Professional Documents
Culture Documents
BH - Gabrielle
BH - Gabrielle
CONTRACT OF WORKS
# of End Unit 2
# of Inside Unit 4
Activity
END UNIT
Unit Cost Unit
Quantity AMOUNT
Conditions:
1. Cleaning of working area should be done regularly.
2. Punchlist will be charged to the contractor.
Accepted by:
Contractor
EHPI Development Corporation
acific Hill, Brgy. Palo-Alto, Calamba, Laguna
CONTRACT OF WORKS
Date: 3/10/2008
w/ 2% tax
Amount Amount wt %age
INSIDE UNIT TOTAL COST
Quantity AMOUNT 6
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
PROGRESS BILLING
Construction of Patricia Conventional
ROMMEL SAPNU EDISON CORPUZ MARSHLOUIE ESPIRITU DOROTEO POLVENAR ANTHONY GONZALES
Housing in Charge Precast-in-charge Land Development Supervisor Contractor Project Officer In-Charge
CORPORATE HOLDINGS MANAGEMENT, INC.
GROUP OF COMPANIES
CHMI Land Inc. EHPI Development Corp.
Sunfields Realty Dev. Inc. Tiera Alegre Realty Dev. Inc.
PROGRESS BILLING
Construction of Patricia Conventional
ROMMEL SAPNU EDISON CORPUZ MARSHLOUIE ESPIRITU DOROTEO POLVENAR ANTHONY GONZALES
Housing in Charge Precast-in-charge Land Development Supervisor Contractor Project Officer In-Charge
CORPORATE HOLDINGS MANAGEMENT, INC.
GROUP OF COMPANIES
CHMI Land Inc. EHPI Development Corp.
Sunfields Realty Dev. Inc. Tiera Alegre Realty Dev. Inc.
CONTRACT OF WORKS
Construction of Gabrielle
genworx
400 250
GENERAL CONSTRUCTION WORKS
1 LAYOUT AND STAKING 1 2 0.25 225.00
2 EXCAVATION 4 2.75 2,750.00
3 FABRICATION AND SETTING OF FOOTING REBARS 1 1 1 650.00
4 FABRICATION AND SETTING OF GF COLUMN REBARS 1 1 1 650.00
5 GRAVEL BEDDING, LEVELING & COMPACTION 2 0.75 375.00
6 PLUMBING ROUGH-IN WITH EXCAVATION 1 1 1 650.00
7 ELECTRICAL ROUGH-IN 1 1 1.5 975.00
8 CONCRETING OF COLUMN FOOTINGS 1 2 1 900.00
9 CONCRETING OF WALL FOOTINGS 1 3 1 1,150.00
10 SLAB ON FILL (MANUAL CONCRETING) 1 4 1 1,400.00
11 FABRICATION AND SETTING OF COLUMN FORMS (GF) 1 1 1 650.00
12 CONCRETING OF GF COLUMNS 1 3 1 1,150.00
13 SETTING OF SCAFFOLDINGS 1 2 3.75 3,375.00
14 DISMANTLING OF COLUMN FORMS (GF) 1 1 1 650.00
SETTING AND DISMANTLING OF ALIGNERS WITH BATTERBOARD
15 1 1 1 650.00
(GF)
PPB PANEL INSTALLATION AND CUTTING OF OPENINGS (GF)
16 including CR 2 4 1 1,800.00
17 FABRICATION AND SETTING OF 2ND FLOOR BEAM REBARS 1 1 2.75 1,787.50
18 FABRICATION AND SETTING OF BEAM FORMS (2F) 1 1 1.5 975.00
19 CONCRETING OF 2ND FLOOR BEAMS 1 4 1 1,400.00
20 DISMANTLING OF BEAM FORMS 1 1 1 650.00
21 INSTALLATION OF T-JOIST 1 5 0.5 825.00
22 INSTALLATON OF 2ND FLOOR SLAB FORMS 1 1 1 650.00
23 INSTALLATION OF WIREMESH 1 1 0.25 162.50
24 CONCRETING OF SECOND FLOOR SLAB 1 4 1 1,400.00
25 FABRICATION AND SETTING OF SF COLUMN REBARS 1 1 1 650.00
26 FABRICATION AND SETTING OF COLUMN FORMS (SF) 1 1 1.25 812.50
27 CONCRETING OF SF COLUMNS 1 4 0.75 1,050.00
28 DISMANTLING OF COLUMN FORMS SF 1 1 0.5 325.00
29 PPB PANEL INSTALLATION AND CUTTING OF OPENINGS (2F) 2 6 2 4,600.00
30 FABRICATION AND SETTING OF ROOF BEAM REBARS 1 3 3 3,450.00
31 FABRICATION AND SETTING OF ROOF BEAM FORMS 1 1 1 650.00
32 CONCRETING OF ROOF BEAMS 1 4 0.75 1,050.00
33 DISMANTLING OF ROOF BEAM FORMS 1 1 0.5 325.00
34 PPB GRINDING 2 3 1,500.00
35 LANKO APPLICATION 2 1 4.5 4,725.00
36 EDGING (WINDOW OPENING,FIREWALL,CANOPY,ETC) 1 1 3 1,950.00
DOORS AND WINDOW MOULDINGS (FABRICATION AND
37 INSTALLATION) 1 1 2 1,300.00
38 CONCRETING OF KITCHEN COUNTER 1 1 400.00
39 ROOF FRAMING (PURLINS & TUBULAR) 1 1 2 1,300.00
