Professional Documents
Culture Documents
OWNER’S ENGINEER:
EPC CONSORTIUM
PROJECT:
Keppel Sakra Cogen 600MW Advanced Gas Turbine
Cogeneration Combined Cycle Plant
TITLE:
3.3 DRAINAGE.......................................................................................................11
3.4 ROADS.............................................................................................................14
4 LOADS....................................................................................................................15
4.1 DEAD LOADS ..................................................................................................15
5 LOAD COMBINATIONS..........................................................................................21
6 DEFLECTION AND STABILITY ..............................................................................21
6.1 DEFLECTIONS ................................................................................................21
6.2 STABILITY........................................................................................................22
6.2.1 OVERTURNING..................................................................................................22
6.2.2 SLIDING..............................................................................................................22
7 STRUCTURAL STEEL............................................................................................22
7.1 CODES AND STANDARDS .............................................................................22
8 CONCRETE ............................................................................................................25
8.1 CODES AND STANDARDS .............................................................................25
KEPPEL Energy Pte Ltd is developing 600MW advanced cogeneration combined cycle
power plant, which is located at Sakra Avenue, Jurong Island, Singapore. The power plant
will be configured as a single shaft CCGT unit comprising of one (1) Advanced J class Gas
Turbine, one (1) condensing steam turbine connected with a common generator, one (1)
Heat Recovery Steam Generator (HRSG) and all required auxiliary systems. The gas
turbine will be designed with dual fuel firing options considering natural gas as a primary
fuel and distillate oil as a backup fuel.
This document outlines the criteria adopted for the design of all civil and structural works
such as buildings, reinforced concrete and steel structures, foundations for equipment’s,
roads, drainage, and landscaping works involved in developing the project.
All concrete structures shall be designed to have a minimum design life of 50 years and
steel structures are designed to have a minimum design life of 25 years before significant
repair or replacement of the main structural elements and secondary structural elements.
The design, supply, fabrication, erection, installation & materials for all civil and structural
and architectural works shall be in accordance with the applicable provisions from the
following internationally recognized codes, standards, recommended practices and
documents but not limed to the latest issue of the relevant Singapore/ British/ European
standards. Any other relevant codes of practice shall be referred to as and when necessary.
The design and specifications shall be in accordance with all the applicable laws and
regulations of the government of Singapore, the applicable local codes and ordinances and
the requirements of the equipment manufacturers. In case of conflict between the codes
and standards, Singapore standards and local regulations, then the more stringent
requirements shall be applied.
For analyzing and designing the structure, the following software’s are used.
STAAD PRO
PROKON
ETABS
The SI system of units shall be used for all structural design. However, where plant and
equipment design already exist in other units, the dimensions and tolerances shall be
presented in SI units to agreed degree of accuracy of conversion from the original units.
English language will be used in calculations.
To facilitate design and construction, a plant grid system has been established with the
plant north aligned with True North. The plant coordinate system is laid out based on this
grid system.
Finished Floor levels of all major buildings/facilities are kept above to allow for gravity
drainage of storm water.
Standard Plant
S. No Description Refer to
elevation
300 mm minimum above
1 All buildings Finished floor level
the finished grade level
Pumps and vertical 300 mm minimum above
2 Bottom of base plate
vessels finished grade level
200 mm minimum above
3 Steel structures Bottom of base plate
finished grade level.
200 mm minimum above
4 Pipe supports Bottom of base plate
finished grade level.
Ladders, staircase and
150 mm minimum above
5 minor pipe and cable tray Bottom of base plate
finished grade level.
supports
As per equipment
6 TG foundation
vendor requirement.
Level is fixed with
7 HRSG reference to the center
line of TG.
Sea water intake 200 mm minimum above
8 Top of Slab
structure the finished grade level
3.3 DRAINAGE
3.3.1 GENERAL
U shaped concrete drain system is provided to collect the storm water drain from the site
by gravity and discharged into the sea. The drain shall be covered either by grating or
concrete slabs.
At road crossing and maintenance area, the drains shall be covered with heavy duty hot
dipped galvanized cover.
The quantity run-off or the peak discharge is calculated using the following rational formula
from Code of Practice (COP) on Surface Water Drainage_7th Ed Add. 1: clause 7.1.
