Professional Documents
Culture Documents
of Airfield Pavements
Presented at
SWIFT Conference
September 13, 2010
By
Tim Smith
Cement Association of Canada
2
Overview
¾ Background discussion on Life Cycle Cost Analysis (LCCA)
¾ LCCA example – Pensacola airport
¾ AirCost LCCA Tool
¾ Overview of concrete pavements sustainable benefits
¾ Life Cycle Assessment (LCA) definition
¾ LCA components
Life Cycle Cost Analysis (LCCA)
¾ Economic procedure used to compare competing design
alternatives
¾ Considers all significant cost and benefits
¾ Expressed in equivalent dollars
¾ Not an engineering tool that determines how long an
alternative will last or how well it will perform
Chief Considerations for LCCA Pavement Selection
¾ Use of comparable design sections
¾ Airport Authority / Agency costs
¾ Selection of accurate rehabilitation activities
¾ Bringing cost back to Present Worth values
¾ Discount rate (time value of money)
¾ Length of analysis period
¾ Salvage value
Agency Costs
¾ Initial bid price or estimate
¾ Maintenance costs (recent bid tabs)
¾ Rehabilitation costs
¾ Important to have good maintenance management system to
provide the most accurate data to give reliable LCCA results
¾ If no good data is available look for airports with similar traffic
levels and climatic / soil conditions
Present Worth Model
ni z
⎛ 1 ⎞
m
⎛ 1 ⎞
PW = C + ∑ Mi⎜ ⎟ − S⎜ ⎟
i =1 ⎝1+ r ⎠ ⎝1+ r ⎠
¾ PW = Present Worth ¾ r = discount rate
¾ C = Initial Construction Cost ¾ ni = number of years from
¾ m = number of maintenance the present of the ith activity
or rehab activities ¾ S = salvage value at the end
¾ Mi = Cost of the ith activity of the analysis period
¾ Z = length of the analysis
period
Discount Rate
¾ Accounts for the time value of money
¾ DR = (INT – IFL) / (1 + IFL)
¾ DR = discount rate
¾ INT = Nominal interest rate
¾ IFL = inflation rate
¾ Historically the difference between interest rates and inflation rate is
3.0%
Salvage Value
¾ Reflects any remaining worth of a pavement at the end of the
analysis period
¾ Two components:
¾ Remaining service life – value of the pavement as it is continued to be
used beyond the analysis period. Structural and functional aspects are
evaluated to determine the serviceability and usefulness of the
pavement surface
¾ Residual value – actual worth of the existing pavement at the end of
the service life in terms of the revenue that may be generated form
the sale or recycling of the existing pavement
¾ Recommended that salvage values be considered in in airport LCCA,
especially when shorter analysis periods (20 to 30 years) are used
FAA AC 150/5320-6E Appendix 1. Economic Analysis
¾ Design procedure document appendix
¾ Analysis method
¾ If resulting Present Worth costs between two alternatives is within 10
percent or less it is assumed the PW is same for the alternatives
¾ Step by step procedure
¾ Example problem comparing seven asphalt alternatives
¾ Costs of rehabilitation activities
¾ Present worth LCC
¾ Summary of alternatives
¾ Comparative ranking of alternatives
Pensacola - PNS Background
Background
¾ May 2005 let rehab project
¾ 12” P‐401
5” P‐154
12” Compacted Subgrade ¾ 3 Contractors
¾ Mandatory Pre‐bid ¾ 1 dropped out
¾ 2 joined forces
¾ Submitted single bid – $4
million over budget
Rejected the Single Bid
Engineer Revised Plans
¾ Added Concrete Option
¾ Design Criteria
¾ Boeing 757 – 5781 annual operations
¾ Used FAA AC 150/5320-6D
¾Equivalent Aircraft as design aircraft
¾ Used LEDFAA to Compare
¾Fleet mix – sums cumulative damage from each
aircraft
¾gives conservative concrete pavement design
Pavement Typical Sections
Asphalt Section
4” P-401 Surface
8” P-401 Base
5” P-154 Subbase
12” Compacted Subgrade
Concrete Section
17” P-501
Surface
Base Base
Sub-base Sub-grade
4” P-401 Surface
8” P-401 Base
5” P-154 Subbase
12” Compacted Subgrade
Concrete Section
17” P-501
¾ How do we compare unequal designs with unequal lives?
