DESIGN REVIEW MEETING #3 BANDUNG

-
No : 011. /TRANS/PV-JAY/BAC/OZJ18 Dated : llf F~blvQ!) 2018 Received date :1'1 February 2018
No : MOM15022018 Dated : 15 February 2018

CCROUT DATE
REVIEW FOR APPROVAL DRAWINGS I DOCUMENTS
DRM3 15 Feb 2018

DRAWING I DOCUMENT NUMBER


DRAWING I DOCUMENT TITLE
PLN REV. CONTRACTOR REV. STATUS
11 0268.5.1-00-C-02-0C-0004-00- \ 1 JAY-0-0CB-CV-CAL-002 1 A EARTHWORK CALCULATION REPORT
Comm't Comm't
PLN'S COMMENTS CONTRACTOR'S RESPONSE
No. No.
1 Approval does not relieve contractor from responsibility for error or deviations
from contract requirements

Date of Issued : January , 2018 Reviewed by : Checked by : \tJ


1/1 h Prl PT PLN (Persero) Pusat EnjiniringKetenagalistrikan
PLTMG JAYAPURA PEAKER (40 MW)
CONTRACTOR DOCUMENT REV IEW
R
CIVIL
If~ ~ I
f
LOG DATE: \'t ( Ov/t & E MECH
IN COMM NO:
v ELECT
Off-N ? I
A o f PPROVED E I&C
w
8 rsi APPROVED AS NOTED SUPPORT

c 0 NOT APPROVED CONTRACTOR

I 0 INFORMATION D RECORD
I
s WORKING DOCUMENT
T
APPROVED DOES NOT RELIEVE CONTRACTOR FROM R
RESPONSIBILITY FOR ERROR OR DEVIATIONS FROM I
CONTRACT REQUIREMENTS 8
u
T
BY
~ I DATE \~\'l- \~
1 I
0
DATE: \Vuz-1t..o r & N
LOG
OUT COMM NO: 012--HJ

0 14/02/ 18 ISSUED FOR APPROVAL

NO STATUS DATE REVISION AND RECORD OF ISSUE DRN DES CHK POE APP

[!] PT PLN (PERSERO)

PT PLN (PERSERO) PUSAT ENJINIRING KETENAGALISTRIKAN

PLN DWG No. 110268.5. 1-00-C-02-0C-0004-00-0


I
PACKAGE V FIX ED POWER PLANT SAC DRAWING NUMBER SAC REV NO
PLTMG JAYAPURA PEAKER 40 MW JAY -0-0CB-CV-CAL-002 L
CODE
EARTHWORK CALCULATION REPORT
AREA
EARTHWORK CALCULATION REPORT

PROJECT : PACKAGE V – EPC POWER PLANT


OWNER : PT. PLN (Persero)
LOCATION : JAYAPURA
DOC. NO. : JAY-O-OCB-CV-CAL-002
AECOM PROJECT NO. : JKTD17055

0 Issued for Approval 03.01.2018 BITA AI DBM


REV DESCRIPTION DATE PREPARED CHKD APVD

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
AECOM’s JOB NO: Rev.
JKTD17055
0
EARTHWORK CALCULATION DOC. NO.

REPORT JAY-O-OCB-CV-CAL-002
Date: By: CHKD: APVD:

03.01.18 BITA AI DBM

HISTORICAL REVISION SHEET


Rev No Date Description
0 03-01-2018 Issued for Approval

INTERNAL DISTRIBUTION

☐ BITA ☐ AECOM ☐ CONSORTIUM

☐ Project Manager ☐ Project Director ☐ Project Director ☐ Project Coordinator


☐ Project
☐ Project Control Manager ☐ Project Control Manager ☐ QA/QC Engineer
Administration
☐ QC Manager ☐ Project Controller ☐ Engineering Manager ☐ Procurement Supervisor
☐ SHE Manager ☐ Lead Civil ☐ Construction Manager ☐ SHE Eng
☐ Admin & Finance Manager ☐ Lead Mechanical ☐ General Support Manager ☐ Commissioning Manager

