You are on page 1of 14

Category

SHE Report per January 5,


A 2020

Work Progress Status per


B January 5, 2020

C Review last week meeting

Information, Outstanding
D issue, and Problem

E Site activity

F Other (discussion, etc.)


Content Notes
1. SHE report by CS
Attachment-1
2. SHE report by Contractor

1. Project Calendar
2. Resume of progress report week-12 (December 30, 2019 – January 5, 2020)
Attachment-2
3. Photo documentation week-12 (December 30, 2019 – January 5, 2020)
4. Quality Assurance

Minutes of meeting #12 (January, 2 2020) Attachment-3

1. Information
1.1. Permit for operational of TC in ASLC

1.2. Contractor to submit approval material according schedule material :


a)Carpet ; b) Sanitair ; c) Grill work ; d) Stainless for railing ; e) Engineering door

1.3. Contractor to proposed approval sub-contractor for : a) ACP work ; b) GRC


work

1.4. IFFLC user request for addition of fume hood and corrosive chemical storage -

2. Outstanding issue
2.1. Show cause meeting (SCM)
3. Problem
3.1. Section TC of IFFLC delayed
3.2. Consideration to the position of beam regarding changes plate type from
conventional to half slab (composit drawing of architecture and mechanical
electrical)

1. Site activity per January 5, 2020


2. Next week activity plan
Reporter
CS
WIKA

CS

CS

CS

WIKA

All
Category Content
SHE Report per January 12, 1. SHE report by CS
A 2020 2. SHE report by Contractor

Presentation of half slab Contractor to presentation the completed of installation half slab
B installation method method

1. Project Calendar
Work Progress Status per 2. Resume of progress report week-13 (January 6 - 12 , 2020)
B January 12, 2020 3. Photo documentation week-13 (January 6 - 12 , 2020)
4. Quality Assurance

C Review last week meeting Minutes of meeting #13 (January 8, 2020)

1. Information

1.1. Contractor to proposed sub-contractor of MEP works

1.2. Schedule proposed material for approval as follows: a)


Soundproof insulation; b) Ceiling; c) Floor and wall finishing
2. Outstanding issue
2.1. Material approval as follows: a) Carpet; b) Sanitary fixture; c)
Grill work; d) Stainless for railings; e) Flush Door;
2.2. The contractor is requested to immediately submit sub-
contractor approval for: a) ACP work; b) GRC work.
Information, Outstanding
D issue, and Problem 2.3. Contractor to submit composite drawing

3. Problem
3.1. There are different between proposed AC by contractor
(Toshiba) with tech. spec.

3.2. No access for worker from 1st floor to 2nd floor at IFFLC

3.3. Concrete block ex loading test AGLC disturbance work


activities

3.4. Composite shop drawing of stair


Notes

Akan ada SHE dari RSA UGM

Produksi half slab per 15 Januari 2020 274 dari 945


Untuk half slab yang reject sebaiknya ditandai
Penumpukan half slab untuk baru yang di cor 8 tumpuk, untuk yang umur 7 hari
bisa sampai dengan 15 tumpuk.
Penandaan reject di half slab yang reject
Check lokasi penyimpanan half slab,s ebaiknya di loaksi yang datar
Check jarak balok sebelum pemasangan tulangan di ujung-ujung half slab agar
tulangan balok tidak tepasang miring
Metode pengecoran half slab dan balok menggunakan tower crane
Category
SHE Report per
A January 19, 2020

Work Progress Status


B per January 19, 2020

Review last week


C meeting

Information,
D Outstanding issue,
and Problem

E Site activity

Other (discussion,
F etc.)
Content Notes
1. SHE report by CS
Attachment-1
2. SHE report by Contractor

1. Project Calendar
2. Resume of progress report week-14 (January 13 - 19 , 2020)
Attachment-2
3. Photo documentation week-14 (January 13 - 19 , 2020)
4. Quality Assurance

Minutes of meeting #14 (January 15, 2020) Attachment-3

1. Information

2. Outstanding issue

-
3. Problem

1. Site activity per January 19, 2020


2. Next week activity plan
Reporter
CS
WIKA

CS

CS

CS

WIKA

All
Category
A SHE Report per January 19, 2020

Work Progress Status per January 19,


B 2020

C Review last week meeting

Information, Outstanding issue, and


D Problem

E Site activity
E Site activity

F Other (discussion, etc.)


Content Notes Reporter
1. SHE report by CS
2. SHE report by Contractor

1. Project Calendar
2. Resume of progress report week-14 (January 6 - 12 , 2020)
3. Photo documentation week-13 (January 6 - 12 , 2020)
4. Quality Assurance

Minutes of meeting #13 (January 8, 2020)

1. Information
1.1. Deletion of 28 unit AW4 types of inspection door in 1st floor and
replace with 2 unit AW4’ in basement floor ASLC
1.2. Shifting beam as Y2 in the IFFLC building
1.3. Additional waterproofing in pit lift area
1.4 Pressure rise fan wall changes from concrete to AAC fire rated 2
hours in ASLC
1.5. Relay out gutter area in mechanical balcony ASLC due to crash
structure beam
1.6. Enlarge panel room in each floor ASLC
1.7. Material approval as follows: a) Red brick; b) Rubber sealant; c)
Movable wall; d) Frame partition; e) Cubicle toilet; f) Rock wool; g)
Calcium silicate; h) Hollow steel; i) Lipped channel; j) ceramic tile; k)
GRC; l) Door/window hardware
2. Outstanding issue
2.1. Material approval as follows: a) Sanitary; b) Grill work; c)
Engineering door; d) Accoustic ceiling
2.2. The contractor is requested to immediately submit sub-
contractor approval for: a) ACP work; b) GRC work.
2.3. The contractor is requested to proposed the ceiling acoustic and
vinyl base
3. Problem
3.1. Tower crane is trouble (January 19-20, 2020) in ASLC
3.2. The size of split for concrete beam and slab should be use less
than 1 cm
3.3. Reinforcement horizontal shear wall must be inside column cross
bar
3.4. Evaluation half slab works (made up of quality, mobilization and
workers)
3.5. The contractor to submit concrete repair method

1. Site activity per January 19, 2020


WIKA
WIKA
2. Next week activity plan

All

You might also like