Project Title -AUIB - Data Center Building 98A

◆ Project Name: Construction of Data Center "Working Program" Plan Actual

Plan Submitalls Actual / Forcast Duration Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20
Activity Name Start Finish Code Status Start Finish Actual Forecast 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27

01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27

2/1/2020 2/3/2020 2/5/2020 2/7/2020 2/9/2020 2/11/2020 2/13/2020 2/15/2020 2/17/2020 2/19/2020 2/21/2020 2/23/2020 2/25/2020 2/27/2020 2/29/2020 3/2/2020 3/4/2020 3/6/2020 3/8/2020 3/10/2020 3/12/2020 3/14/2020 3/16/2020 3/18/2020 3/20/2020 3/22/2020 3/24/2020 3/26/2020 3/28/2020 3/30/2020 4/1/2020 4/3/2020 4/5/2020 4/7/2020 4/9/2020 4/11/2020 4/13/2020 4/15/2020 4/17/2020 4/19/2020 4/21/2020 4/23/2020 4/25/2020 4/27/2020 4/29/2020 5/1/2020 5/3/2020 5/5/2020 5/7/2020 5/9/2020 5/11/2020 5/13/2020 5/15/2020 5/17/2020 5/19/2020 5/21/2020 5/23/2020 5/25/2020 5/27/2020 5/29/2020 5/31/2020 6/2/2020 6/4/2020 6/6/2020 6/8/2020 6/10/2020 6/12/2020 6/14/2020 6/16/2020 6/18/2020 6/20/2020 6/22/2020 6/24/2020 6/26/2020 6/28/2020 6/30/2020 7/2/2020 7/4/2020 7/6/2020 7/8/2020 7/10/2020 7/12/2020 7/14/2020 7/16/2020 7/18/2020 7/20/2020 7/22/2020 7/24/2020 7/26/2020 7/28/2020 7/30/2020 8/1/2020 8/3/2020 8/5/2020 8/7/2020 8/9/2020 8/11/2020 8/13/2020 8/15/2020 8/17/2020 8/19/2020 8/21/2020 8/23/2020 8/25/2020 8/27/2020 8/29/2020 8/31/2020 9/2/2020 9/4/2020 9/6/2020 9/8/2020 9/10/2020 9/12/2020 9/14/2020 9/16/2020 9/18/2020 9/20/2020 9/22/2020 9/24/2020 9/26/2020 9/28/2020 9/30/2020 10/2/2020 10/4/2020 10/6/2020 10/8/2020 10/10/2020 10/12/2020 10/14/2020 10/16/2020 10/18/2020 10/20/2020 10/22/2020 10/24/2020 10/26/2020 10/28/2020 10/30/2020 11/1/2020 11/3/2020 11/5/2020 11/7/2020 11/9/2020 11/11/2020 11/13/2020 11/15/2020 11/17/2020 11/19/2020 11/21/2020 11/23/2020 11/25/2020 11/27/2020

Milestone

Engineering - Submittals

TMC-DC-001 Architectural Drawings Bldg.98A 18-Jan-20 25-Jan-20 submit 0 7


TMC-DC-002 Sewer network / data center bldg.98A 2-Oct-19 9-Oct-19 CLOSE 0 7

TMC-DC-003 Mechanical shopdrawing - Bldg. 98 data center 10-Jan-20 15-Jan-20 CLOSE 0 5

TMC-DC-004 Storm Water Network of BLD.98A ( Data Center). 10-Jan-20 17-Jan-20 OPEN 0 7
TMC-DC-005 HVAC system including ducts and accosseries 19-Dec-19 26-Dec-19 Inprogress 0 7
TMC-DC-006 Sewer Lift station 6-Jan-00 Inprogress 0 7

TMC-DC-006 GPON system 25-Jan-20 30-Jan-20 waiting 0 5

TMC-DC-007 WAP system 25-Jan-20 30-Jan-20 waiting 0 5


TMC-DC-008 VOIP system 25-Jan-20 30-Jan-20 waiting 0 5

TMC-DC-009 IPTV system 25-Jan-20 30-Jan-20 waiting 0 5

TMC-DC-010 Fire alarm system 25-Jan-20 30-Jan-20 waiting 0 5


TMC-DC-011 CCTV system 25-Jan-20 30-Jan-20 waiting 0 5
TMC-DC-009 AV system 25-Jan-20 30-Jan-20 waiting 0 5
TMC-DC-009 PAVA system 25-Jan-20 30-Jan-20 waiting 0 5
Fire supression system FM200 for UPS and server
TMC-DC-012 room only
waiting 0 7

