You are on page 1of 10

PREPARED

BY PTT PUBLIC COMPANY LIMITED


CHECKED
BY ONSHORE COMPRESSOR STATION 4
PROJECT
APPROVED
BY
CERTIFIED
(PTT)
REV. DATE REVISED APPROVED DESCRIPTION
NO. BY BY
D1 18-Feb-08 ISSUED FOR ITB
D2 11-Jun-08 ISSUED FOR ITB

SPECIFICATION FOR

PNEUMATIC TEST

SPC-0804.02-96.59 REV.D2
TOTAL 10 PAGES

.
AREA CODE OF SITE LOCATION

GENERAL AREA: 010


PTT PLC. CONTRACT NO. PTT PLC. PROJECT NO.

0804.02
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 2 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

CONTENTS

SECTION

1.0 GENERAL 3

2.0 PNEUMATIC TESTING 4

3.0 TEST MEDIUM 5

4.0 TEST PRESSURE 5

5.0 BLINDS FOR PRESSURE TEST 5

6.0 TEST PACK PREPARATION 6

7.0 TESTING PREPARATIONS 7

8.0 PNEUMATIC TEST PROCEDURE 8

10.0 SAFETY 9
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 3 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

1.0 GENERAL

1.1 Purpose

This Specification prescribes minimum requirements on pneumatic test


procedure and acceptance criteria of piping works.

1.2 Scope of Application

This specification covers all related activities of work to be performed for


project by CONTRACTOR on piping construction works.

1.3 Definition

1.3.1 Category D Fluid Service (per ASME B31.3) – A fluid service in which all the
following apply:
(1) The fluid hanged is nonflammable, nontoxic, and not damaging to
human tissues.
(2) The design gauge pressure does not exceed 10.35 bar.
(3) The design temperature is between -29°C and 186°.

1.3.2 Category M Fluid Service (per ASME B31.3) – A toxic fluid service in which
exposure to very small quantities of the fluid in the environment can produce
serious irreversible harm to persons on breathing or bodily contact, even when
prompt restorative measures are taken.

1.3.3 Damaging to Human Tissues (per ASME B31.3) – A fluid which, under
expected operating conditions, can harm skin, eyes, or exposed mucous
membranes so that irreversible damage may be done unless prompt restorative
measures are taken.

1.3.4 Calculated Test Pressure – the test pressure determined in accordance with
paragraph 4.0

1.3.5 Deleted

1.3.6 Deleted

1.3.7 Design pressure – The pressure of each component in a piping system which is
not less than the pressure at the most severe condition of coincident internal
or external pressure (minimum or maximum) expected during service.

1.3.8 Test pressure – The pressure does not exceed stress intensity of yield strength
of each component in a piping system at test temperature and should not be
lower than design pressure.

1.4 References

1.4.1 Related Code and Standards


(1) ASME B31.3 Process Piping
(2 ASME SECTION IX “Welding and Brazing Qualifications”
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 4 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

(3) ASME SECTION XIII Div 2, AT-502

1.4.2 Related Specifications and Procedure


Following specification shall be as a supplementary to this specification and
Procedure.
(1) Piping Construction (SPC-0804.02-96.51)
(2) Hydrostatic Pressure Test (SPC-0804.02-96.58)
(3) Internal Cleaning of Piping (SES-PR.Q2-99-0204.10-3500-013)

1.5 Units

SI unit shall be used as the measurement system for the drawings and
document to be submitted. However, nominal sizes of piping component shall
be in accordance with inch system, which abbreviation in (B)

2.0 PNEUMATIC TESTING

2.1 Circuit Monitoring and Checking

For pneumatic testing of circuits, access to the area of the test shall be limited
to only the personnel directly involved in the test or personnel involved in the
inspection and monitoring.

During the pressure test the total circuit shall be inspected and tested for any
leaks. If any leaks are found on flanged, threaded, plugged or welded joints the
system pressure shall be totally released prior to any rectification work
starting. Disciplinary action shall be taken against any individual and/or
supervisor authorizing and/or undertaking work on the pressurized system.

For flanged joint testing during pneumatic testing of circuits the flange joints
shall be hermetically sealed by means of adhesive paper tape and a pinhole
made in the tape to permit easy detection of leaks.

2.2 Circuit Monitoring and Checking

The following equipment and components shall not be included in the system,
and this equipment shall be isolated from the test section.

2.2.1 Rotating equipment such as pumps, compressors and turbines.

2.2.2 Safety valves rupture discs, flame arrestor, and stream traps.

2.2.3 Pressure vessels with sophisticated internals.

2.2.4 Equipment and piping lined with refractoriness.

2.2.5 Storage tanks.

2.2.6 Filters, if filter element(s) is not dismantled.

2.2.7 Heat exchangers of which tube sheets and internals have been designed for
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 5 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

differential pressure between tube side and shell side.

