You are on page 1of 21

Drawing Status

Project Project Name Engineer In-Charge Drafters Updates @6 Jan 2020


Number
10125 ICH Chiong / P. Heng 3 EPS, 5 SL Refer attachment
Kwong

10135 OBV Sai Peng --> Chiong / Chin Ching --> Design dev't done.
Paramanathan

Mr.Wong Tasnim

Mr.Wong Tapan To issue all wall mould dwgs by 8/1

10147 Nursing Home Wen Kai Myo All drawings issued for production
(SJSM)

10148 Glory Jaric --> Vee Rafizah L32-39 issued for prod.
Pending L40-49 layout for drafing

10149 WHC Para --> now Jaric


Façade : Danny Mines 2: Sham
& Brn
SL: Surojit

Core walls : Fairuz 9 SKD drafters


Columns : Tan Win Mines 2:
Yong Shah,Farid, Loh

ST-slabs, Drop panel Wana


& beams : Jaric

10155 Skin Centre Sai Peng --> Arif / Manu, Jade


Paramanathan

4-sty L3 50% approved.


10-sty L3 rev & resubmitted on
13/12.
4-sty L4 submitted for approval .

10-sty L4 to submitted for approval


18/12.
10-sty L5 submitted for approval
6/1/2020
Satheesh L3 beams approved.
4-stry L4 pending
approval. L3 beam
connection detail submitted 13/12.
10-sty L4 to
submitted 17/12 10-sty L5 to
submit by 7/1

Rafizah L4 submitted for approval 20/12 L5


submitted for approval 20/12

10156 TUV Wen Kai Sham All completed

10157 HDB Eunos Ave Wen Kai Dwg until Lvl 6 subm Approved.
Rf not drawn yet as CAD file not
given (requested since Oct'19)

10158 Sports @ Sai Peng --> ? -


Canberra

10160 Anglo Chinese


School
-
10164 HDB - Bukit Wen Kai Yatanar HC only. Only roof pending approval
Batok
10165 Senior Care Pang Heng Kiong --> Yatanar
Centre (CMC) Chiong

10167 Punggol Town Wen Kai Abdul Kader All (except C49 and C50) L3 column
Hall (PTH) issued for prodn
L4 zone 4 columns pending approval
L4 zone 3 columns not yet drawn

Khilaluddin L5 not drawn yet

Stair A, B, C pending approval


Stairs D,E pending revision from EP
Stairs F sent for production

10168 NUS laboratory Jaric Wana

10169 FVCC Saiful Sukri Col: LVl 1 & Lvl2 issued for prodn; Lvl
3 pending approval. L4 dwg in
progress

ST2&3 issued for prodn.


ST1,4&5 submitted for apprv

HC: Level 2 issued for prod,


Level 3 pending approval
10170 RVCC - no one - -
10172 Parc Esta Saiful Alex , Nishanth
Stop drafting
10175 Zhengua School Wen Kai Design done, prod ongoing (st case
& beams bal)
AS-BUILT BY 22/11

10176 JTCWNC Saiful Asri Beam : Level 7 &8- for prod. Level
LR-shop dwg in progress(trgt issue by
ths week)

Col : Level 6 & 7 for prod. Level 8


issued for approval, Level LR in
progress

HC : Level 7 & 8 for prod.

Single-T : Level 8 issued for


production, LR issued for approval.

Myo, AO - Façade: Lvl 1: All Elevation issued for


façade production; Lvl 2-7(typical): 90%
elevation issued for production

ST7&8 issued for prodn; ST 4,5 & 6,7


issued for approval

10185 Factory @ Tuas Jaric --> Vee Rafizah -


South

10186 HDB @ Chua Jaric Rafizah -


Choo Kang
10187 Airtrunk Jun Tee -
10188 HDB Sengkang Jaric -
10189 SGA Wen Kai Typical HCS issued for production.

Jun Tee L2 Data hall,Gantry & Centre core


GL14 &15 beam issued for prod.

L2 Centre core gantry & Switchgear


beam pending approval

All L3 & L4 beams pending Arup


approval. They have no objection if
factory want start to cast L3 typical
beam, provided EP take the
risk/responsible.
10191 Shimano Factory Sai Peng ---> Vee Rafizah L4 &L5 pending approval

10192 ASM Wen Kai Rafizah

10193 Kranji camp Jaric ---> Vee Rafizah Resubmitted for approval on
3/1/2020 due to design loading
changed. Approval received on
4/1/2020. Preparing HCS panel
drawings based on latest layouts for
production.

10194 Equinix Danny Dwg completed

10195 Mayflower Vee Nora B L3 & 5 submitted for approval 23/12

10196 NTUC Vee Nora B/Tapan L3M-L7 pending approval.

10197 Potong Pasir Vee Nora B/Tapan Panel 2000-2008 issued for
production on 31/12/19. Remaining
panels are subjected to changes for
M&E opening positions, however still
pending revised M&E opening layout
based on consultant's comment.

10198 Bukit Merah Vee Tapan Dwg completed


Secondary
School

10199 Teck Whye Vee Tapan Dwg completed


Secondary
School

10200 SGA Phase 2 Param Tapan/ Jade Pending approval


10201 NUS Medical Param Jade To start drawing
Science Library

10202 Prakash Jade Pending consultant ACAD dwg

10203 Prakash Tapan Pending consultant ACAD dwg


Updates @13 Jan 2020 Updates @20 Jan 2020

Design dev't done.

Tasnim submit Tower A & B staircase


walls & flight shop dwgs for
production on 17.1.20.

