Professional Documents
Culture Documents
Factory Name & Address 5F Apparels Limited, Zirabo, Ashulia Road, Savar, Dhaka
Date of Inspection by Accord 27-Jan-2015
Accord Rating
Finance Plan Agreed Yes
Factory Name & Address 5F Apparels Limited, Zirabo, Ashulia Road, Savar, Dhaka
Date of Inspection by Accord 6-Feb-2015
Accord Rating
Finance Plan Agreed Yes
Visit Type Sub Visit Type Item No Accord Inspection Observation Accord Action Final Action Plan Final Timeline Comments from Accord Timeline Progress Status
Plan Accord
Separate the Corrected May 18 2016
boiler room by On 22-08-2016: In progress. The boiler room has not been separ
aminimum 1-hr On 31/10/2016: Fire door installation is not done yet.
fire- On 02-01-17: Fire door installation work is not done yet. Note th
ratedconstruction On 06-04-17: Installation of boiler in new location has been start
for non-high On 25/July/2017: Corrected.
rise,and 2-hr fire On 25/03/2018: Corrected
ratedconstruction On 29/01/2019: Corrected.
Initial Inspection 1 The boiler room on the ground floor is for high rise.Seal On 21/11/2019: Corrected.
Within 3 months Corrected
Provide
and/or protect defined Done Jun 1 2016
storageareas
allopenings toand On 22-08-2016: In progress. Heavily stacked combustible storage
limit
maintain the On 31/10/2016: It has been found same as before.
storagearrangeme
therequired fire On 02-01-17: It is found same as it was before.
nt as follows:-
separations.When On 06-04-17: No action has been taken yet.
Maximum
located to the height On 25/July/2017: Not corrected yet.
of 2.45m(8ft.)
exteriorof a and On 25/03/2018: Corrected
maximum
building, 3m area
(10 On 29/01/2019: Corrected.
Initial Inspection 2 Areas used for combustible storage on of23m2
t
ft.)separation (250 ft2)-
is On 21/11/2019: Corrected.
Within 3 months Corrected
Provide
If sprinkler dedicated We will provied Jun 1 2016
required.Provide
storagerooms
protected:maximu
proper the fire door On 22-08-2016: In progress. Civil related work has not been start
separated
m height ofby
ventilationand within three On 31/10/2016: Fire door installation is ongoing.
minimum1-hr
3.66m(12ft.)
consult a andfire- months. On 02-01-17: It is found same as it was before.
rated
maximum
qualifiedengineer area On 06-04-17: Action has been taken but not enough yet.
construction.Wher
of93m2 On 25/July/2017: Fire doors are inhouse but not installed yet.
e(305ft2)Separate
separate On 25/03/2018: Same as before.
storagerooms
areas are On 29/01/2019: No remarkable progress after last follow up note
Initial Inspection 3 Rooms used for combustible storage ont not
ofunenclosed On 21/11/2019: NoWithin 3 months
remarkable progressIn Progress
has been observed sinc
Provide minimum We will provied Jun 1 2016
feasible,provide
combustiblestorag
1-hr
e by rateddoors
defined a minimum the fire door On 22-08-2016: In progress. It was found same as previous follow
for buildings with
storageareas
cleardistance of within three
and On 31/10/2016: Still office area and northeast exit stair are not s
3 orfewer
limit
3m the stories months.
(10ft.). On 02-01-17: Fire door installation work is in progress. Note that
and 1.5-hr
storagearrangeme On 06-04-17: No action has been taken yet.
firerated
nt as follows:- doors for On 25/July/2017: In progress. Fire door installation is pending on
buildings
Maximumthatare height 4 On 25/03/2018: Same as before.
or more stories.
of 2.45m(8ft.) and On 29/01/2019: No remarkable progress after last follow up note
Initial Inspection 4 The exit stairs are not separated from Seal
maximum area On 21/11/2019: NoWithin
remarkable
3 months
progress
In Progress
has been observed sinc
Openings
allunprotected
of23m2 (250 from ft2)- Fire door Apr 19 2016
exit
openingsenclosureto installation work is
If sprinkler On 22-08-2016: Corrected in last follow-up; found same in curre
utility
toseparate spaces
protected:maximu theshall ongoing. Note On 31/10/2016: Corrected.
beprovided
exit
m heightstairsof with a that, We allready On 02-01-17: Corrected as per last follow-up inspection.
vestibule
fromwork
3.66m(12ft.) withfire
and seal all the
areas On 06-04-17: Corrected.
rated
and
maximum construction
other area penetrations. On 25/July/2017: Corrected.
andopenings.Provi
buildingspaces
of93m2 on On 25/03/2018: Corrected
de
all a 1 hr. fire
floor
(305ft2)Separate On 29/01/2019: Corrected.