2.2.8 Instrument such as control valves, pressure gages, level gages, and flow
meter. (Excluding thermocouples)

2.3 Exclusions

The followings are excluded from the testing requirements of this specification
:

2.3.1 Any package unit previously tested by the vendor in accordance with the
applicable codes.

2.3.2 Plumbing systems, which are tested in accordance with the applicable
plumbing codes.

2.3.3 Lines and systems which are open to the atmosphere such as drain, vents,
open discharge of relief valve, and atmospheric sewers.

3.0 TEST MEDIUM

The gas used as test medium shall use the nonflammable and nontoxic gas
such as N2 or inert gas, if not compressed air.

4.0 TEST PRESSURE

The test pressure shall be 110% of design pressure and according to test
pressure in line list SES-SH-50-0204.10-3500-01-A2. Equipment for testing
(referred to sketch in appendix II) should be have as following;

1) Air Compressor
2) Flexible hose
3) Calibrated Pressure gauge
4) Oil filter
5) Temporary piping set
6) N2 cylinder, if required
7) Safety valve

Note: Safety valve required for pneumatic testing, rapid opening or pop action
of over pressure, should be installed and connected with an adequate
system of piping not containing valve which can isolate tested system.

5.0 BLINDS FOR PRESSURE TEST

5.1 Plain test blanks shall be used with 3mm flat asbestos gaskets for blanking flat
face, and raised face. Provide full face blanks and gaskets for Class 150
connections. However, where permanent operational blinds are installed, they
may be used for pressure testing, provided they are rated the testing pressure
as per Appendix I.
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 6 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

5.2 Plate material, extra length bolts and gaskets, which are made at the Job Site
could be used the testing. Maximum allowable testing pressure for test blinds
refer to Appendix I.

5.3 Temporary spades and blanks installed for testing purposes shall be designed
to withstand the test pressure without distortion. Temporary test spades and
blanks shall be readily identifiable by painting a red color on the handle.

5.4 For ring joint flanges, spare ring joints shall be required as they are to be used
only once.

6.0 TEST PACK PREPARATION

6.1 General

6.1.1 CONTRACTOR will prepare a marked up of P&ID indicating the test limits.

6.1.2 From the marked up P&ID, Subcontractor will divide the piping into suitable
Test Packs. The size of the packs may be revised by Subcontractor provided
that the specification for limits in Clause 6.2 below is complied with
CONTRACTOR shall be notified of such revisions and will authorize
Subcontractor to proceed of said revisions meet the specification.

6.2 Test Pack Limits

Subcontractor shall not test through equipment without CONTRACTOR’s


written approval.

6.3 Test Pack Format


(1) Pressure test report for piping
(2) Marked-up P&ID
(3) Blind check list
(4) Welding History Report and Welding Joint Marked ISO Drawing
(5) NDE report
(6) PWHT and Hardness test report
(7) Post-Test Punch List (CONTRACTOR + Client)
(8) Copies of reinforcing pad pressure test certificates. (if necessary)

6.3.1 Test Packs shall include the latest available revision of each isometric covering
the scope of the test.
(1) Test limits and highlight line to be tested.
(2) Size (thickness) and location of all test blinds and including those
required at instrument connection e.g. orifice flanges.
(3) Indentify location for the connection of the fill and drainage points for
the system.
(4) Vent points
(5) Deleted
(6) Location and range of pressure gauges to be used. Note that on large
piping systems and/or system with none return valves more than one
gauge may be required.
(7) Deleted
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 7 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

(8) If required, temporary supports shall also be indicated in the test pack.
(9) Any control valve, check valve, safety valves or other piping
accessories requiring removal, turning, or some other action should be
highlighted.

6.3.2 Test Packs shall also contain copies of P&ID’s marked-up to show at least the
following information:
(1) Piping Field Test Pack Number
(2) Specific Limits of that Test Pack Only
(3) Location of Test blinds, Isolation valve and Temporary piping.

6.4 Test Pack Approvals and Distribution

The “Original” pack shall be submitted to PTT/Consultant for review.

6.5 Field Revision Request (FRR)

CONTRACTOR’s Engineer shall check the status of the affected test pack and
advice subcontractor for test packs where pneumatic test completed.
CONTRACTOR will over-stamp the original test pack with “RETEST”. The re-
stamp original will then be returned to subcontractor under memorandum with
an instruction to carry out the retesting.

7.0 TESTING PREPARATIONS

7.1 All joints, including welds, shall be accessible and left uninstalled, unpainted
and exposed for examination during the test joints previously tested in
accordance with this specification may be insulated or covered.

7.2 Before testing

7.2.1 Piping systems shall have been completely checked for correctness.

7.2.2 All lines, vessels and equipment shall be checked to insure the entire system
can be completely drained after testing.

7.2.3 Temporary gaskets may be used, which are not the same as permanent
gaskets provided.
(1) Such use will not lead to damage of the flange faces.
(2) Temporary gaskets are removed immediately after completion of tests.

