TRUE concerning wellbore pressures
when circulating a gas influx to surface. (Drillers Method)

a. So long as the correct kill procedures are followed that part of the wellbore which is
above a gas influx will have a constant pressure.

b. So long as the correct kill procedures are followed that part of the wellbore which is
below a gas influx will have a constant pressure.

c. So long as the correct kill procedures are followed that part of the wellbore which is
below a gas influx will have an increasing pressure.

16. From the statements A to F below, place 3 of them correctly in the blanks provided :

A - Drillers

B - Bring pump up to speed holding drill pipe pressure constant

C - Constant bottom hole pressure

D - Concurrent

E - Bring the pump up to speed holding the casing pressure constant

F - Drill pipe pressure constant

The main principle of well killing methods is to maintain _____________________

The most common methods are the Wait and Weight and ____________________ method

In both methods you must ______________________ when starting up.


WELL CONTROL

17. Which one of the following statements is true concerning wellbore pressure during the 1 st
circulation of the Driller‟s method?

a. Pressure at any point above a gas influx is constant.

b. Pressure at any point above a gas influx is decreasing.

c. Pressure at any point above a gas influx is rising.

d. Pressure at any point below a gas influx is decreasing.

e. Pressure within a gas bubble remains constant.

18. A gas is being circulated up the hole during a kill operation what effect will this have on
the pressures at the various locations listed.

EFFECT IN PRESSURE

LOCATIONS Increase Decrease Stays the Increase at first


same Then remains
constant

Gas Bubble
Surface Casing
Gauge

Casing shoe

Bottom Hole
At any point
below gas
bubble
At any point
above Gas
bubble
WELL CONTROL

19. While killing the well on the 1st Circulation of the Driller‟s method, the drill pipe pressure
is 1,200 psi at 30 spm. Casing pressure is 1,000 psi. Very quickly the drill pressure
increases to 1,500 psi but no change in casing pressures. Pump rate still holds at 30.

You decide to open the choke to bring the drill pipe pressure back to 1,200 psi with 30 spm.

What has happened to bottom hole pressure ?

a. Increase
b. Decrease
c. Stay in the same.

20. In the previous example you decided to stop the pump and close the choke before
making a decision. You think that the nozzles may be blocking. What would you do?

a. Start pump up to 30 spm and manipulate choke to get 1,200 psi on drill pipe.
b. Start pump up to 30 spm holding the choke pressure constant. Once pump is up to
speed note the drill pipe pressure and hold that constant for rest of 1st circulation.
c. Increase mud weight by an amount equal to 300 psi.
d. By using the spm versus pump pressure equation the spm for 1,500 psi would be 34
spm. Therefore you bring pump up to 34 spm and adjust choke to obtain 1,500 psi
drill pipe pressure.

21. During the second circulation of the Driller‟s method you hold drill pipe pressure constant
until kill mud is at the bit. What would happen to bottom hole pressure ?

a. Increase
b. Decrease
c. Stay the same

22. During the first circulation of the Driller‟s method you decided to hold casing pressure
constant. What would happen to bottom hole pressure ?

a. Increase
b. Decrease
c. Stay the same

23. During the second circulation of the Driller‟s method you decide to hold casing pressure
constant until kill mud is at the bit. What would happen to bottom hole pressure ?

a. Increase
b. Decrease
c. Stay the same
WELL CONTROL

24. Below is a list of problems. Match the cause to the problem.

PROBLEM CAUSE

a. Both gauges falling 1. Choke plugging


b. Both gauges rising 2. Bit plugging
c. D.P. gauges rising 3. Choke washout
d. D.P. gauge falling 4. Nozzle / pipe washout

a. matches _____________________________

b. matches _____________________________

c. matches _____________________________

d. matches _____________________________

25. Which of the following pressures do not increase with gas migration ?

a. Bottom hole pressure


b. Casing shoe pressure
c. Shut in casing pressure
d. Gas bubble pressure
WELL CONTROL

25. The following graphical diagrams show the approximate changes in pressure at certain
points in the well during the Wait and Weight method.

a. Surface casing pressure


b. Casing shoe pressure
c. Bottom hole pressure
d. Drill pipe pressure

NOTE / Pressure reading are not drawn to scale.

