MC SHIPPING LTD.

SINGAPORE

INCIDENT REPORT
 Date of Preliminary report: 04 DEC.2019
 Date of Intermediate report: 06 DEC.2019
 Date of Final report: 10 Dec.2019

/// CONFIDENTIAL ///  INCIDENT REPORT (No.1)


TO : Technical Dept

SHIP TYPE : Bulk Carrier / Handymax

FROM: First Marine Service Co.,Ltd

SHIP NAME: ORION OCEAN MEMBER OF CREW : 20 including


Master
CHARTERER: AS KLAVENESS CHARTERING

SUB-CHARTERERS (if any): OXBOW ENERGY


SOLUTIONS

DATE/TIME OF INCIDENT: 03 DEC.2019 /2015LT PLACE: KANDLA,INDIA

VESSEL’S POSITION: LAT: 24-03.8N LONG: 061-55.0E

WEATHER CONDITION:CLOUDY

SEA ROUTE: AT SEA

Laden /Ballast: BALLAST


Type of Cargo: NIL

TYPE OF INCIDENT: DECK CRANE NO.1 LUFFING OPERATION TROUBLE

OUTLINE OF INCIDENT:C
03 Dec.2019 - at around 2015LT while the vessel is discharging cargo at Kandla,India, Deck Crane no.1
luffing will operate only when booming down, but when booming up the brake will not release thus
make the luffing inoperable during boom up.

ESTIMATED CAUSE(ON SHIP):

Spare part replacement = JPY 910,000


Transportation = JPY 265,000
Custom Clearance /Deliv. Charge = USD 1500

1
MC SHIPPING LTD. SINGAPORE

STATUS OF SPARES AVAILABILITY WHERE APPLICABLE:

New spare part delivered onboard on 8th Dec.2019 evening.

COUNTER MEASURES:
Removed vane pump of Deck crane no.2 and transferred to Deck crane no.1 .

08th Dec.19 - Received new spare vane pump


1900LT / 08th Dec 19 - Work permit issued by Port thru her agent
2030LT / " - New hyd. pump delivered on board
2030LT / " - Commence installation work by Engineers
2330LT / " - Completed installation then tested Deck crane no.2 luffing operation and found
satisfactory.

SHIP’S PROFILE:

BUILT: 16 SEP 2015

LAST DRY DOCK DATE: 23 JUN.2018

EQUIPMENT MAKER & MODEL:MITSUBISHI / ELECTRO HYDRAULIC

MACHINERY MAKER CONTACTED AND THEIR RECOMMENDATION (if applicable):

Maker recommended to transfer vane pump from no.2 or no.3 Deck crane and install in no.1 Deck
crane to determine if the vane pump is defective.

CLASS SURVEY CARRIED OUT : NA

SURVEY REPORT ENCLOSED : NA

PANAMA FLAG ADMINSTRATION INFORMED (where applicable): NA

P&I (name): Japan P & I

P&I INFORMED/ ATTENDED: NA

H&M (name): Tokio Marine Nichido Fire Insurance Co.

H&M INFORMED / ATTENDED: NA

LOCAL PORT AUTHORITIES INFORMED (where applicable): NA

2
MC SHIPPING LTD. SINGAPORE

ANY FOLLOW UP REPAIR REQUIRED:


- NA
DELAY SCHEDULE: about 18.75H
CARGO DAMAGE: NA
DAMAGE : DEFECTIVE VANE PUMP

OFF-HIRE : STOPPED DISCHARGING OPERATION ON CH NO.1 AROUND 2015 LT /03 RD DEC.2019 to


1500LT 04th Dec.2019

BUNKER CONSUMPTIONS DURING OFF-HIRE: NOT YET DETERMINE

Enclosures:
1. Relevant photographs: included
2. SOF : included
3. Other documents as required: Spare part delivery receipt