7.3 Short pieces of piping, which must be removed to permit installation of a blind
or blank, shall be tested separately.

7.4 Lines containing check valves shall have the source of pressure located in the
piping upstream of the check valve so that the pressure is applied under the
seat.

If this is possible, remove or jack open the check valve closure mechanism or
remove check valve completely and provide necessary spool piece or blinds. A
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 8 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

notation shall be included on the Punch List that check valve flapper has been
removed. Subcontractor shall install a new gasket wherever the check valve
bonnet has been disturbed. Where flappers have been removed, tagging shall
mark valves.

7.5 Test equipment to be used during testing shall have suitable capacity for the
range of test pressure required. The range of pressure gauges to be used shall
be with a minimum span of 1.5 times pressure and maximum span of 2 times
of test pressure.

7.6 All pressure gauges are to be calibrated specially for OCS #4 Project prior to
use. If gauges have been used previously on other projects or for other
purposes, they shall be recalibrated. Validation of gauges and chart recorders
shall be for a maximum of 90 days, however, recalibration shall be required if
the calibrated gauge/recorder is damaged or strained.

7.7 If the specified test duration exceeds 8 hours, then a chart recorder shall be
used to record test pressure.

7.8 Prior approval must be obtained from the CONTRACTOR and PTT/Consultant
to include vessels or inline equipment in the pressure test circuit.

8.0 PNEUMATIC TEST PROCEDURE

8.1 Prior testing start, Supervisor/Tester is to set up the exclusion zone, complete
with signs, three languages, prior to pressure being raised on the system. Also
marshals shall be positioned at all exclusion barriers to ensure no personnel
enter the exclusion zone.

8.2 During pneumatic testing care must be exercised not to exceed the specified
design pressure by more than ten (10) percent, also see Para. 2.1 (maximum
test pressure to ne marked on the Test pressure gauge, prior to pressurized the
system)

8.3 When pneumatic testing at over 2kg/Cm2, a preliminary check at 2kg/Cm2 shall
be made to locate major leaks. The pressure shall be increased in gradual steps
of 4kg/Cm2 or 10 percent of the test pressure, whichever is greater.

8.4 A double block and vent valve arrangement shall be included in the
pressurizing line to the system being tested. A test pressure gauge shall be
downstream of the double block. After each pressure step has been reached,
close the block valves and open vent valve to atmosphere. If after a 10
minutes period the “Step Pressure” has held, proceed to the next “Step
Pressure”. If not, examine the entire system for leakage.

8.5 The pressure shall be held at design pressure for 10 minutes prior to raising the
pressure to the test pressure. At test pressure shall be held for 30 minutes
during which time to access within the exclusion zone will be allowed.

8.6 After 30 mins the test pressure shall be reduced to design pressure at which
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 9 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

point access within the exclusion zone will be allowed to the testing team only
and the inspection of the joints shall be undertaken. All flange, threaded,
welded joints and attachment shall be inspected with a proprietary testing
solution. The design pressure shall be maintained until inspections of all joints
are completed.

8.7 Any leak identified shall be marked with marker pen and the system shall be
depressurized prior to any repair or rectification work being undertaken.

8.8 Depressurization of the system on completion of the inspection shall be by


nominated vent valves taking into consideration any none return valves
included within system.

8.9 All instrument shall be disconnected from the test system prior to the test
commencing.

9.0 REPORTS AND TEST RECORDS

9.1 As a minimum, the Subcontractor shall maintain records of all pressure tests,
records of all welding operations, including welder, numbers, and post weld
heat treatment charts referenced to weld numbers, records of all hardness
tests and records of all certification records.

9.2 All records shall be submitted and approved by the CONTRACTOR and shall be
submitted to the Client/Consultant.

9.3 All records shall be submitted and approved by the CONTRACTOR and shall be
submitted to the CLIENT/CONSULTANT.

10.0 SAFETY

10.1 General

10.1.1 Appointment of CONTRACTOR’s Test Controller who is in attendance and


responsible throughout the testing and inspects the welding during testing.

10.1.2 Appointment of the subcontractor’s test controller who will be responsible for
ensuring safe testing in accordance with the specification.

10.1.3 Display of safety warning signs to alert workers in the vicinity of the pressure
testing with line identification.

10.1.4 Pressure test training and maintenance of a competency register as required by


CONTRACTOR Safety plan.

10.1.5 Pressure rating for the test manifold and the test equipment and the required
inspection/testing.

10.1.6 The air in the subsystem shall be released slowly by means of opening the
SPC-0804.02-96.59
PTT PUBLIC COMPANY LIMITED PAGE: 10 OF 10
PNEUMATIC TEST ENGINEERING SPECIFICATION REV: D2

valves. The vent valves shall be left open until the pressure in the loop reaches
zero.

10.1.7 All of the CONTRACTOR and Piping Subcontractors Test Controllers must be
cautious when approaching flange joints & listen for escaping air.

You might also like