Answer:

Answer:

Answer:
WELL CONTROL

Answer;
WELL CONTROL

EXERCISE # 11
Well Data:

Measured depth: 15,500 ft


TVD: 15,000 ft
Hole size: 8½“
Air gap: 70 ft
Water depth: 1,000 ft
Drill collars 6 ½: 1,000 ft

Capacities:

Drill pipe capacity: 0.01776 bbl/ft


Drill pipe metal displacement: 0.00650 bbl/ft
Drill pipe closed end displacement: 0.02426 bbl/ft
HWDP (1000 ft) 0.0088 bbl/ft
Drill collar capacity: 0.00768 bbl/ft
Choke line (1100 ft): 0.006 bbl/ft
Marine riser: 0.39 bbl/ft

Annular capacities:

Open hole / drill collar: 0.0292 bbl/ft


Open hole / drill pipe: 0.0459 bbl/ft
Casing / drill pipe: 0.0505 bbl/ft

Pre-recorded data:

Current mud weight: 16.0 ppg


Casing 9 5/8 – 47 ppf set at (MD/TVD): 9,000 ft
Fracture gradient at shoe: 0.91 psi/ft
SCR @ 40 SPM ( riser) 500 psi
SCR @ 40 SPM ( choke line) 750 psi
Pump output: 0.119 bbl/stk
Surface lines: 17 bbls

Kick data:

SIDPP: 100 psi


SICP: 350 psi
Pit gain: 10 bbls
WELL CONTROL

1. What is the MAASP?

a. 402 psi
b. 502 psi
c. 602 psi
d. 702 psi

2. What is the MAMW?

a. 16.5 ppg
b. 17.5 ppg
c. 18.5 ppg
d. 19.5 ppg

3. How many strokes does it take to pump from surface to bit?

a. 1954 strokes
b. 2054 strokes
c. 2154 strokes
d. 2254 strokes

4. How many strokes does it take to pump from bit to shoe?

a. 2367 strokes
b. 1384 strokes
c. 2732 strokes
d. 1199 strokes

5. How many strokes does it take to complete one circulation through the choke line?

a. 7940 strokes
b. 5234 strokes
c. 9876 strokes
d. 3576 strokes

6. How many strokes are required to displace the riser?

a. 4382 strokes
b. 6523 strokes
c. 1363 strokes
d. 3.506strokes

7. What kill mud weight is required?

a. 16.13 ppg
b. 17.13 ppg
c. 18.13 ppg
d. 19.13 ppg
WELL CONTROL

8. What is the ICP?

a. 400 psi
b. 500 psi
c. 600 psi
d. 700 psi

9. What is the FCP?

a. 504 psi
b. 604 psi
c. 306 psi
d. 806 psi

10. What is the MAASP after killing the well?

a. 456 psi
b. 756 psi
c. 641 psi
d. 985 psi

11. What is the initial dynamic pressure?

a. 50 psi
b. 100 psi
c. 150 psi
d. 200 psi

12. What informations are essential to calculate the fracture pressure of a leak off test?

a. The capacity of the drill string


b. The TVD of the casing shoe
c. The presence of a float in the string
d. The pore pressure of the formation being tested
e. The mud density
f. The TVD of the well
g. The Annular pressure losses
h. The MD of the casing
i. The accurate hole capacity
WELL CONTROL

EXERCISE # 14
Use the Well Data to answer the questions.

WELL DATA

Well Depth 7,500 ft TVD


12,000 ft MD
Kick Off Point 4,000 TVD / 4,000 MD
End Of Build 5,500 TVD / 7,000 MD
Bit size 8.5”
Drill Pipe 5” OD. 19.5 lbs/ft
Capacity = 0.01776 bbls/ft
Heviwate 5” OD x 3” ID x 1500 ft
Capacity = .009 bbls/ft
Drill Collars 61/2” x 213/16” x 700 ft
Capacity = 0.008 bbls/ft
Casing 95/8”, 47 lb/ft. P110 8.681” ID
100% Internal yield = 10,900 psi
Set at 5,050 ft TVD / 5,500 MD
Choke Line 1,000 ft – Capacity: .008 bbls/ft
Riser 1,000 ft – Riser / DP: .335 bbls/ft
Formation strength test 1,800 psi w/ 11.5 ppg
Mud weight in use 12.5 ppg.
Surface Volume 1,000 bbls
Pumps National triplex 12-P-160
With 51/2” Liners
Capacity = 0.088 bbls/stk

PUMP PRESSURE

Slow Pump Rate Riser 700 psi at 40 spm


CLFL 250 psi at 40 spm

ANNULAR VOLUMES

Drill pipe/HW - Casing = 0.0505 bbls/ft


Drill pipe/HW - Open hole = 0.0459 bbls/ft
Drill collars - Open hole = 0.03 bbls/ft