TMC-DC-013 Access control system 25-Jan-20 27-Jan-20 waiting 0 2


TMC-DC-014 Lighting system for meeting room only 25-Jan-20 4-Feb-20 waiting 0 10
TMC-DC-015 Envinromental monitoring system for server room 25-Jan-20 30-Jan-20 waiting 0 5
TMC-DC-016 Lightng system for Data center 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-017 UPS calculation, desing 25-Jan-20 2-Feb-20 waiting 0 8
TMC-DC-018 LV system with electrical distribution 25-Jan-20 26-Jan-20 waiting 0 1

TMC-DC-019 Grounding system for Building Structure 25-Jan-20 26-Jan-20 waiting 0 1

TMC-DC-020 Grounding system for LV 25-Jan-20 26-Jan-20 waiting 0 1


TMC-DC-021 Lightning arrestor for data center 25-Jan-20 26-Jan-20 waiting 0 1
TMC-DC-022 Life and saftey plan 21-Jan-20 22-Jan-20 Inprogress 0 1
TMC-DC-068 Wall Paint data sheet 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-069 Structure paint data sheet 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-070 Floor Epoxy data sheet 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-071 Fire rated gypum board data sheet 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-072 Raise Floor fire rated data sheet 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-073 Sanetry work 25-Jan-20 27-Jan-20 waiting 0 2

TMC-DC-074 Kitchen work 25-Jan-20 27-Jan-20 waiting 0 2

TMC-DC-075 Doors data sheet 25-Jan-20 27-Jan-20 waiting 0 2


TMC-DC-075 Fiber cement board for all inside walls data sheet 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-075 Walk way 25-Jan-20 27-Jan-20 waiting 0 2
TMC-DC-076 Storm water trench 25-Jan-20 27-Jan-20 waiting 0 2

Engineering - Approvals

TMC-DC-001 Architectural Drawings Bldg.98A 26-Jan-20 27-Jan-20 Inprogress 0 1


TMC-DC-023 Sewer network / data center bldg.98A 25-Jan-20 1-Feb-20 C OPEN 0 7

TMC-DC-024 Mechanical shopdrawing - Bldg. 98 data center 7-Dec-19 14-Dec-19 B CLOSE 0 7

TMC-DC-025 Storm Water Network of BLD.98A ( Data Center). 15-Jan-20 22-Jan-20 B OPEN 0 7
TMC-DC-026 HVAC system including ducts and accosseries 19-Dec-19 26-Dec-19 D OPEN 0 7

TMC-DC-027 Sewer Lift station not submit 0 7

TMC-DC-028 GPON system 30-Jan-20 1-Feb-20 not submit 0 2

TMC-DC-029 WAP system 30-Jan-20 1-Feb-20 not submit 0 2


TMC-DC-030 VOIP system 30-Jan-20 1-Feb-20 not submit 0 2

TMC-DC-031 IPTV system 30-Jan-20 1-Feb-20 not submit 0 2

TMC-DC-032 Fire alarm system 30-Jan-20 1-Feb-20 not submit 0 2


TMC-DC-033 CCTV system 30-Jan-20 1-Feb-20 not submit 0 2
TMC-DC-034 AV system 30-Jan-20 1-Feb-20 not submit 0 2
TMC-DC-034 PAVA system 30-Jan-20 1-Feb-20 not submit 0 2
TMC-DC-035 Fire supression system not submit 0 7
TMC-DC-036 Access control system 27-Jan-20 3-Feb-20 not submit 0 7
TMC-DC-037 Lighting system for meeting room only 4-Feb-20 11-Feb-20 not submit 0 7
TMC-DC-038 Envinromental monitoring system for server room 30-Jan-20 6-Feb-20 not submit 0 7
TMC-DC-039 Ligitng system for Data center 27-Jan-20 3-Feb-20 not submit 0 7
TMC-DC-040 UPS calculation, desing, installion and distribuiton 2-Feb-20 4-Feb-20 not submit 0 2
TMC-DC-041 LV system with electrical distribution 27-Jan-20 29-Jan-20 D OPEN 0 2