Where:
Qr = Peak runoff at the point of design (m3/sec)
C = Run-off Coefficient = 0.8 (Residential/Industrial
area densely built up)
Drains shall be designed to have discharge capacities (Qc) adequate to cope with the
estimated peak runoffs (Qr). The size, geometry and the bed gradient of a drain determine
its discharge capacity (Qc). With the required discharge capacity (Qc) determined [which
must be equal to or larger than the peak runoff (Qr)], the size of the drain is computed
from the Manning's Formula from COP on Surface Water Drainage_7th Ed Add. 1: clause
7.2.
The velocity of flow in a drain shall not be lower than 1.0 m/s for self-cleansing action to
take place.
The velocity of flow in a concrete-lined drain shall be limited to a maximum of 3.0 m/s or
below the critical velocity, whichever is lower. (COP 7th Ed clause 7.3.2)
Sufficient freeboard shall be provided to prevent waves or fluctuation of the water surface
from overflowing the cope/bank. Generally, a depth of freeboard equivalent to 15% of the
depth of the drain is considered.
The sanitary wastewater from various buildings inside the plant is collected and
discharged into the PUB sewer system available near the plant boundary. PVC pipe will
be used to collect the solid and wastewater from different buildings and discharged into
the Public Sewer system. The minimum pipe size of 150mm will be used and be verified
during detail engineering.
Oily water from various sources is collected in plant sump by gravity and it is pumped and
separated in the underground oil water separator. The clear water separated from this
shall be discharged to holding pond. The skimmed oily content shall be disposed by truck
by Owner. Detail process information will be available in the process description document.
All roads shall be rigid concrete pavement following the specification of LTA standard for
service roads. The roads are sloped 2% to one side towards the drain.
The main road for two-way traffic shall be 7.4m wide and one way traffic shall be 6m wide.
The bending radius for 7.4 m and 6.0m shall be 6.5m and 6.0m respectively.
The whole project site is covered with fence. Anti-climb fence will be provided as per the
recommendations from SBD report and remaining area will be provided with 2.5m height
chain link fence. A controlled access gate shall be located near the Guard entrance as per
SBD recommendation.
RCC paving
Paving area shall be minimum 150mm thick reinforced concrete construction with slope
towards the drain and thickness is verified during detail engineering stage. The concrete
pavement shall be placed on 200mm thick hard core / laterite over well compacted subgrade.
The exposed area which is not covered by foundation, concrete paving, grass area and
structures shall be covered with stone aggregate/ gravel paving. Gravel paving shall be
100mm thickness with 40mm maximum crushed rocks or gravels of approved grading and
quality.
Landscaping:
All green belt area will be followed as per Nparks requirements.
Dead Load (or Static Load) shall consist of the weight of structures and all equipment of a
permanent or semi-permanent nature including tanks, bins, wall panels, partitions, roofing,
piping, insulation, electrical cables, floor finishers, bus ducts & trays, refractory, soil weight
above foundation, earth pressure and other loads permanently supported by structures. The
dead loads shall be calculated based on unit weight stipulated in SS EN 1991-1 or actual
material weight in accordance with SS EN 1991.
The unit weight of the construction materials to be used for analysis and design are as
follows:
Steel 78.5
Water 10.0
Glass 26.0
Superimposed dead load shall be derived from the loading of finishes, services, ceiling,
partitions, water, soil, concrete toppings, etc. Typical superimposed loading shall be as
follows unless noted.
Live load shall be defined as the mass of all movable loads including personnel, tools,
miscellaneous equipment, cranes, hoists, parts of dismantled equipment and temporarily
stored materials. The minimum unfactored floor live loads on floor shall be in accordance
with SS EN 1991-1-1 except where otherwise specified below:
These loads shall be considered as live loads and in combination with permanent
loads and other live loads with appropriate load factors.
The total weight of equipment shall include accessories or supplementary component and
internals attached thereto or supported thereby. Either equipment loads for erection or
normal operation or for testing shall be considered together with other loads. For major
equipment, structural members and bases shall be specifically located and designed to
carry the equipment load into the structural system.
Estimated area loads for piping and cable tray provided by the Mechanical and Electrical
design will be used for structural design.
Piping load includes the weights of pipe, fittings, valves, insulation and the fluid contents of
the pipes. Piping loads for miscellaneous piping systems may initially be estimated as
uniform loads per unit floor area based on expected density and size of piping supported.