WELL CONTROL DATA

SIDPP = 800 psi


SICP = 900 psi
GAIN = 20 bbls

You are recommended to complete a kick sheet to answer the following questions:
WELL CONTROL

1. What is the Initial Circulating Pressure at 40 spm?

2. What is the Final Circulating Pressure?

3. What Kill Mud weight is required?

4. What is the Maximum allowable fluid density?

5. What is the MAASP with the current mud weight?

6. How many strokes are required to pump kill mud from surface to KOP?

7. What is the pressure reduction per 100 strokes surface to KOP?

8. How many strokes are required to pump kill mud from KOP to EOB?
WELL CONTROL

9. What is the pressure reduction per 100 strokes KOP to EOB?

10. How many strokes are required to pump kill mud from EOB to bit?

11. What is the pressure reduction per 100 strokes EOB to bit?

12. When kill mud reaches the KOP, what is the circulating pressure?

13. When kill mud reaches the EOB, what is the circulating pressure?

14. If the well had to be shut in when kill mud reaches the KOP, what would be the
SIDPP?

15. What is the drill string volume?

16. What is the total strokes to pump kill kud to the bit?
WELL CONTROL

17. What is the marine riser – DP capacity?

18. Approximately, how many strokes are required to fill the choke line?

19. What should be the approximate pressure on the casing gauges when the
pump reaches 40 SPM?

20. What is the MAASP with the current mud weight (dynamic conditions)?
WELL CONTROL

EXERCISE # 15
Use the Well Data to answer the questions.

WELL DATA

Well Depth 10,000 ft TVD


14 ,000 ft MD
Kick Off Point 3,500 TVD / 3,500 MD
End Of Build 4,000 TVD / 4,500 MD
Bit size 8.5”
Drill Pipe 5” OD. 19.5 lbs/ft
Capacity = 0.01776 bbls/ft
Drill Collars 61/2” x 213/16” x 500 ft
Capacity = 0.007 bbls/ft
Casing 95/8”, 47 lb/ft. P110 8.681” ID
100% Internal yield = 10,900 psi
Set at 6,000 ft TVD / 7,000 MD
Choke Line 580 ft – Capacity: .008 bbls/ft
Riser 580 ft – Riser / DP: .335 bbls/ft
Formation strength test 1,500 psi w/ 9.8 ppg
Mud weight in use 10 ppg.
Surface Volume 274 bbls
Pumps National triplex 12-P-160
With 6” Liners
Capacity = 0.099 bbls/stk

PUMP PRESSURE

Slow Pump Rate Riser 520 psi at 40 spm


CLFL 100 psi at 40 spm

ANNULAR VOLUMES

Drill pipe/HW - Casing = 0.0489 bbls/ft


Drill pipe/HW - Open hole = 0.0459 bbls/ft
Drill collars - Open hole = 0.03 bbls/ft

WELL CONTROL DATA

SIDPP = 500 psi


SICP = 650 psi
GAIN = 11 bbls

You are recommended to complete a kick sheet to answer the following questions:
WELL CONTROL

1. What is the Initial Circulating Pressure at 40 spm?

2. What is the Final Circulating Pressure?

3. What Kill Mud weight is required?

4. What is the Maximum allowable fluid density?

5. What is the MAASP with the current mud weight?

6. How many strokes are required to pump kill mud from surface to KOP?

7. What is the pressure reduction per 100 strokes surface to KOP?

8. How many strokes are required to pump kill mud from KOP to EOB?
WELL CONTROL

9. What is the pressure reduction per 100 strokes KOP to EOB?

10. How many strokes are required to pump kill mud from EOB to bit?

11. What is the pressure reduction per 100 strokes EOB to bit?

12. When kill mud reaches the KOP, what is the circulating pressure?

13. When kill mud reaches the EOB, what is the circulating pressure?

14. If the well had to be shut in when kill mud reaches the KOP, what would be the
SIDPP?

15. What is the drill string volume?

16. What is the total strokes to pump kill kud to the bit?

17. What is the marine riser – DP capacity?


WELL CONTROL

18. Approximately, how many strokes are required to fill the choke line?

19. What should be the approximate pressure on the casing gauges when the
pump reaches 40 SPM?

20. What is the MAASP with the current mud weight (dynamic conditions)?

You might also like