TMC-DC-042 Grounding system for Building Structure 27-Jan-20 29-Jan-20 not submit 0 2

TMC-DC-043 Grounding system for LV systems 27-Jan-20 29-Jan-20 not submit 0 2


TMC-DC-044 Lightning arrestor for data center 1-Feb-20 3-Feb-20 not submit 0 2
TMC-DC-045 Life and saftey plan not submit 0 7
TMC-DC-068 Wall Paint 27-Jan-20 30-Jan-20 not submit 0 3
TMC-DC-069 Structure paint 27-Jan-20 30-Jan-20 not submit 0 3
TMC-DC-070 Floor Epoxy 27-Jan-20 30-Jan-20 not submit 0 3
TMC-DC-071 Fire rated gypum board 27-Jan-20 30-Jan-20 not submit 0 3
TMC-DC-072 Raise Floor fire rated 27-Jan-20 30-Jan-20 not submit 0 3
MHC - JDC- SAB - Working Program 1 of 3
Plan Submitalls Actual / Forcast Duration Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20
Activity Name Start Finish Code Status Start Finish Actual Forecast 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27

01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27
TMC-DC-072 Raise Floor fire rated 27-Jan-20 30-Jan-20 not submit 0 3
TMC-DC-073 Sanetry work 27-Jan-20 30-Jan-20 not submit 0 3

TMC-DC-074 Kitechen work 27-Jan-20 30-Jan-20 not submit 0 3

TMC-DC-075 Doors 27-Jan-20 30-Jan-20 not submit 0 3


TMC-DC-075 Fiber cement board for all inside walls 27-Jan-20 30-Jan-20 not submit 0 3
TMC-DC-075 Walk way 27-Jan-20 30-Jan-20 not submit 0 3
TMC-DC-076 Storm water trench 27-Jan-20 30-Jan-20 not submit 0 3

Procurement - Materials Order Actual Forecast

TMC-DC-046 Sewer network / data center bldg.98A 0 7

TMC-DC-047 Mechanical shop drawing - Bldg. 98 data center 0 7

TMC-DC-048 Storm Water Network of BLD.98A ( Data Center). 0 7


TMC-DC-049 HVAC system including ducts and accosseries 0 7
TMC-DC-050 Sewer Lift station 0 7

TMC-DC-051 GPON system 11-Sep-19 9-Jan-20 Available 0 120


TMC-DC-052 WAP system 11-Sep-19 9-Jan-20 Available 0 120
TMC-DC-053 VOIP system 19-Sep-19 11-Jan-20 Available 0 114
Waiting for
TMC-DC-054 IPTV system 23-Sep-19 24-Jan-20 shipment
0 123
Waiting for
TMC-DC-055 AV system 26-Dec-19 5-Mar-20 shipment
0 70
TMC-DC-055 PAVA system 16-Sep-19 24-Jan-20 Available 0 130
TMC-DC-056 Fire alarm system 23-Sep-19 12-Jan-20 Available 0 111
TMC-DC-057 CCTV system 11-Sep-19 9-Jan-20 Available 0 120
Waiting for
TMC-DC-058 Fire supression system- Mechanical Part 23-Sep-19 21-Mar-20 shipment
0 180
Waiting for
TMC-DC-059 Access control system 1-Dec-19 29-Feb-20 shipment
0 90
TMC-DC-060 Lighting system for meeting room only 6-Jan-00 Not submit 0 7
TMC-DC-061 Envinromental monitoring system for server room 6-Jan-00 0 7
TMC-DC-062 Ligitng system for Data center 3-Feb-20 23-Feb-20 0 20
TMC-DC-063 UPS 4-Feb-20 24-Feb-20 0 20
TMC-DC-064 LV system with electrical distribution 29-Jan-20 18-Feb-20 0 20