Initial Inspection 5 Boiler room dischargesdirectly into exitrated
areas dooron that
levels.Ensure the On 21/11/2019: Corrected
Within 3asmonths
per previous
Corrected
follow up.
exit
the stairdoors
fire
ofunenclosed side and
aareself-closing
1-hr. fire
combustiblestoragrated and
door
e by aon thesouth
positivelatching
minimum
room
and side.
that Ensure
they
cleardistance of
thatthe
areprovided
3m (10ft.). fire rating
with
of
firethe
exit
vestibuleconstruc
(panic)hardware
The exit stair We will provied Jun 1 2016
enclosure shallbe the fire door On 22-08-2016: In progress. It was found same as previous follow
provided with a within three On 31/10/2016: Fire door installation is ongoing.
minimum1-hr fire months. On 02-01-17: Fire door installation work is in progress. Note that
resistance rating On 06-04-17: Installation of fire rated door has not been comple
forbuildings with 3 On 25/July/2017: Work hasn't been completed yet.
or fewerstories On 25/03/2018: Same as before.
and a minimum of On 29/01/2019: No remarkable progress after last follow up note
Initial Inspection 6 The exit stair enclosures are not separ 2-hr fire resistance On 21/11/2019: NoWithin
remarkable
3 months
progress
In Progress
has been observed sinc
Provide stair
rating forbuildings Fire detection Feb 18 2016
designationsigns
4 or more stories. equipments & fire On 18-02-2016: Corrected.
and occupant protaction On 19-04-2016: Corrected.
loadsigns at equipments are in On 02-01-17: Corrected as per last follow-up inspection.
required locations house On 06-04-17: Corrected.
,we will stard On 25/July/2017: Corrected. Occupant load sign shall be posted
work from On 25/03/2018: Corrected
october 2018 On 29/01/2019: Corrected.
Initial Inspection 7 Building did not havestair designation On 21/11/2019: Corrected.
Immediately Corrected
Remove locking Fire detection Feb 18 2016
featuresfrom all equipments & fire On 18-02-2016: Corrected. During inspection, locking feature wa
egress doors / protaction On 19-04-2016: Corrected. Non-compliant locking feature was n
gates.If locks are equipments are in On 02-01-17: Corrected.
required house On 06-04-17: Corrected.
forsecurity ,we will stard On 25/July/2017: Corrected.
reasons, work from On 25/03/2018: Corrected
utilizespecial door october 2018 On 29/01/2019: Corrected.
Initial Inspection 8 Egress doors / gateswith locking feature locking On 21/11/2019: Corrected.
Immediately Corrected
Remove all
featurescomplying Fire detection Feb 18 2016
storage
with NFPAfrom 101and equipments & fire On 22-08-2016: Corrected. Storage has not been observed in exi
exitstairs
ACCORD and protaction On 31/10/2016: Corrected.
egress paths.
standard6.8.2. equipments are in On 02-01-17: Corrected.
house On 06-04-17: Corrected.
,we will stard On 25/July/2017: Corrected.
work from On 25/03/2018: Corrected
october 2018 On 29/01/2019: Corrected.
Initial Inspection 9 Storage was located in the exit stair pr Immediately
On 21/11/2019: Corrected. Corrected
Replace all gates / Fire detection Feb 18 2016
slidingdoors along equipments & fire On 18-02-2016: Corrected.
the means of protaction On 19-04-2016: Corrected. No non-compliant gate was found du
egress with side- equipments are in On 02-01-17: Corrected.
hinged,swinging house On 06-04-17: Corrected.
egress doors ,we will stard On 25/July/2017: Corrected.
inaccordance with work from On 25/03/2018: Corrected
ACCORDstandard october 2018 On 29/01/2019: Corrected.
Initial Inspection 10 Collapsible gates /sliding doors through6.8.1 On 21/11/2019: Corrected.
Within 1 month Corrected
Modify the egress Fire detection Feb 18 2016
door toswing in equipments & fire On 22-08-2016: Corrected as per previous follow-up inspection.
the direction protaction On 31/10/2016: Corrected.
ofegress trave equipments are in On 02-01-17: Corrected.
house On 06-04-17: Corrected.
,we will stard On 25/July/2017: Corrected.
work from On 25/03/2018: Corrected
october 2018 On 29/01/2019: Corrected.
Initial Inspection 11 Exit stair doors on theroof floor does n On 21/11/2019: Corrected.