Piping load will be derived from preliminary piping arrangement provided by the piping
department. For the consideration of friction due to configuration, operating loads and
temperatures, the horizontal loads shall be considered 10 percent of the vertical load for
normal pipes and 30 percent of the vertical load for steam pipes. For steam pipes, actual
loads will be determined later from the pipe stress analysis. The cable tray load and cables
loads shall be calculated based on the actual cable routing drawing.
Wind load for all structures shall be determined based on SS EN 1991-1-4 and NA to SS
EN 1991-1-4.
The wind pressure acting on the external surfaces calculated as per the below formula.
We = qp(ze) x cpe
Where:
The building structure shall be checked and design for an enhanced robustness
consideration to cater for impact of seismic actions due to distant earthquakes. The
Structures shall be designed as per Singapore regulations BC3:2013. As per the regulations,
building structures with height more than 20m shall be considered for seismic design.
For seismic design, the ground type is defined as C as per soil investigation report.
If any blast loads are happening to structure, this shall be considered as per the equipment
vendor recommendation.
Lifting loads shall be considered as per the major components lifted by vendor
recommendation.
Vibration load means vibration force by heavy machinery, surge load of catalyst, etc. which
act on the structure. Rotating parts shall be considered as vibrating mass.
The foundation and structure of reciprocating machine and/or equipment having provable
vibration shall be designed to prevent vibration and resonance through dynamic analysis.
Soil pressure refers to the lateral soil pressure acting on the below grade structure or
foundation and potential surcharge loads from normal service or construction. All
underground earth and liquid retaining structures are designed for earth pressure at rest.
Backfill 0.5 19
All underground structures including drains, sumps, pipe and cable trenches shall be
designed for the surcharge load of 5 kN/m2 except for the structures nearer to the road shall
be 20 kN/m2
The 30t fire engine loading shall be considered for the loads exerted on bridges, roadway
pavements, parking and unloading areas, buried piping under road, box culverts, and
embankments within the plant.
Impact loads shall be added to other loads for components supporting reciprocation or
rotating machines, elevator, hoists, cranes, or other equipment creating dynamic forces.
The following impact load shall be used, unless higher or lower values are obtained from
analysis:
Other type of loadings may be taken into consideration in the design of plant structures as
per the requirements of the equipment manufacturer or the like.
5 LOAD COMBINATIONS
Load combinations and load factors shall be derived based on the NA to SS EN 1990
Table NA.A1.2(A), NA.A1.2(B) and NA.N1.2(C). Table NA.A1.2(B) shall be adopted with
load pattern as per NA to SS EN 1992-1-1 Table NA.1 Clause 5.1.3(1)P.
6.1 DEFLECTIONS
The permissible deflection for steel structures shall be followed based on National Annex
to SS EN 1993-1-1.
Vertical deflection
6.2 STABILITY
Structures subjected to overturning moments, shear and uplift shall be designed to satisfy
the following requirements for stability.
6.2.1 OVERTURNING
The ratio of the resisting moment due to dead load to overturning caused by wind pressure
or earthquake load shall not be less than 1.5 and 1.25 respectively.
6.2.2 SLIDING
The ratio of resisting force to the total shear shall not be less than 2.0 & 1.7 for operation
& Earthquake respectively.
6.2.3 FLOATING
The ratio of dead load of structure to the total uplift force shall not be less than 1.25.
7 STRUCTURAL STEEL
All steel plates, columns, beams, channels, angles, and other steel sections shall conform
to BS EN 10025 and BS EN10210. The minimum yield stress to be used for design shall
be 235 N/mm2.
Material Criteria
Building frame design shall be a combination of rigid frame in transverse direction and
braced frame in longitudinal direction. Alternatively, it will be braced frames in both
directions. The minimum depth of steel members shall be 1/24 by span unless clearance
requirements dictate the shallower members in certain areas, exclude roof, truss, and minor
members. Members shall be framed into members of equal or greater depth.
Fire protection shall be provided in accordance with the most onerous of the design
conditions of NFPA 850 and FM requirements. Fire resistance coating shall be applied to
all structures as per SCDF requirements.
The design of buildings, civil constructions, and all fire protection installation shall also
confirm to local regulations, latest edition and amendments and are subject to acceptance
by the local authority having jurisdiction.
Bolts:
Connections shall be in accordance with standard connection design for shop welded and
field bolted connections. All the bolt connections are slip critical connections. All bolted
connections shall be designed for minimum 2 nos of M16 bolts.