☐ Engineering Manager ☐ Lead Electrical ☐ Finance Manager


☐ Project Engineer ☐ Finance Manager ☐ SHE Manager
☐ Mechanical Lead Engineer ☐ Document Control
☐ Lead
☐ Piping Lead Engineer
Geotechnical
☐ Process Lead Engineer ☐ HSE Manager
☐ Civil Lead Engineer
☐ Electrical Lead Engineer
☐ Instrument Lead Engineer

BAGUS KARYA - AECOM - COGINDO

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
EARTHWORK CALCULATION REPORT

Client : PT PLN Revision 0


Project : EPC Package 5 Fixed Power Plant Project By BITA
Document No. : JAY-O-OCB-CV-CAL-002 Check AI
Approve DBM
Date 03.01.18

Table of Contents
1.0 General 1
1.1 Introduction 1
1.2 Scope 1
1.3 Language 1
1.4 Units of Measurement 1
1.5 Codes and Standards 1
1.6 Abbreviations 1
2.0 EARTHWORK DESIGN 2
2.1 Site Location 2
2.2 Topographic Map 2
2.3 Earthwork Scheme 3
2.4 Shrinkage and Swelling Factor 3
2.5 Earthwork Plan and Sections 5
2.6 Earthwork Volume Calculation 7
2.7 Fill Soil Parameter Specification 8

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
i
EARTHWORK CALCULATION REPORT

Client : PT PLN Revision 0


Project : EPC Package 5 Fixed Power Plant Project By BITA
Document No. : JAY-O-OCB-CV-CAL-002 Check AI
Approve DBM
Date 03.01.18

List of Tables
Table 1. List of Abbreviations 1
Table 2. Shrinkage and swelling factors (Burch 1997). 4
Table 3. Earthwork Volume Calculation 8
Table 4. Backfilling Sieve Size Requirement 8

List of Figures
Figure 1 Topographic Map– Jayapura 2
Figure 2. Location– Jayapura 3
Figure 3. Site Grading Plan 5
Figure 4. Earthwork Bedding Plan 7

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
ii
Page 1 of 8

EARTHWORK CALCULATION REPORT

1.0 General
1.1 Introduction
PT Perusahaan Listrik Negara (Persero is developing a cluster of small and medium sized electric generation
power plants (the Facility). Spread over six regions of the Indonesian archipelago The Facility), with their
locations and corresponding capacities.

1.2 Scope
The scope of this document is to design the Bau-Bau PLTMG site civil work not including the initial/ existing
areas, there is consist of earthwork scheme, road pavement design, storm water/drainage, fencing. The
purpose of this report is to provide engineering back up calculation.

1.3 Language
All drawings, calculations and documents shall be written in English.

1.4 Units of Measurement


Units of Measurement in the Design shall be SI system.

1.5 Codes and Standards


In principle, the following Codes and Standards shall be applied.
 Alexandria Rhea Crooks, (2013), Application of Shrinkage and Swelling Factors on State Highway
Construction.

1.6 Abbreviations
Table 1. List of Abbreviations

Term Abbreviations

EARTHWORK

MASL Meter above sea level

EL Existing Level

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 2 of 8

EARTHWORK CALCULATION REPORT

2.0 EARTHWORK DESIGN


2.1 Site Location
The specified location within the working area of PLN were located in Holtekamp Village, Muaratani
District, Jayapura Regency, Papua Province, to eastward approximately 45 km from Santani Airport
or 27 km from Jayapura city.

2.2 Topographic Map


Topographic condition of the existing site for development a PLTMG as described on the Figure 1.

Initial/Existing Area

Pond

Existing Trench

Figure 1 Topographic Map– Jayapura

Based on topographic maps, the initial terrains were laid off at various levels, there are range of 2 to
3.5 MASL. Majorly the central and south areas are surrounded by lowest terrain into face off the
coastal area. The pond’s bottom level is about -2 MASL, there was a natural pond which
intentionally excavate for personal consumable based on site information. The existing trench is
around from north until south sides, those areas are could not be hampered during construction.

