Agenda #14
Agenda #14
Information, Outstanding
D issue, and Problem
E Site activity
1. Project Calendar
2. Resume of progress report week-12 (December 30, 2019 – January 5, 2020)
Attachment-2
3. Photo documentation week-12 (December 30, 2019 – January 5, 2020)
4. Quality Assurance
1. Information
1.1. Permit for operational of TC in ASLC
1.4. IFFLC user request for addition of fume hood and corrosive chemical storage -
2. Outstanding issue
2.1. Show cause meeting (SCM)
3. Problem
3.1. Section TC of IFFLC delayed
3.2. Consideration to the position of beam regarding changes plate type from
conventional to half slab (composit drawing of architecture and mechanical
electrical)
CS
CS
CS
WIKA
All
Category Content
SHE Report per January 12, 1. SHE report by CS
A 2020 2. SHE report by Contractor
Presentation of half slab Contractor to presentation the completed of installation half slab
B installation method method
1. Project Calendar
Work Progress Status per 2. Resume of progress report week-13 (January 6 - 12 , 2020)
B January 12, 2020 3. Photo documentation week-13 (January 6 - 12 , 2020)
4. Quality Assurance
1. Information
3. Problem
3.1. There are different between proposed AC by contractor
(Toshiba) with tech. spec.
3.2. No access for worker from 1st floor to 2nd floor at IFFLC
Information,
D Outstanding issue,
and Problem
E Site activity
Other (discussion,
F etc.)
Content Notes
1. SHE report by CS
Attachment-1
2. SHE report by Contractor
1. Project Calendar
2. Resume of progress report week-14 (January 13 - 19 , 2020)
Attachment-2
3. Photo documentation week-14 (January 13 - 19 , 2020)
4. Quality Assurance
1. Information
2. Outstanding issue
-
3. Problem
CS
CS
CS
WIKA
All
Category
A SHE Report per January 19, 2020
E Site activity
E Site activity
1. Project Calendar
2. Resume of progress report week-14 (January 6 - 12 , 2020)
3. Photo documentation week-13 (January 6 - 12 , 2020)
4. Quality Assurance
1. Information
1.1. Deletion of 28 unit AW4 types of inspection door in 1st floor and
replace with 2 unit AW4’ in basement floor ASLC
1.2. Shifting beam as Y2 in the IFFLC building
1.3. Additional waterproofing in pit lift area
1.4 Pressure rise fan wall changes from concrete to AAC fire rated 2
hours in ASLC
1.5. Relay out gutter area in mechanical balcony ASLC due to crash
structure beam
1.6. Enlarge panel room in each floor ASLC
1.7. Material approval as follows: a) Red brick; b) Rubber sealant; c)
Movable wall; d) Frame partition; e) Cubicle toilet; f) Rock wool; g)
Calcium silicate; h) Hollow steel; i) Lipped channel; j) ceramic tile; k)
GRC; l) Door/window hardware
2. Outstanding issue
2.1. Material approval as follows: a) Sanitary; b) Grill work; c)
Engineering door; d) Accoustic ceiling
2.2. The contractor is requested to immediately submit sub-
contractor approval for: a) ACP work; b) GRC work.
2.3. The contractor is requested to proposed the ceiling acoustic and
vinyl base
3. Problem
3.1. Tower crane is trouble (January 19-20, 2020) in ASLC
3.2. The size of split for concrete beam and slab should be use less
than 1 cm
3.3. Reinforcement horizontal shear wall must be inside column cross
bar
3.4. Evaluation half slab works (made up of quality, mobilization and
workers)
3.5. The contractor to submit concrete repair method
All