Jay 0 Ocb CV Cal 002 - Rev01.a
Jay 0 Ocb CV Cal 002 - Rev01.a
-
No : 011. /TRANS/PV-JAY/BAC/OZJ18 Dated : llf F~blvQ!) 2018 Received date :1'1 February 2018
No : MOM15022018 Dated : 15 February 2018
CCROUT DATE
REVIEW FOR APPROVAL DRAWINGS I DOCUMENTS
DRM3 15 Feb 2018
I 0 INFORMATION D RECORD
I
s WORKING DOCUMENT
T
APPROVED DOES NOT RELIEVE CONTRACTOR FROM R
RESPONSIBILITY FOR ERROR OR DEVIATIONS FROM I
CONTRACT REQUIREMENTS 8
u
T
BY
~ I DATE \~\'l- \~
1 I
0
DATE: \Vuz-1t..o r & N
LOG
OUT COMM NO: 012--HJ
NO STATUS DATE REVISION AND RECORD OF ISSUE DRN DES CHK POE APP
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
AECOM’s JOB NO: Rev.
JKTD17055
0
EARTHWORK CALCULATION DOC. NO.
REPORT JAY-O-OCB-CV-CAL-002
Date: By: CHKD: APVD:
INTERNAL DISTRIBUTION
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
EARTHWORK CALCULATION REPORT
Table of Contents
1.0 General 1
1.1 Introduction 1
1.2 Scope 1
1.3 Language 1
1.4 Units of Measurement 1
1.5 Codes and Standards 1
1.6 Abbreviations 1
2.0 EARTHWORK DESIGN 2
2.1 Site Location 2
2.2 Topographic Map 2
2.3 Earthwork Scheme 3
2.4 Shrinkage and Swelling Factor 3
2.5 Earthwork Plan and Sections 5
2.6 Earthwork Volume Calculation 7
2.7 Fill Soil Parameter Specification 8
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
i
EARTHWORK CALCULATION REPORT
List of Tables
Table 1. List of Abbreviations 1
Table 2. Shrinkage and swelling factors (Burch 1997). 4
Table 3. Earthwork Volume Calculation 8
Table 4. Backfilling Sieve Size Requirement 8
List of Figures
Figure 1 Topographic Map– Jayapura 2
Figure 2. Location– Jayapura 3
Figure 3. Site Grading Plan 5
Figure 4. Earthwork Bedding Plan 7
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the material
described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which it has been
provided, except as expressly permitted by the Consortium
ii
Page 1 of 8
1.0 General
1.1 Introduction
PT Perusahaan Listrik Negara (Persero is developing a cluster of small and medium sized electric generation
power plants (the Facility). Spread over six regions of the Indonesian archipelago The Facility), with their
locations and corresponding capacities.
1.2 Scope
The scope of this document is to design the Bau-Bau PLTMG site civil work not including the initial/ existing
areas, there is consist of earthwork scheme, road pavement design, storm water/drainage, fencing. The
purpose of this report is to provide engineering back up calculation.
1.3 Language
All drawings, calculations and documents shall be written in English.
1.6 Abbreviations
Table 1. List of Abbreviations
Term Abbreviations
EARTHWORK
EL Existing Level
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 2 of 8
Initial/Existing Area
Pond
Existing Trench
Based on topographic maps, the initial terrains were laid off at various levels, there are range of 2 to
3.5 MASL. Majorly the central and south areas are surrounded by lowest terrain into face off the
coastal area. The pond’s bottom level is about -2 MASL, there was a natural pond which
intentionally excavate for personal consumable based on site information. The existing trench is
around from north until south sides, those areas are could not be hampered during construction.
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 3 of 8
±250 m
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 4 of 8
It is important to note that shrink and swell in this research refers to this volume change in soils
during construction. This volume change is due to the shifting of soil particles when a soil is
unearthed, moved, and/or compacted. This is not referring to shrink/swell clays which
have a high plasticity index. The volume of shrink/swell clays alters when there is a change in water
content in the soil, and therefore varies insitu. The topic of discussion in this research, therefore, is
the shrinking and swelling of soils in the excavation and placement processes during construction,
not shrink/swell clays.
It is also important to note the use of different shrink and swell terms in this report. Shrinkage and
swelling factors are the factors applied to earthwork calculations. The factors are used as
conversions between different soil volumetric states. On the other hand, shrink and swell values
refer to the potential of a soil to shrink and swell in volume. This potential is usually in the form of a
percentage which can then be converted to a factor for use in earthwork calculations.
Table 2. Shrinkage and swelling factors (Burch 1997).
Based on the table above, swell factor has been determined 1.13 and 1.00 for shrinkage factor.
swell factor will input to determine a fill volume and shrinkage for cut volume.
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 5 of 8
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 6 of 8
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 7 of 8
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium
Page 8 of 8
This drawing/document is the proprietary information of the EPC Consortium for the project named above. This drawing/document or the
material described thereon may not be copied or disclosed in any form or medium to third parties, or used for any purpose other than for which
it has been provided, except as expressly permitted by the Consortium