TMC-DC-065 Grounding system for Building Structure 29-Jan-20 18-Feb-20 0 20

TMC-DC-066 Grounding system for LV systems 29-Jan-20 18-Feb-20 0 20


TMC-DC-067 Lightning arrestor for data center 3-Feb-20 23-Feb-20 0 20
TMC-DC-068 Wall Paint 30-Jan-20 9-Feb-20 0 10
TMC-DC-069 Structure paint 30-Jan-20 9-Feb-20 0 10
TMC-DC-070 Floor Epoxy 30-Jan-20 9-Feb-20 0 10
TMC-DC-071 Fire rated gypum board 30-Jan-20 9-Feb-20 0 10
TMC-DC-072 Raise Floor fire rated 30-Jan-20 9-Feb-20 0 10
TMC-DC-073 Senaitry work 30-Jan-20 9-Feb-20 0 10

TMC-DC-074 Kitchen work 30-Jan-20 9-Feb-20 0 10

TMC-DC-075 Doors 30-Jan-20 9-Feb-20 0 10


TMC-DC-075 Fiber cement board for all inside walls 30-Jan-20 9-Feb-20 0 10
TMC-DC-075 Walk way 16-Feb-20 21-Feb-20 0 5
TMC-DC-076 Storm water trench 16-Feb-20 21-Feb-20 0 5
TMC-DC-076 Escape route and emergency lighting 0 7

Procurement - Materials Delivery (Including Long Lead) Actual Forecast

Waiting for
TMC-DC-054 IPTV system 23-Sep-19 24-Jan-20 shipment
0 123
TMC-DC-080 Envinromental monitoring system for server room 0 7
Waiting for
TMC-DC-058 Fire supression system- Mechanical Part 23-Sep-19 21-Mar-20 shipment
0 180
Waiting for
TMC-DC-059 Access control system 1-Dec-19 29-Feb-20 shipment
0 90
Waiting for
TMC-DC-055 AV system 26-Dec-19 5-Mar-20 shipment
0 70
TMC-DC-081 UPS 0 7

TMC-DC-082 Mist Water Fire fighting system 0 7


TMC-DC-083 Aersol fire supression optional 0 7
TMC-DC-083 Envinromental monitoring system for server room 0 7

Execution - Civil Works Actual Forecast

TMC-DC-084 Structure Paint 20-Feb-20 25-Feb-20 0 5

TMC-DC-085 Fire rated gypum board ceiling 24-Feb-20 10-Mar-20 0 15


Fiber cement board for all inside walls + door
TMC-DC-086 frames
24-Feb-20 10-Mar-20 0 15

TMC-DC-087 Fire rated wall paint 6-Mar-20 16-Mar-20 0 10


TMC-DC-088 Floor Epoxy 9-Mar-20 14-Mar-20 0 5
TMC-DC-089 Raise Floor fire rated 23-Feb-20 26-Feb-20 0 3
TMC-DC-090 Doors 24-Feb-20 5-Mar-20 0 10
TMC-DC-091 Snetry + WC work 25-Feb-20 11-Mar-20 0 15
TMC-DC-092 Kitchen work 26-Feb-20 12-Mar-20 0 15
TMC-DC-093 Walk way 21-Feb-20 2-Mar-20 0 10

TMC-DC-094 Storm water trench + lift station ( if new) 1-Feb-20 21-Feb-20 0 20

Execution - Electrical Works - Stage# 01 (Containment works) Actual Forecast

TMC-DC-092 Ligitng system for Data center 25-Feb-20 26-Mar-20 0 30

TMC-DC-093 UPS 10-Mar-20 9-Apr-20 0 30


TMC-DC-094 LV system with electrical distribution 16-Mar-20 15-Apr-20 0 30
TMC-DC-095 Grounding system for Building Structure 14-Mar-20 13-Apr-20 0 30
TMC-DC-096 Grounding system for LV systems 26-Feb-20 27-Mar-20 0 30

TMC-DC-097 Lightning arrestor for data center 5-Mar-20 4-Apr-20 0 30

Execution - Electrical Works - Stage# 02 (Cable laying and dev Actual Forecast
MHC - JDC- SAB - Working Program 2 of 3
Plan Submitalls Actual / Forcast Duration Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20
Activity Name Start Finish Code Status Start Finish Actual Forecast 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27

