You are on page 1of 12

How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

tensix.com

TheP6Pro
5-6 minutes

In most organizations only a few folks are familiar with Primavera


P6. Typically, the vast majority of project team members are, for the
most part, Primavera P6 illiterate. How then can you efficiently
retrieve and include schedule updates from team members less
familiar with the particulars of Primavera P6?

Assuming you are not using such tools as Primavera Team


Member, it is always possible to resort to manual data entry when
including status inputs from team members unfamiliar with
Primavera P6. This, however, may quickly become laborious when
updating the status of large projects. And there is a more efficient
way to retrieve and include team member status updates.

It is possible to export the schedule to Microsoft Excel where team


members can input their schedule updates. The updated
spreadsheet may then be imported back into Primavera P6
Professional, where the scheduler continues the schedule update
process.

This article looks at the Primavera P6 Professional XLS export and


import process, and how to use Microsoft Excel as the medium for
retrieving and including team member schedule updates.

1 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

We begin with our demonstration project, Figure 1.

Figure 1

This schedule is a pipe repair and improvement project. We want to


retrieve and include schedule updates from team members familiar
with the project, but not Primavera P6. This can be done by using
Microsoft Excel as the medium between team members and the
Primavera P6 schedule.

Let’s proceed and export the pipe repair and improvement


schedule. Select File | Export, Figure 2.

2 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Figure 2

Choose to export to an XLS spreadsheet, Figure 3.

Figure 3

In Figure 4, elect to export activities, activity relationships,


resources, and resource assignments.

3 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Figure 4

In the projects to export dialog toggle on export for the pipe repair &
improve project, Figure 5.

Figure 5

After selecting export, click next, Figure 6.

4 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Figure 6

In the select template dialog, we choose the standard template and


click modify, Figure 7.

Figure 7

In the activities subject area select the columns tab and include all
the options listed in Figure 8.

5 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Figure 8

Click OK. Click next, Figure 9.

Figure 9

6 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Choose an appropriate file name and file location, Figure 10.

Figure 10

Click next.

We have our project XLS spreadsheet in Figure 11.

Figure 11

Your team member only has to update the columns we have


marked in yellow above. The activity status column options are: Not
Started, In Progress, or Completed. Have your team member input
the activity status along with the actual start and actual finish of

7 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

each activity. Make sure your team member also uses the same
format as the start and finish columns.

Note that the percent complete type for this schedule is duration %
complete. Primavera P6 Professional does not read columns with
an “(*)” in their column heading, so it is not enough to specify the
duration % complete. Your team member must also enter the
remaining duration in its respective column.

You will also observe that the project management activity


(W1020), has been marked by us in green. No updates are
required to this activity, as P6 automatically progresses this level of
effort type activity when the schedule is recalculated.

Our updated schedule Excel spreadsheet is in Figure 12.

Figure 12

Note, in particular, the duration % complete and remaining duration


of the ‘Insulate Piping’ activity (W1080). Looks good! We are ready
to import our team member project updates. In Figure 13 we begin
the XLS spreadsheet import process.

8 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Figure 13

In Figure 14 we elect to import activities, activity relationships,


resources, and resource assignments. Click next.

Figure 14

We want to import the XLS file to the same XER file we exported

9 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

from. So select the same import to XER file, Figure 15.

Figure 15

Click finish. Our schedule activity status is per Figure 16.

Figure 16

To complete the update process we need to move the data date


forward and recalculate the schedule. We move the data date
forward in Figure 17.

10 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Figure 17

After recalculating the schedule the final updates to the pipe repair
and improve project schedule are displayed in Figure 18.

Figure 18

Summary

11 of 12 1/31/2018, 7:41 PM
How To Export & Import Primavera P6 Schedule Status Using Excel about:reader?url=https://tensix.com/2018/01/how-to-export-import-prim...

Primavera P6 Professional includes Microsoft Excel XLS export


and import capabilities. Though it may require effort, investigate the
process of exporting and importing Primavera P6 schedules directly
to and from Microsoft Excel. Because of its wide spread adoption, a
Microsoft Excel spreadsheet works well as the medium for
retrieving and including team member updates in the Primavera P6
Professional schedule. Thus, the project manager can leverage
Microsoft Excel’s almost universal acceptance and usage to
consolidate schedule updates from folks less than proficient with
Primavera P6.

12 of 12 1/31/2018, 7:41 PM

You might also like