Weld:
All welding rods and electrodes shall be of low hydrogen type. For welding E70xx electrodes
will be used and the nominal tensile strength of E70xx weld metal shall be 482 N/mm2.
Welding shall be minimum 6mm continuous fillet weld UNO.
7.6 FINISHING
All steel structures shall be shop coated with inorganic zinc primer after fabrication in
accordance with SSPC No. 10 or equivalent.
7.7 GRATING
Grating will be of mild steel welded type. Minimum grating size shall be 25x 5 mm to be
used for walkway and staircase. Grating which are likely to be subjected to equipment
laydown loads will be designed to carry the intended loading. All grating shall be hot dipped
galvanized.
7.8 HANDRAILS
All handrails will be of welded construction using HDG steel with 32.0 to 50.0 mm outside
diameters. Handrail will be two rail system and the members and spacing shall be as per
detailed design. The height of handrail shall not be less than 1.0m. All the HDG handrails
will be painted as per the colour code of company.
All steel staircase and walkways shall be provided with minimum width of 900mm. All stairs
shall have maximum 175 mm risers and minimum tread width of 250 mm.
Platforms and walkways shall be minimum 800mm wide. All platforms shall have kick plate
of 100mm high x 6mm thick around periphery. It will be designed as per BCA requirement.
8 CONCRETE
Strength
Concrete
fck Elements
Grade
(N/mm2)
C12/15 12 Lean / Mass Concrete
Substructure (Raft Foundation, Pile caps,
C28/35 28 Basement Walls, Basement
Slabs, Basement Beams)
C35/45 40 Driven pile, water retaining structure
All steel fabric shall conform to BS 4483 with a minimum yield stress of 485 N/mm2.
Followings are pile type and capacity considered for foundation design.
Bore pile
Diameter of pile = 800mm
Vertical capacity = 2300 kN
Lateral capacity = 230 kN
Pile length = Estimated based on borehole information
Permissible pile vertical settlement for TG and HRSG foundation shall be of 8mm. All other
buildings and plant foundations, the permissible pile vertical settlement shall be of 15mm.
For raft foundation and spread footing, the permissible settlement shall not exceed 25mm.
All storage tank foundations are supported on mat foundation on the soil improved ground
and the foundations shall be designed based on the recommendations of API 650.
The dynamic design of foundation shall comply with the German Standard DIN 4024 or an
equivalent international standard or in accordance with manufacturer’s recommendations.
The design of the turbine foundation shall include for the thermal effects on the foundation
and its ability to withstand the extreme differential temperatures likely to be experienced by
the foundation, during the construction as well as throughout its design life.
The design of the foundation should incorporate an internal reinforcement cage system
which is essential for the foundation to act as a homogenous mass and provide additional
a second line of defence to the machine anchoring system with the holding down bolts.
All transformers shall be provided with fire wall as per NFPA requirements. The containment
for the transformer shall be provided for any accidental leakage of transformer oil and this
containment is designed as NFPA requirements.
Based on the soil investigation report, the highest ground water table is available at
+0.520m SHD. For designing the underground structure, the ground water table shall be
considered 1.5m above the HGWL (0.52+1.5 =2.02 SHD) +2.00m SHD.
All water retaining structures shall be designed and detailed in accordance with SS EN
1992-3 along with Singapore National Annex.
8.8 CEMENT
Cement shall be Ordinary Portland cement Type I conforms to ASTM C150. Type II cement
may be used for large concrete pours where a moderate low heat generation is desirable.
Type III Rapid hardening Portland cement may be used for areas where high early strength
gain is required such as for precast elements.
All trenches, tunnels, liquid retaining structure and pits shall be provided with 150mm wide
PVC water stops at all construction joints.
8.10 GROUTING
Grout shall be non-shrink, non-ferrous, high strength, dense, durable, pre-mixed, ready to
use and proprietary type from an approved manufacturer to set equipment’s and structural
steel members on foundation and to fill voids in concrete where shrinkage inherent in normal
cementitious grout cannot be tolerated or as specified by design. The minimum thickness
of grout shall be 25mm. Non shrink grouts shall conform to ASTM C1107, Grade C.
Minimum compressive strength will be 24 N/mm2 after 1 day and 50 N/mm2 after 28 days.
While grouts for major equipment’s will be provided as per vendor requirements.