40 INSTALLATION OF FASCIA BOARDS 1 1 1.25 812.50
41 FABRICATION & INSTALLATION OF GUTTERS & FLASHING 1 1 1.5 975.00
42 INSTALLATION OF ROOF SHEETS & RIDGE ROLLS 1 1 2 1,300.00
43 INSTALLATION OF WINDOWS 1 1 1.25 812.50
44 INSTALLATION OF DOORS & LOCKSET 1 1 400.00
45 INSTALLATION OF GF & SF CEILING FRAMES -
46 INSTALLATION OF GF & SF CEILING BOARDS -
47 INSTALLATION OF CR CEILING & CEILING EAVES FRAMES 1 1 2.5 1,625.00
48 INSTALLATION OF CR CEILING & CEILING EAVES BOARDS 1 1 2.5 1,625.00
49 PAINTING OF EXTERIOR (1ST COATING -FLAT) 2 3.5 2,800.00
50 PAINTING OF EXTERIOR (FINAL COATING) 2 3.5 2,800.00
51 PAINTING OF GF & SF CEILING -
52 PAINTING OF CR CEILING & CEILING EAVES 2 2.5 2,000.00
53 PAINTING OF DOORS 1 1 400.00
54 KITCHEN COUNTER TILING AND GROUTING 1 1 400.00
55 CR TILING AND GROUTING 1 4 1,600.00
56 PPB FOR STAIR LANDING (INCLUDING PLASTERING) 1 1 1 650.00
57 FABRICATION & INSTALLATION OF STRINGERS 1 1 1 650.00
58 INSTALLATION OF STAIR STEPS (PRE CUT) 1 1 400.00
FABRICATION & INSTALLATION OF RAILINGS INCLUDING
59 1 1 1.5 975.00
PAINTING
FABRICATION & INSTALLATION OF CANOPY FRAME, WITH
60 FASCIA, 1 1 1 650.00
ROOF SHEET AND FLASHING
INSTALLATION OF CEILING FRAMES & PAINTING OF FASCIA &
61 CEILING OF CANOPY 1 2 800.00
62 FABRICATION & INSTALLATION OF DOWNSPOUTS 1 1 400.00
63 CHB FOR CATCH BASINS 1 1 1 650.00
64 FABRICATION & SETTING OF CATCH BASIN STEEL GRATINGS -
65 EXCAVATION OF SEPTIC TANK 1 1.5 375.00
SETTING OF SEPTIC TANK (INCLUDING PIPES FOR IN & OUT
66 CONNECTING TO DRAINAGE, & SLAB ON FILL) 1 1 1 650.00
67 CONCRETING OF SERVICE AREA (DOOR STEP) 1 1 0.25 162.50
68 METER CENTER (Fabrication & Installation of rebars) 1 1 2.5 1,625.00
69 BACKFILLING(INSIDE & OUTSIDE) 2 1 500.00
INSTALLATION OF WIRING AND ELECTRICAL FIXTURES
70 1 4 1,600.00
(Including feeder line)
71 INSTALLATION OF PLUMBING FIXTURES 1 1 400.00
72 HAULING OF MATERIALS 3 3 2,250.00
73 GENERAL CLEANING 2 1 500.00
PREVIOUS PAYMENT
NET AMOUNT COLLECTIBLE
Note: 1. Once the contract was re-contracted to the new contractor, the previous contractor has no right to claim the punchlist and retention of what he had finish.
2. 5% Punchlist will be released atleast 98% accomplishment of the contract, 5% Retention will be release upon 100% accomplishment 1 year after to the last
3. The company has the right to nuliffy or cancel the contract as per contractor's failure to comply with the rules and regulations.
4. Punchlist and retention will be void as per contractors failure to finish the contract
Prepared by: Conforme: Checked by:
CONTRACT OF WORK
Construction of Gabrielle
Manpower
ACTIVITY Skilled Labor # of Days Total Cost
400 250
CONTRACT OF WORK
Construction of Gabrielle
Manpower
ACTIVITY Skilled Labor # of Days
500 409
DIRECT LABOR
CONTRACTOR'S PROFIT (10%)
TOTAL CONTRACT AMOUNT
.
:
:
:
:
:
Total Cost
329.50
4,499.00
909.00
909.00
613.50
909.00
1,363.50
1,318.00
1,727.00
2,136.00
909.00
1,727.00
4,942.50
909.00
909.00
2,636.00
2,499.75
1,363.50
2,136.00
909.00
1,272.50
909.00
227.25
2,136.00
909.00
1,136.25
1,602.00
454.50
6,908.00
5,181.00
909.00
1,602.00
454.50
2,454.00
6,340.50
2,727.00
1,818.00
500.00
1,818.00
1,136.25
1,363.50
1,818.00
1,136.25
500.00
-
-
2,272.50
2,272.50
3,500.00
3,500.00
-
2,500.00
500.00
500.00
2,000.00
909.00
909.00
500.00
1,363.50
909.00
1,000.00
500.00
909.00
-
613.50
909.00
227.25
2,272.50
818.00
2,000.00
500.00
3,681.00
818.00
114,850.50
11,485.05
126,335.55