SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-127 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A


2 FW-128 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
3 FW-129 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
4 FW-130 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
5 FW-131 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
6 FW-132 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
7 FW-132A 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
8 FW-132B 21-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

Page 1
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QC INSPECTOR
SIGNATURE
DATE

Page 2
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-132C 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A

2 FW-132D 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A


3 FW-132E 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
4 FW-132F 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
5 FW-132G 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
6 FW-132H 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
7 FW-141 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
8 FW-142 22-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A

Page 3
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QC INSPECTOR
SIGNATURE
DATE

Page 4
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-143 23-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A


2 FW-144 23-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
3 FW-145 23-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
4 FW-146 23-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A

Page 5
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QC INSPECTOR
SIGNATURE
DATE

Page 6
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-147 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A


2 FW-148 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
3 FW-149 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
4 FW-150 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
5 FW-151 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
6 FW-152 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
7 FW-153 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
8 FW-154 24-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A

Page 7
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QC INSPECTOR
SIGNATURE
DATE

Page 8
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-155 25-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A


2 FW-156 25-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
3 FW-157 25-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
4 FW-158 25-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
5 FW-159 25-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
6 FW-160 25-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
7 FW-161 25-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

Page 9
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE
DATE

Page 10
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-162 26-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A


2 FW-163 26-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
3 FW-167 26-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

Page 11
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QC INSPECTOR

SIGNATURE
DATE

Page 12
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-168 27-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A


2 FW-169 27-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
3 FW-170 27-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
4 FW-171 27-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
5 FW-172 27-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

Page 13
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QC INSPECTOR
SIGNATURE
DATE

Page 14
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Sl Pipe Welder Weld Consumables


No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm
1 FW-173 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

2 FW-174 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

3 FW-175 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

4 FW-176 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE


5 FW-177 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

6 FW-178 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

7 FW-179 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

8 FW-180 28-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A

9 FW-194 28-Jun-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A

For Seeh Al-Sarya Engineering LLC


NAME: Mr.MITHUN.R.S
POSITION QA/QC INSPECTOR
SIGNATURE
DATE

Page 15
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-180A 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A


2 FW-181 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
3 FW-182 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
4 FW-183 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
5 FW-184 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
6 FW-185 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
7 FW-185A 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
8 FW-185B 29-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
9 FW-195 29-Jun-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A
10 FW-196 29-Jun-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A
11 FW-197 29-Jun-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A
12 FW-198 29-Jun-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A

Page 16
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE
DATE

Page 17
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-185C 30-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A


2 FW-185D 30-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
3 FW-185E 30-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
4 FW-185F 30-Jun-17 WPS 31 12"/10.31 29/852 58/888 PIPE/PIPE 1302K 1187A
5 FW-199 30-Jun-17 WPS 31 12"/10.31 1579 1839 PIPE/PIPE 1302K 1187A
6 FW-200 30-Jun-17 WPS 31 12"/10.31 1579 1839 PIPE/PIPE 1302K 1187A

Page 18
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE
DATE

Page 19
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-201 1-Jul-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A


2 FW-202 1-Jul-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A
3 FW-203 1-Jul-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A
4 FW-204 1-Jul-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A
5 FW-248 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
6 FW-249 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
7 FW-250 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
8 FW-251 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
9 FW-252 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
10 FW-253 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
11 FW-254 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
12 FW-255 1-Jul-17 WPS 31 12"/10.31 29/852 58/888 PIPE-PIPE 1302K 1187A
13 FW-256 1-Jul-17 WPS 31 12"/10.31 1579 1839 PIPE-PIPE 1302K 1187A

Page 20
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE
DATE

Page 21
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-257 2-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A


2 FW-258 2-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
3 FW-259 2-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
4 FW-260 2-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
5 FW-261 2-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
6 FW-262 2-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
7 FW-263 2-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
8 FW-86 2-Jul-17 WPS 31 12"/10.31 888/58 888/58 PIPE-BEND 1302K 1187A
9 FW-87 2-Jul-17 WPS 31 12"/10.31 888/58 888/58 BEND-PIPE 1302K 1187A

Page 22
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE
DATE

Page 23
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-264 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A


2 FW-265 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
3 FW-266 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
4 FW-267 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
5 FW-268 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
6 FW-269 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
7 FW-273 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
8 FW-274 3-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
9 FW-83 3-Jul-17 WPS 31 12"/10.31 888/58 888/58 BEND-PIPE 1302K 1187A
10 FW-84 3-Jul-17 WPS 31 12"/10.31 888/58 888/58 PIPE-BEND 1302K 1187A
11 FW-85 3-Jul-17 WPS 31 12"/10.31 888/58 888/58 BEND-PIPE 1302K 1187A

Page 24
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S
POSITION QA/QC INSPECTOR
SIGNATURE

DATE

Page 25
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-275 4-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A


2 FW-276 4-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
3 FW-277 4-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
4 FW-278 4-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
5 FW-279 4-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
6 FW-80 4-Jul-17 WPS 31 12"/10.31 888/58 888/58 BEND-PIPE 1302K 1187A
7 FW-81 4-Jul-17 WPS 31 12"/10.31 888/58 888/58 PIPE-BEND 1302K 1187A
8 FW-82 4-Jul-17 WPS 31 12"/10.31 888/58 888/58 BEND-PIPE 1302K 1187A

