C1 C2 C3 C4 C5
C6 C8
C7
C9
C12
C10
C11
C14
C13 C15
SCALE 1 : 5
NOTE:
1- ALL CONCRETE OF MIX M20 UNLESS OTHERWISE SPECIFIED
2- ALL STEEL REINFORCEMENT OF GRADE Fe415
3- CLEAR COVER : COLUMN - 40mm, BEAMS - 25mm, SLABS & STAIR CASE - 15mm
4- SBC OF SOIL TAKEN AS 200KN/M2 WHICH IS TO BE VERIFIED AT SITE