1 PRELIMINARIES
a) Insurance and levy 7 days 1/7/2019 7/7/2019
b) Stamping Contract Document 60 days 7/7/2019 6/9/2019
c) Site office 14 days 11/7/2019 24/7/2019
d) Project Signboard 14 days 11/7/2019 25/7/2019
e) Setting Out
- OGL and Boundary 21 days 8/7/2019 29/7/2019
2 REINSTATEMENT WORKS
TRAFFIC MANAGEMENT AND CONTROL
a) Traffic Management Team 14 days 12/7/2019 26/7/2019
b) Temporary Road Furniture and Sign 14 days 12/7/2019 26/7/2019
SITE PREPARATION
a) Clearing Works 21 days 27/7/2019 17/8/2019
b) Raised up existing utility manhole 30 days 18/8/2019 17/9/2019
c) Walkway
- Trim and milling works 7 days 18/8/2019 25/8/219
- 100mm thick base 60 days 25/8/2019 24/10/2019
- 100mm thick brush finish 60 days 8/9/2019 7/11/2019
LANDSCAPE REINSTATEMENT
a) Clear dead and unhealthy trees 21 days 16/10/2019 6/11/2019
b) Root protection 30 days 7/11/2019 6/12/2019
HANDING OVER
a) Final Cleaning Works 4 days 27/12/2019 31/12/2019
b) Hand over 0 days 31/12/2019 31/12/2019
SETIA SKY VILLE - UPGRADING OF ROADWORKS TO JALAN VAN PRAAGH AND LORONG SLIM
1 PRELIMINARIES
a) Insurance and levy 7 days
b) Setting Out 14 days
2 REINSTATEMENT WORKS
ROAD AND PAVEMENT
a) Road works
- Trim works 20 days
- Lay 300mm thick crusher run 30 days
- CBR test 7 days
- Laying binder course 14 days
- Laying wearing course 14 days
- Coring test 7 days
- Road marking 8 days
- Road signage 8 days
3 RELOCATED
a) Signage 7 days
c) Traffic Light 30 days
HANDING OVER
a) Final Cleaning Works 3 days
b) Hand over 0 days