Page 26
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE

DATE DATE

Page 27
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-205 5-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A


2 FW-206 5-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A
3 FW-207 5-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A
4 FW-208 5-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A
5 FW-280 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
6 FW-281 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
7 FW-282 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
8 FW-283 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
9 FW-284 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
10 FW-285 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
11 FW-286 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
12 FW-287 5-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A

Page 28
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE

DATE DATE

Page 29
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-209 6-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A


2 FW-210 6-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A
3 FW-211 6-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A
4 FW-212 6-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A
5 FW-288 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
6 FW-289 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
7 FW-290 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
8 FW-291 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
9 FW-292 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
10 FW-293 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
11 FW-293A 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
12 FW-293B 6-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A

Page 30
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE
DATE DATE

Page 31
SEEH AL-SARYA ENGINEERING L L C

DAILY WELD PRODUCTION REPORT


Contract No: SWL-2011-24000017460 Work Order No
Contract Title: Construction of Flow line DPR#
Client: Occidental of Oman Incl Project no.
12" OIL PRODUCTION HEADER FROM REHAM
TEST PACK MANIFOLD TO SAQR MANIFOLD Specification:

Welder Weld Consumables


Sl Pipe
No Joint No Weld date WPS
Size W#01 W#02
Item E 6010 E 7010 P1
3.2mm 3.2mm

1 FW-213 7-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A


2 FW-214 7-Jul-17 WPS 31 12"/10.31 58 888 PIPE-PIPE 1302K 1187A
3 FW-293C 7-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
4 FW-293D 7-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
5 FW-302 7-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A
6 FW-303 7-Jul-17 WPS 31 12"/10.31 29/852 1579/1839 PIPE-PIPE 1302K 1187A

Page 32
For Seeh Al-Sarya Engineering LLC
NAME: Mr.MITHUN.R.S

POSITION QA/QC INSPECTOR


SIGNATURE
DATE

Page 33
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-16
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-16
2137403 1261-16
2137403 1261-16
2137403 1261-16
2137403 1261-16
2137403 1261-16
2137403 1261-16
2137403 1261-16

Page 34
Seeh Al-Sarya Engineering LLC

Page 35
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-17
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-17

2137403 1261-17
2137403 1261-17
2137403 1261-17
2137403 1261-17
2137403 1261-17
2137403 1261-17
2137403 1261-17

Page 36
Seeh Al-Sarya Engineering LLC

Page 37
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-018
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-18
2137403 1261-18
2137403 1261-18
2137403 1261-18

Page 38
Seeh Al-Sarya Engineering LLC

Page 39
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-19
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-19
2137403 1261-19
2137403 1261-19
2137403 1261-19
2137403 1261-19
2137403 1261-19
2137403 1261-19
2137403 1261-19

Page 40
Seeh Al-Sarya Engineering LLC

Page 41
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-20
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-20
2137403 1261-20
2137403 1261-20
2137403 1261-20
2137403 1261-20
2137403 1261-20
2137403 1261-20

Page 42
Seeh Al-Sarya Engineering LLC

Page 43
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-21
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-21
2137403 1261-21
2137403 1261-21

Page 44
Seeh Al-Sarya Engineering LLC

Page 45
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-22
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-22
2137403 1261-22
2137403 1261-22
2137403 1261-22
2137403 1261-22

Page 46
Seeh Al-Sarya Engineering LLC

Page 47
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-23
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm
2137403 1261-23

2137403 1261-23

2137403 1261-23

2137403

2137403 1261-23

2137403 1261-23

2137403 1261-23

2137403 1261-23

2137403 1261-23

Seeh Al-Sarya Engineering LLC

Page 48
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-24
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24
2137403 1271-24

Page 49
Seeh Al-Sarya Engineering LLC

Page 50
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-25
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-25
2137403 1261-25
2137403 1261-25
2137403 1261-25
2137403 1261-25
2137403 1261-25

Page 51
Seeh Al-Sarya Engineering LLC

Page 52
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-26
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26
2137403 1261-26

Page 53
Seeh Al-Sarya Engineering LLC

Page 54
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-27
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-27
2137403 1261-27
2137403 1261-27
2137403 1261-27
2137403 1261-27
2137403 1261-27
2137403 1261-27
2137403 1261-27
2137403 1261-27

Page 55
Seeh Al-Sarya Engineering LLC

Page 56
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-28
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28
2137403 1261-28

Page 57
Seeh Al-Sarya Engineering LLC

Page 58
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-29
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-29
2137403 1261-29
2137403 1261-29
2137403 1261-29
2137403 1261-29
2137403 1261-29
2137403 1261-29
2137403 1261-29

Page 59
Seeh Al-Sarya Engineering LLC

Page 60
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-30
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30
2137403 1261-30

Page 61
Seeh Al-Sarya Engineering LLC

Page 62
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-31
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31
2137403 1261-31

Page 63
Seeh Al-Sarya Engineering LLC

Page 64
L-SARYA ENGINEERING L L C

WELD PRODUCTION REPORT


SAS 1261
1261-32
1207897

API 1104

Weld Consumables
Remarks
E 7010 P1
4mm

2137403 1261-32
2137403 1261-32
2137403 1261-32
2137403 1261-32
2137403 1261-32
2137403 1261-32

Page 65
Seeh Al-Sarya Engineering LLC

Page 66