Within 3 months Corrected
Provide handrails Fire detection Feb 18 2016
on bothsides of equipments & fire On 22-08-2016: Corrected.
the exit stair. protaction On 31/10/2016: Corrected.
Newhandrails equipments are in On 02-01-17: Corrected.
shall have house On 06-04-17: Corrected.
aminimum height ,we will stard On 25/July/2017: Corrected.
of 865 mm(34 in.) work from On 25/03/2018: Corrected
and a october 2018 On 29/01/2019: Corrected.
Initial Inspection 12 Handrails are notprovided on both sideso maximumheight On 21/11/2019: Corrected.
Within 3 months Corrected
of 965 mm (38 in.)
asmeasured from
the leadingedge
of the
tread.Intermediat
e handrails shallbe
provided when
Replace the fire Ditection system Jul 10 2016
alarmsystem with installation work On 22-08-2016: In progress. The drawing of fire alarm system ha
a new, on going On 31/10/2016: Installation work still not started.
listedaddressable On 02-01-17: It is found same as it was before.
fire alarmsystem On 06-04-17: No action has been taken regarding the order (LC)
in accordance On 25/July/2017: L/C has been opened.
withNFPA 72. On 25/03/2018: Same as before.
On 29/01/2019: Factory personnel informed that, materials are i
Initial Inspection 13 The fire alarm system is antiquated, n On 21/11/2019: Installation
Design within
work4hasmonbeen
In Progress
started.
Smoking is Corrected Feb 18 2016
prohibited in On 22/08/2016: Corrected. Posted.
anygarment On 31/10/2016: Corrected.
factory building On 02-01-17: Corrected.
orseparate storage On 06-04-17: Corrected.
building.Signs On 25/July/2017: Corrected.
shall be posted On 25/03/2018: Corrected
inBengali and On 29/01/2019: Corrected.
Initial Inspection 14 The required no smoking signs are not English at On 21/11/2019: Corrected.
Within 1 months Corrected
Inspect, test and Corrected
allbuilding Apr 25 2016
maintain
entrances. If On 22-08-2016: In progress. The factory is maintaining a checklis
theportable fire
thefactory creates On 31/10/2016: No action has been taken.
extinguishersand
a On 02-01-17: No action has been taken.
keep written
designatedsmokin On 06-04-17: Action shall be as per ACCORD Standard.
records onsite,in
g area outside On 25/July/2017: Corrected.
accordance
thebuilding, On 25/03/2018: Corrected
withNFPA
information10.of On 29/01/2019: Corrected.
Initial Inspection 15 Inspection, testing and maintenance oftheseareas will be On 21/11/2019: Corrected.
Within 3 months Corrected
Inspect,
posted ontest and Ditection system Jul 10 2016
maintain
thesigns. thefire installation work On 22-08-2016: It is an integrated part of fire alarm system.
alarm system and on going On 31/10/2016: No action has been taken.
keepwritten On 02-01-17: It is an integrated part of fire alarm system.
records on-site, On 06-04-17:It is an integrated part of fire alarm system.
inaccordance with On 25/July/2017: It's an integrated part of Fire alarm system.
NFPA 72. On 25/03/2018: It is an integrated part of FAS.
On 29/01/2019: It's an integrated part of Fire alarm system.
Initial Inspection 16 Inspection, testing and maintenance fo On 21/11/2019: It'sWithin 3 months
an integrated part In
ofProgress
Fire alarm system.
Provide fire Hydrent system Feb 18 2016
departmentconne installation work
ction in on going On 22-08-2016: Corrected as the highest occupiable floor height
accordancewith On 31/10/2016: In progress. Presently factory is 5 storied buildin
ACCORD On 02-01-17: Fire fighting system drawing has been reviewed by
standard5.5.4. On 25/July/2017: It's an integrated part of Fire Fighting system.
On 25/03/2018: It is an integrated part of FFS.
On 29/01/2019: Factory personnel informed that, materials are i
Initial Inspection 17 Fire department connection is not prov On 21/11/2019: FireWithin
pump3room
months
and reservoir
In Progress
constructions are
Inspect, test and Hydrent system Apr 25 2016
maintain the installation work On 22-08-2016: The factory has not provided any document for
stand pipe system on going On 31/10/2016: No action has been taken.
and keep written On 02-01-17: It is an integrated part of fire fighting system.
records on-site, in On 06-04-17:It is an integrated part of fire fighting system.
accordance with On 25/July/2017: It's an integrated part of Fire Fighting system.
NFPA 14. On 25/03/2018: No action has been taken for installation and m
On 29/01/2019: Factory personnel informed that, materials are i
Initial Inspection 18 Inspection, testing and maintenance of On 21/11/2019: It isWithin
an integrated
3 monthspartInofProgress
Fire Fighting system.