Tower wall mould dwgs issued to Tower wall mould dwgs issued to
factory factory 8/1/20. Now Tapan preparing
Tower A walls shop dwgs for
approval & production.

All drawings issued for production

L40-49 Consultant dwg received on


10.1.2020

Refer attachment
4-sty L3 - 50% approved column & 4-sty L3 - 50% approved column &
balance pending approval. balance pending approval.
10-sty L3 - 50% approved 10-sty L3 - 90% approved
column & balance pending approval. column & balance pending approval.

4-sty L4 submitted & 4-sty L4 submitted &


pending approval. pending approval.
10-sty L4 10-sty L4
submitted on 18/12 & pending submitted on 18/12 & pending
approval. approval.
10-sty L5 submitted on 7/1/20 & 10-sty L5 submitted on 7/1/20 &
pending approval. 10- pending approval. 10-
sty L6 modelling in Tekla & preparing sty L6, L7 & L8 done modelling in
the drwgs & target for approval Tekla & prepared the drwgs. Now
submission next week. internal checking & amending
process. Target approval submission
on 22.01.2020
4-sty L3 - Beams approved. 10-sty L3 - 50% approved beams &
10-sty L3 - 50% approved beams & balance pending approval.
balance pending approval. 4-stry L4 - Comments by
4-stry L4 submitted & KH, on amending process. Target
pending approval. submission on 22.1.20.
10-sty L4 submitted 10-sty L4 -
on 17/12 & pending approval. Comments by KH, on amending
10-sty L5 still preparing process. Target submission on
the drwgs & target for approval 23.1.20. 10-sty L5 -
submission next week. Comments by KH, on amending
process. Target submission on
24.1.20. 10-sty L6, L7 & L8,
on modelling in Tekla & preparing
the drwgs. Target approval
submission by next week.

Lvl 4 submitted on 20/12 & pending Lvl 4 submitted on 20/12 & pending
approval. approval.
Lvl 5 submitted on 20/12 & pending Lvl 5 submitted on 20/12 & pending
approval. approval.
Lvl 6 preparing HCS layout& target Lvl 6 submitted on15/1 & pending
for approval submission next week. approval.
But waiting for CPB drawings more Lvl 7 submitted on 15/1 & pending
than 1 month+. approval. Lvl 8 preparing
HCS layout & target for approval
submission this week. But still
waiting for CPB from Lvl 5 -8
drawings more than 1 month+.

All completed

Dwg until Lvl 6 subm Approved.


Rf not drawn yet as CAD file not
given (requested since Oct'19)

HC only. Only roof pending approval


since June 19
Upper Roof façade- 1 elevation
oustanding

All (except C49 and C50) L3 column


issued for prodn
L4 zone 4 columns pending approval
L4 zone 3 columns not yet drawn

Stair A, B, C pending approval


Stairs D,E pending revision from EP
Stairs F sent for production
DESIGN AND DELIVERY COMPLETED
AS-BUILT GIVEN
PE endorsement not yet

1200 mm HCS issued for production,


split slabs pending IFC approval

L2 Data hall,Gantry & Centre core


GL14 &15 beam issued for prod.

Switchgear status B.
L2 Core Area remaining beams
pending IFC approval

Data hall, gantry beams all IFC


approved
L3 typical approved
L3 non typical & L4 pending status
A/B
L5 pending Approval

All issued for prodn

Pending approval for L3 & 5

L3M-L7 pending approval.

Pending approval for panel markings


2009-2021 at level 2. Submitted
layout and panel details for L3,5,6 for
approval on 7/1/2020.

Dwg completed

Dwg completed

Pending approval Pending for approval


Drawings in progress, target 2nd, 3rd & 4th Level HCS Installation
submission by this week. Layouts & Section drawings is
completed & also HCS Design Calc.
Today will submit for approval.

Consultant dwg received 13/1


Updates @27 Jan 2020

Design dev't done.

Now Tapan preparing Tower A & B


walls shop dwgs for approval &
production.
4-sty L3 - 95% approved column &
balance pending approval from Arup.
10-sty L3 - 95%
approved column & balance pending
approval.
4-sty L4 - 80%
approved column & balance pending
approval from Arup.
10-sty L4
submitted on 18/12/19 & pending
approval from Arup.
10-sty L5 submitted
on 7/1/20 & pending approval from
Arup. 10-sty L6, L7 &
L8 done modelling in Tekla &
prepared layout & details drwgs.
Now internal checking & amending
process. Target approval submission
on 27/1/20.
10-sty L3 - 95% approved column &
balance pending approval from Arup.
4-stry L4 -
Comments by KH, on amending
process. Target submission on
22.1.20.
10-sty L4 - Comments by KH,
on amending process. Target
submission on 23.1.20.
10-sty L5 - Comments by KH, on
amending process. Target submission
on 24.1.20. 10-sty L6, L7 &
L8, on modelling in Tekla & preparing
the drwgs. Target approval
submission by next week.

Lvl 4 submitted on 20/12 & pending


approval.
Lvl 5 submitted on 20/12 & pending
approval.
Lvl 6 submitted on15/1 & pending
approval.
Lvl 7 submitted on 15/1 & pending
approval. Lvl 8 preparing
HCS layout & target for approval
submission this week. But still
waiting for CPB from Lvl 5 -8
drawings more than 1 month+.
Pending for approval
2nd, 3rd & 4th Level HCS Installation
Layouts & Section drawings submit
already on 21/1/20. Pending for
approval or comments from
Contractor / Consultant.

You might also like