01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27
Execution - Electrical Works - Stage# 02 (Cable laying and dev Actual Forecast

TMC-DC-092 Ligitng system for Data center 30-Dec-99 29-Jan-00 0 30


TMC-DC-093 UPS 30-Dec-99 29-Jan-00 0 30

TMC-DC-094 LV system with electrical distribution 30-Dec-99 29-Jan-00 0 30


TMC-DC-095 Grounding system for Building Structure 30-Dec-99 29-Jan-00 0 30
TMC-DC-096 Grounding system for LV systems 30-Dec-99 29-Jan-00 0 30
TMC-DC-097 Lightning arrestor for data center 30-Dec-99 29-Jan-00 0 30

Execution - Mechaincal Works Actual Forecast

TMC-DC-098 Sewer network / data center bldg.98A 26-Mar-20 25-Apr-20 0 30


TMC-DC-099 Mechanical shop drawing - Bldg. 98 data center 9-Apr-20 9-May-20 0 30
TMC-DC-100 Storm Water Network of BLD.98A ( Data Center). 15-Apr-20 15-May-20 0 30
TMC-DC-101 HVAC system including ducts and accosseries 13-Apr-20 13-May-20 0 30

TMC-DC-102 Sewer Lift station 27-Mar-20 26-Apr-20 0 30

Execution - ICT Works - Stage# 01 (Containment works) Actual Forecast

TMC-DC-103 GPON system 2-Feb-20 22-Feb-20 0 20

TMC-DC-104 WAP system 2-Feb-20 22-Feb-20 0 20


TMC-DC-105 VOIP system 2-Feb-20 22-Feb-20 0 20
TMC-DC-106 IPTV system 2-Feb-20 22-Feb-20 0 20
TMC-DC-107 AV system 2-Feb-20 22-Feb-20 0 20
TMC-DC-107 PAVA system 2-Feb-20 22-Feb-20 0 20
TMC-DC-108 Fire alarm system 2-Feb-20 22-Feb-20 0 20
TMC-DC-109 CCTV system 2-Feb-20 22-Feb-20 0 20

TMC-DC-110 Fire supression system 2-Feb-20 22-Feb-20 0 20


TMC-DC-111 Access control system 2-Feb-20 22-Feb-20 0 20
TMC-DC-112 Lighting system for meeting room only 2-Feb-20 22-Feb-20 0 20
TMC-DC-113 Envinromental monitoring system for server room 2-Feb-20 22-Feb-20 0 20

Execution - ICT Works - Stage# 02 (Cable laying and device Ins Actual Forecast

TMC-DC-103 GPON system 23-Feb-20 19-Mar-20 0 25


TMC-DC-104 WAP system 23-Feb-20 19-Mar-20 0 25
TMC-DC-105 VOIP system 23-Feb-20 19-Mar-20 0 25

TMC-DC-106 IPTV system 23-Feb-20 19-Mar-20 0 25


TMC-DC-107 AV system 23-Feb-20 19-Mar-20 0 25
TMC-DC-107 PAVA system 23-Feb-20 19-Mar-20 0 25

TMC-DC-108 Fire alarm system 23-Feb-20 19-Mar-20 0 25


TMC-DC-109 CCTV system 23-Feb-20 19-Mar-20 0 25

TMC-DC-110 Fire supression system 23-Feb-20 19-Mar-20 0 25


TMC-DC-111 Access control system 23-Feb-20 19-Mar-20 0 25
TMC-DC-112 Lighting system for meeting room only 23-Feb-20 19-Mar-20 0 25

TMC-DC-113 Envinromental monitoring system for server room 23-Feb-20 19-Mar-20 0 25

Execution -Testing & Commissioning Works Actual Forecast

TMC-DC-040 22-Feb-20 22-Apr-20 0 60


TMC-DC-041 22-Feb-20 22-Apr-20 0 60

TMC-DC-042 22-Feb-20 22-Apr-20 0 60


TMC-DC-043 22-Feb-20 22-Apr-20 0 60
TMC-DC-044 22-Feb-20 22-Apr-20 0 60

MHC - JDC- SAB - Working Program 3 of 3