Provide visible Ditection system Jul 10 2016
and installation work On 22-08-2016: It is an integrated part of fire alarm system.
audiblenotificatio on going and PA On 31/10/2016: No action has been taken.
n for the building system has done. On 02-01-17: It is an integrated part of fire alarm system.
inaccordance with On 06-04-17:It is an integrated part of fire alarm system.
NFPA 72 On 25/July/2017: It's an integrated part of Fire alarm system.
On 25/03/2018: It is an integrated part of FAS.
On 29/01/2019: It is an integrated part of fire alarm system.
Initial Inspection 19 Visible and audible notification was n On 21/11/2019: It isWithin
an integrated
3 monthspartInofProgress
fire alarm system.
Provide additional Ditection system Jul 10 2016
notificationapplia installation work On 22-08-2016: It is an integrated part of fire alarm system.
nces such that the on going and PA On 31/10/2016: No action has been taken.
firealarm system is system has done. On 02-01-17: It is an integrated part of fire alarm system.
audiblethroughou On 06-04-17: No action has been taken yet.
t the building On 25/July/2017: It's an integrated part of Fire alarm system.
inaccordance with On 25/03/2018: It is an integrated part of FAS.
NFPA 72. On 29/01/2019: It is an integrated part of fire alarm system.
Initial Inspection 20 The fire alarm systemon each floor do On 21/11/2019: It isWithin
an integrated
6 monthspartInofProgress
fire alarm system.
Remove single- Ditection system Jul 10 2016
station installation work On 22-08-2016: It is an integrated part of fire alarm system.
smokealarms. on going . On 31/10/2016: No action has been taken.
Provide On 02-01-17: It is an integrated part of fire alarm system.
automaticsmoke On 06-04-17: No action has been taken yet.
detection On 25/July/2017: It's an integrated part of Fire alarm system.
throughoutthe On 25/03/2018: It is an integrated part of FAS.
building, tied into On 29/01/2019: It is an integrated part of fire alarm system.
Initial Inspection 21 The building is equippedwith single-s the firealarm On 21/11/2019: It isWithin
an integrated
9 monthspartInofProgress
fire alarm system.
Remove manual Corrected
system, in Feb 18 2016
on/offswitches
accordancewith On 22-08-2016: Corrected.
from
NFPA 72. On 31/10/2016: Corrected.
emergencylighting On 02-01-17: Corrected.
units to prevent On 06-04-17: Corrected.
themfrom being On 25/July/2017: Corrected.
switched off. On 25/03/2018: Corrected
On 29/01/2019: Corrected.
Initial Inspection 22 Manual on-off switch is provided for em On 21/11/2019: Corrected.
Within 1 month Corrected
Inspect, test and Corrected Apr 25 2016
maintain On 22-08-2016: In progress. The factory is maintaining a checklis
theemergency On 31/10/2016: No action has been taken.
lighting system On 02-01-17: No action has been taken.
inthe accordance On 06-04-17: Action shall be as per ACCORD Standard.
with TheACCORD On 25/July/2017: Corrected. Maintaining as per standard.
standard. On 25/03/2018: Corrected as per previous follow up. No docume
Keepwritten On 29/01/2019: Corrected.
Initial Inspection 23 Inspection, testing andmaintenance f records on-site. Within 3 months Corrected
On 21/11/2019: Corrected.
Test the Corrected May 12 2016
emergency On 22-08-2016: No action has been taken yet.
lightingsystem on On 31/10/2016: No action has been taken.
each floor On 02-01-17: Partially corrected. The factory management has in
andprovide On 06-04-17: It is found same as before.
additional On 25/July/2017: Corrected.
emergencyfixtures On 25/03/2018: Corrected
to supply On 29/01/2019: Corrected.
Initial Inspection 24 Based on the numberand location of emeadequateillumina On 21/11/2019: Corrected.
Within 3 months Corrected
Provide minimum
tion along the Corrected May 15 2016
aisle widths
meansof of 36-
egress. On 22-08-2016: No action has been taken yet.
inch.
Provide On 31/10/2016: Not corrected.
aminimum On 02-01-17: It is found same as it was before.
illumination of On 06-04-17: No action has been taken yet. It is found same as b
10lux at the floor On 25/July/2017: Corrected.
level withinexit On 25/03/2018: Corrected.
stairs and along On 29/01/2019: Corrected.
Follow Up Inspection 25 New Finding (1st Follow-up): The widthexitdischarge
o On 21/11/2019: Corrected.