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 3 of 8

EARTHWORK CALCULATION REPORT

2.3 Earthwork Scheme


The PLTMG area is about 250 meter along from the coastal. Based on the condition, there was no
flood or any possibility the site will be flooded by sea water, even though no tidal or waves study
which coverage the disaster which come through.

±250 m

Figure 2. Location– Jayapura

Design grading was designed by considering design criteria as follows:


- Minimizing damage to the environment due to the construction of PLTMG.
- Considering the soil subgrade and given a free board the area from rob flood surcharge, wind
set up of the water surface and wave action, backfill the develop site is the best option.
- Considering design of stormwater drainage system, where all of storm water runoff will be
discharged to the sea by gravity.
- Integrated level between existing road and any nearest infrastructure access.
- Providing flat level areas for all of facilities.

2.4 Shrinkage and Swelling Factor


Shrinkage and swelling factors account for the volume change on a project between the various
stages of soil placement. Generally, soil shrinks when going from a loose state to a compacted
state, and soil swells from the insitu soil state to a looser volumetric state. When conducting
earthwork estimates, shrinkage and/or swelling factors are applied to the soils present in an attempt
to compensate for changes in volumetric amounts.

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 4 of 8

EARTHWORK CALCULATION REPORT

It is important to note that shrink and swell in this research refers to this volume change in soils
during construction. This volume change is due to the shifting of soil particles when a soil is
unearthed, moved, and/or compacted. This is not referring to shrink/swell clays which
have a high plasticity index. The volume of shrink/swell clays alters when there is a change in water
content in the soil, and therefore varies insitu. The topic of discussion in this research, therefore, is
the shrinking and swelling of soils in the excavation and placement processes during construction,
not shrink/swell clays.
It is also important to note the use of different shrink and swell terms in this report. Shrinkage and
swelling factors are the factors applied to earthwork calculations. The factors are used as
conversions between different soil volumetric states. On the other hand, shrink and swell values
refer to the potential of a soil to shrink and swell in volume. This potential is usually in the form of a
percentage which can then be converted to a factor for use in earthwork calculations.
Table 2. Shrinkage and swelling factors (Burch 1997).

Based on the table above, swell factor has been determined 1.13 and 1.00 for shrinkage factor.
swell factor will input to determine a fill volume and shrinkage for cut volume.

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 5 of 8

EARTHWORK CALCULATION REPORT

2.5 Earthwork Plan and Sections

Figure 3. Site Grading Plan

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 6 of 8

EARTHWORK CALCULATION REPORT

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 7 of 8

EARTHWORK CALCULATION REPORT

2.6 Earthwork Volume Calculation


Earthwork modeling and calculation has been executed by Autodesk civil 3D, the following figure is present cut
and fill elevation bedding at plant areas. The cut and fill depth is refer to the earthwork elevation table below.

Figure 4. Earthwork Bedding Plan

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 8 of 8

EARTHWORK CALCULATION REPORT

Table 3. Earthwork Volume Calculation

2.7 Fill Soil Parameter Specification


 Backfill material that is deposited near the working place for more than 12 hours shall be protected with
polyethylene sheet so as not to damage the material.
 Each layer of backfill material, if dry, shall be wetted uniformly to the moisture content required to obtain
the specified density.
 Structural backfilling shall contain no muck, roots, sod or other deleterious material The material shall be
free of debris, organic material, rocks over 150mm in maximum dimension and excessive moisture or
dryness and meet the following gradation requirements:
Table 4. Backfilling Sieve Size Requirement
% by Weight Passing
Sieve Size
Square Mesh Sieves
102 mm (4 inch) 100
No.40 (0.425 mm) 0-60
No.200 (0.075 mm) 0-15

 Plasticity index (PI) ≤ 6


 Material shall be free of debris and low durability
 Material shall be have a resistance of magnesium sulfat < 30% after 4 cycles and sodium sulfat < 15%
after 5 cycles.

This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium