Observe & Killing well terlebih dahulu jika diperlukan. Menghindari steam kick
Workover Procedure for HCE-30A (if fishing success by CTU) rev.2ver.0 Page 2 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
- Install 13-5/8” Exp. Spool dan 12” Master Valve. annulus tsb sdh mengeras)
Workover Procedure for HCE-30A (if fishing success by CTU) rev.2ver.0 Page 3 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
Rig up Drillable Packer and set in ~1400 mRKB - Run 9-5/8” Bridge Plug & set di 1415 m (di dalam 9-
Berdasarkan well history, terdapat 13-3/8”
5/8” Casing).
Fill up water up to surface casing leaking (9-5/8” TOL) antara 1000-1400 m,
- Squeeze 13-3/8” casing leaking (1000 -1400 m)
sehingga harus dilakukan squeeze casing leaking
(depend on logging result)
tersebut terlebih dahulu.
Prepare for Run Casing and Cementing Job based Note: Squeeze 13-3/8” berdasarkan injectivity
on PT survey and caliper Detail lengkap terdapat di Workover Procedure point
test terlebih dahulu
no.6A.
Workover Procedure for HCE-30A (if fishing success by CTU) rev.2ver.0 Page 4 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
Make up stab in stinger on 1 stand 5” DP. Stand Turunkan BOP dan lepas 12" MV terlebih dahulu Untuk mengakomodasi pemasangan 10" X 13-
back in the derrick. sebelum run 9-5/8” Casing 5/8" Exp Spool
Workover Procedure for HCE-30A (if fishing success by CTU) rev.2ver.0 Page 5 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
Workover Procedure for HCE-30A (if fishing success by CTU) rev.2ver.0 Page 6 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
7 Completion Test
Workover Procedure for HCE-30A (if fishing success by CTU) rev.2ver.0 Page 7 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
Kesimpulan :
1. Sebelum tajak, harus dipastikan sumur di killing terlebih dahulu untuk menghindari resiko steam kick.
2. Karena kondisi Wellhead & Master Valve yang sudah tidak layak, maka perlu penggantian Wellhead dan Master Valve baru. Penggantian Wellhead
dan Master Valve baru dengan asumsi dapat running Hot Packer di 13-3/8” Casing.
3. Running Impression Block akan dapat menyebabkan multi interpretasi hasil. Jika ingin mengetahui lebih detail mengenai obstruction di 13-3/8”
Casing disarankan untuk melakukan Well Investigasi terlebih dahulu dengan menggunakan Down Hole Video (DHV) untuk mendapat keakuratan
data.
4. Menggunakan casing swage untuk mengembalikan casing collapse ke bentuk casing semula pada sumur geothermal berpotensi besar dapat
menyebabkan casing collapse kembali dikemudian hari.
5. Apabila ada indikasi casing collapse maka perlu dilakukan milling. Akan tetap konsep dasar pekerjaan milling yaitu “merusak casing sedemikian
rupa” agar dapat dilalui oleh peralatan sampai TD. Remedial casing (squeeze/tie back) pada casing yang terbuka/bocor diperlukan untuk
menghindari masalah yang akan timbul dikemudian hari.
6. Kebocoran 13-3/8” casing di kedalaman 1000-1400 m harus diatasi terlebih dahulu sebelum running 9-5/8” Tie Back Casing.
7. Jika masih ada indikasi fill/rontokan dari bocoran diatas tidak direkomendasikan logging job sebelum bagian casing yg rusak/bocor tersebut
dilakukan remedial terlebih dahulu.
8. Penyemenan 9-5/8” Tie Back Casing lebih baik menggunakan single slurry (15.8 ppg), untuk mendapatkan compressive strength yang tinggi dengan
property yang lebih baik.
9. Terdapat 2 (dua) opsi Wellhead Configuration untuk sumur HCE-30A:
a. Jika menggunakan existing 20” WH, 13-5/8” Exp.Spool dan 12” Master Valve maka membutuhkan tambahan material baru untuk 10” Exp.
Spool & 10" X 13-5/8” DSA.
b. Jika tidak menggunakan existing 20” WH, 13-5/8” Exp.Spool dan 12” Master Valve maka membutuhkan tambahan material baru 11”
Wellhead & 10” Master Valve baru.
10. Workover sumur HCE-30A ini dapat dilakukan, akan tetapi dengan catatan bahwa sudah tidak ada fish 11” Nozzle.
Workover Procedure for HCE-30A (if fishing success by CTU) rev.2ver.0 Page 8 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
Spud In
Reaming Obstruction NO
400-468 mtr
Observe Well & Killing Well (13-3/8” Casing)
(from 3-1/8" Side Valve Milling Obstruction 400-468 m
Exp.Spool) YES (13-3/8” Casing) until of depth
requirement
Install
20" WH or 13-5/8" WH
Preparation
Water Supply Equipment GDE 1 set
H2S Equipment H2S Serv. 1 set
13-5/8” BOP Equipment Rig Serv. 1 set
13-5/8” Rotating Head (optional) Aerated Serv. 1 set
C. Operation Procedure
4. CASING CLEARANCE
A. Reaming Casing Collapse
4.1. Make up Reaming BHA as listed below:
10” Taper Mill dressed with tungsten carbide & nozzle
9-5/8” Water Melon Mill
Float Sub
Workover Procedure for HCE-30A (if fishing success by
CTU) rev.2ver.0
Page 13 of 27 HCE-30A WORKOVER PROGRAM
Tetra Pak Building Ground Floor Kav. 99
Jl. Buncit Raya, Jakarta Selatan - 12510
Telp. (021) 798 6660/ (021) 791 60087 Fax. (021) 791 97882
Website: www.ametis-institute.com
Email: info@ametis-institute.com
8” DC
5” HWDP
4.2. RIH and tag obstruction (est.400-468 m) with 3 klbs and determine
this as top collapsed casing, pick up approximately 0.5 meter,
circulated bottoms up with maximum flow rate, take and record
parameters PUW and SOW.
4.3. Start reaming down the obstruction with parameter 20-30 RPM, max
flow rate, 2 -5 klbs WOB to 9-5/8” Top Casing Liner (+ 1409 m).
Noted: If can’t pass thru obstruction, POOH and go to step B.
Milling Casing Collapse.(Optional Running Impression Block)
4.4. Once the clear of obstruction (indicated by torque), work the pipe
between casing collapse interval. Check if there is any indication of
noticeable obstruction.
4.4.1. Observe the parameter based on reaming progress.
4.4.2. During ream obstruction keep hole full and monitoring
pressure.
4.4.3. Circulate with max flow rate for 10 minutes on every 1 hour
milling.
4.4.4. If any increase of torque during running to bottom, find out
this condition by observe the combination of torque and also
the drag of the drill sting and report to COMPANY MAN.
Attempt to ream the tight spot and circulate with
maximum GPM.
4.5. Pull out of hole the string. Try normal pull, if tight hole indicated,
POOH with back ream to surface and continue lay down the 12” Taper
Mill.
Noted: Proceed to step C. Reaming & Casing Clearance up to
TD (+ 2566 m)
4.9. Once the clear of obstruction (indicated by torque), work the pipe
between the milled casing interval. Check if there is any indication of
noticeable obstruction.
4.9.1. Observe the parameter based on milling progress.
4.9.2. Circulate with max flow rate for 10 minutes on every 1 hour
milling.
4.9.3. If any increase of torque, find out this condition by observe
the combination of torque and also the drag of the drill sting
and report to COMPANY MAN.
Attempt to ream the tight spot and circulate with
maximum GPM.
4.9.4. Pull out of hole the string. Try normal pull, if tight hole
indicated, POOH with back ream to surface and continue lay
down the 12” Flat Bottom Mill.
5. LOGGING JOB #1
5.1. M/U Dummy tools for logging job.
5.2. RIH Dummy tools for logging job until reach TD (+ 2566 m).
5.3. POOH Dummy tools to surface.
5.4. M/U dan RIH Wireline Logging Tools (PT Survey, MFC and CBL) until
reach TD (+ 2566 m).
5.5. Evaluation Logging Job.
Noted: The detailed program can follow and refer to Appendix
of this program. Confirm the program with Geologist &
Production Engineer and discuss with Drilling Superintendent.
6.11. RIH with BHA 12-1/4” bit assembly, tag the TOC and record TOC.
6.12. Redress the cement to 9-5/8” TOL, closed rams and conduct pressure
test with various 100 psi for 5 minutes then 200 psi for 5 minutes.
6.13. POOH string to surface.
7. LOGGING JOB #2
7.1. M/U Dummy tools for logging job.
7.2. RIH Dummy tools for logging job until reach 9-5/8” Tieback Casing
Shoe (+ 1400 m).
7.3. POOH Dummy tools to surface.
7.4. M/U dan RIH Wireline Logging Tools (CBL) until reach 9-5/8” Tieback
Casing Shoe (+ 1400 m).
7.5. Evaluation Logging Job.
Note: The detailed program can follow and refer to Appendix of
this program. Confirm the program with Geologist &
Production Engineer and discuss with Drilling Superintendent.
8. COMPLETION
8.1. Close master valve and secure the well. Always keep pumping from
backside (wing valve) during closed master valve.
8.2. Nipple down the BOP equipment.
8.2.1. Keep pumping the hole from annulus with pumping rate at
least 60 ltr/sec during nipple down BOP.
8.2.2. Stop quenching and remove all water line to the well.
8.2.3. Reinstall wellhead tee.
8.2.4. Recheck and tighten all wellhead flanges.
8.3. Shut in and flowing the well.
8.4. Rig down and Move to HCE-28 Well.
8.5. Material Usage Report of the Well.
END
APPENDIX
WELLHEAD CONFIGURATION
HCE-30A
0.97 mtr
12" MV, ANSI 900
10" X 13-5/8"
+0.3 mtr DSA Additional Material Required
+ 3.13 mtr
0.34 mtr
0.51 mtr
20" WH, 3M
Additional Material Required
CASING
20"
HCE-30A
Depth RKB
30" Conductor
14 mMD
26" HOLE SECTION 20" CASING K-55, 133 PPF, BTC (ID = 18.73")
552 mMD 551 mMD
17-1/2" HOLE SECTION 13-3/8" CASING SM-80S, 72 PPF, DINO VAM (ID = 12.374")
1515 mMD 1514 mMD
12-1/4" HOLE SECTION 9-5/8" PERFORATED CASING SM-80S, 47 PPF, DINO VAM (ID = 8.681")
2588 mMD 2566 mMD
Depth RKB
30" Conductor
14 mMD
12-1/4" HOLE SECTION 9-5/8" PERFORATED CASING SM-80S, 47 PPF, DINO VAM
2588 mMD 2566 mMD
BOP DRAWING
CLASS III 13 5/8" 3K BOP DIAGRAM (w/ Rotating Head)
SUMMARY:
1. Class III BOP, 13-5/8" 5K BOP (Annular, Blind Ram and Pipe Ram)
2. Minimal requirement of Sub Structure if using this stack: XX ft on lower beam of Sub Structure
3. Drill String: 5" DP
5000
13 5/8" 5K ROTATING HEAD XX m
5000
5000
13 5/8" 5K ANNULAR XX m
5000
5000
GATE RAMS
XXX m
5000
GROUND LEVEL
CASING
20"