Duct support load calculation not The responsible Supervisor was not available
available during this activity but his instruction to use
wood lumber was neglected by his team
Duct insulation started depending resulting in accident
on load calculations by Technical
Department considering a higher Lack of command on team and failure to
value than expected design provide resources to execute the work i.e.
calculation sufficient wood lumber was not made available
for the task resulting in worker using pipe piece.
ACCIDENT
Approved Load Calculation Is Gap between the two ducts was created by
Available inserting a wood lumber to prevent crush hazard.
Estimated load calculation of duct But the worker used 8cm long and 3mm thick
support is lower than the approved hollow pipe section instead of wood lumber
calculation
During support installation this piece of pipe
Additional support is to be installed misbalanced and the duct fell on workers hand