Within 1 months Corrected
Remove
paths andall Corrected Jun 1 2016
combustible
aminimum 2.5 lux On 22-08-2016: In progress. Combustible construction material h
materials and
along exitaccess On 31/10/2016: No action has been taken.
replace
aisles. by non On 02-01-17: It is found same as it was before.
combustible On 06-04-17: Action shall be as per NFPA 101/Accord standard.
materials. On 25/July/2017: Corrected.
On 25/03/2018: Corrected.
On 29/01/2019: Corrected.
Follow Up Inspection 26 New Finding (1st Follow-up): Combustib On 21/11/2019: Corrected.
Within 1 month Corrected
Separate the Done May 15 2016
flammable gas On 23-08-2016: No action has been taken yet. Flammable gas cy
cylinder On 31/10/2016: Separation wall shall be minimum 10 feet heigh
storage area by a On 02-01-17: Corrected as per recommendation given during the
minimum 2- On 06-04-17: Corrected as per previous follow up inspection.
hr fire-rated On 25/July/2017: Corrected.
construction. Seal On 25/03/2018: It was found during latest follow up.
and/or protected On 29/01/2019: Not Corrected.
Follow Up Inspection 27 New finding (2nd Follow-up): Flammable all openings On 21/11/2019: NotWithin
seperated.
1 month In Progress
Seal all
to maintain the May 19 2016
penetrations
required fire and On 23-08-2016: No action has been taken yet.
openings to the
separations. On 31/10/2016: No action has been taken.
interior of the On 02-01-17: Partially corrected.
building along the On 06-04-17: Corrected.
discharge path, up On 25/July/2017: Corrected.
to a height of 10 On 25/03/2018: Corrected.
ft. to provide a On 29/01/2019: Corrected.
Follow Up Inspection 28 New Findings (3rd Follow up): The exit minimum
d 1-hr fire On 21/11/2019: Factory
Withinshall
1 month
seal the unsealed
In Progress
penetration alon
Remove locking Corrected
separation. Aug 24 2016
featuresfrom all
egress doors / On 22-08-2016: New Finding
gates.If locks are On 31/10/2016: Corrected. Fire door installation is on going.
required On 02-01-17: Corrected.
forsecurity On 25/July/2017: Corrected.
reasons, On 25/03/2018: Corrected.
utilizespecial door On 29/01/2019: Corrected.
Follow Up Inspection 29 New Finding (4th Follow Up): Non-complilocking On 21/11/2019: Corrected.
Immediately Corrected
Replace all gates / Corrected
featurescomplying Aug 29 2016
slidingdoors
with NFPA 101andalong
the means of
ACCORD On 22-08-2016: New Finding
egress with side-
standard6.8.2. On 31/10/2016: Corrected. Factory has been removed all collaps
hinged,swinging On 02-01-17: Corrected.
egress doors On 25/July/2017: Corrected.
inaccordance with On 25/03/2018: Corrected.
ACCORDstandard On 29/01/2019: Corrected.
Follow Up Inspection 30 New Finding (4th Follow Up): Collapsibl6.8.1 Within 1 week
On 21/11/2019: Corrected. Corrected
Provide stair Done Aug 27 2016
designationsigns On 22-08-2016: New Finding
and occupant On 31/10/2016: No action has been taken.
loadsigns at On 02-01-17: No action has been taken.
required locations On 06-04-17: Corrected.
On 25/July/2017: Corrected. Still some modifications are require
On 25/03/2018: Same as before.
On 29/01/2019: Partially Corrected, stair designation signage ava
Follow Up Inspection 31 New Finding (4th Follow Up): Stair desi On 21/11/2019: NoImmediately
progress has been Inobserved
Progresssince the previo
Keep egress paths Done Aug 25 2016
and stairs clear of On 22-08-2016: New Finding
storage. On 31/10/2016: Corrected.
On 02-01-17: Corrected.
On 06-04-17: Corrected.
On 25/July/2017: Corrected.
On 25/03/2018: Corrected.
On 29/01/2019: Re-opened. During inspection aisles were found
Follow Up Inspection 32 New Finding (4th Follow Up): Storage w On 21/11/2019: Storage
Immediately
has been observed
In Progress
inside the exit stair.
Modify the egress Corrected Nov 30 2016
door to swing in
the direction of On 31/10/2016: New finding.
egress travel. On 02-01-17: It is found same as it was before.
On 06-04-17: Action has been taken but not enough yet.
On 25/July/2017: Corrected.
On 25/03/2018: Corrected
On 29/01/2019: Corrected.
Follow Up Inspection 33 New Fiding: Exit stair door/egress door On 21/11/2019: Corrected.
Within 1 month Corrected
Date
07-Jan-2020 ELECTRICAL SAFETY