¾ Using LCCA process to evaluate the bids
¾ FAA Airport Improvement Program (AIP) Handbook, Chapter
9, Paragraph 910, Life Cycle Costs in Competitive Sealed Bids
can be used but does not explain how
¾ FAA AC 150/5320‐6D, Appendix 1, Economic Analysis is part
of the design procedure to see if should considered alternate
bids ‐ Example Problem
LCCA Development Bid Process
¾ Format Developed Based on FAA Model in FAA AC 150/5320‐
6D, Appendix 1, Economic Analysis
¾ Received Input from ACPA, AI and FAA
¾ General Parameters were:
¾ Design Life ‐ 20 Years (FAA Requirement based on grant period)
¾ Concrete Expected Life ‐ 40 Years
¾ Asphalt Expected Life ‐ 30 Years with mill and overlay at 15
years
¾ Discount Rate (Inflation Factor) ‐ 5%
¾ Maintenance Requirement for each alternative
Maintenance Requirements
¾ Concrete Runway Maintenance Activities
¾ Year 0 - Insertion of TOTAL BID PRICE of Concrete Bid
¾ Year 15 - Joint Seal Replacement (Maintenance)
¾ Year 19 - Crack Sealing (Maintenance)
¾ Year 20 - Estimated 5% Slab Replacement (Maintenance)
¾ Asphalt Runway Maintenance & Rehabilitation Activities
¾ Year 0 - Insertion of TOTAL BID PRICE of Asphalt Bid
¾ Year 6 - Pavement Preservation System (Maintenance)
¾ Year 13 - Pavement Preservation System (Maintenance)
¾ Year 15 – 3” Mill and Overlay (Rehabilitation)
¾ Information based on Florida APMS
Development of Salvage Value
¾ Concrete Runway LCCA
¾ Took Full Bid Price at Year 0 and Used Straight Line Depreciation
over 20 Year Design Period
¾ Total Cost / 40 Years x 20 Years (Remaining Life) x Present
Worth Factor at Year 20 = Salvage Value
¾ Asphalt Runway LCCA
¾ Took Full Bid Price at Year 0 and Used Straight Line Depreciation
over 20 Year Design Period PLUS Mill & Overlay at Year 15 over
5 Year Remaining Design Period
¾ Total Cost / 30 Years x 10 Years (Remaining Life) x Present
Worth Factor at Year 20 PLUS Mill & Overlay Cost / 15 Years x
10 Years (Remaining Life) x Present Worth Factor at Year 20 =
Salvage Value
¾ Submitted Electronic Spreadsheets to All Bidders, Plan
Holders & Plan Rooms
Bids Received
Note: Salvage value is based on straight-line depreciation of the expected life of the last rehabilitation item.
Excel Spreadsheet – AC Option
Runway 17-35 Reconstruction
Pensacola Regional Airport
Life Cycle Cost Analysis Evaluation - APAC - Southeast, Inc.
Low Bid Asphaltic Concrete Runway
• Difference ‐ $267,091
LCCA Summary
¾ Make Sure All Maintenance Activities & Rehabilitation Costs are
Current, Based on Recent Bids
¾ Establish reasonable salvage value for each alternative
¾ Level “playing field” brings competition and value
¾ FAA Recognized the need for guidance
AirCost LCCA Tool
¾ Developed by ARA under contract with the Airfield Asphalt
Pavement Technology program (AAPTP)
¾ Not officially released yet
¾ May become FAA standard
¾ Components:
¾ Pay items and cost library which can be added to
¾ Project details
¾ Airport details
¾ LCCA parameters
¾ Summary of Alternative
Concrete Pavement
Green Benefits
Beyond Longevity Lower Energy Footprint
Light Reflectance
And Urban Heat Island Effect
¾ Durability and longevity of concrete (i.e., concrete’s 35+ year
design life)
¾ Lower life cycle cost due to reduced maintenance activities and
costs
¾ Cement is made locally, bitumen is imported
Concrete Pavement – Environmental Benefits
¾ Uses less energy to build & maintain
¾ Once set, concrete is inert
¾ Makes use of industrial by‐products
¾ Reduces urban heat island effect
¾ Potential CO2 sink
Use of Industrial by-products
¾ Types of Supplementary Cementing Materials:
¾ Fly ash
¾ Blast furnace slag
¾ Silica fume
¾ Benefits
¾ Decreases material going to landfill sites
¾ Improves concrete pavement strength and durability (must use
appropriate levels of SCMs)
¾ May improve concrete pavement workability
¾ Decreases amount of CO2 associated with PCCP
¾ Study completed on Use of SCMs in PCCP
Urban Heat Island Reduction
Pavement Type Albedo (solar reflectance)
Asphalt 0.05‐0.10 (new)
0.10‐0.15 (weathered)
Gray Portland Cement 0.35‐0.40 (new)
Concrete 0.20‐0.30 (weathered) Source: ACPA R&T
Update Concrete
White Portland 0.70‐0.80 (new) Pavement Research
Cement Concrete 0.40‐0.60 (weathered) & Technology June
2002
NASA Infrared Imagery Atlanta Airport May 1997
NASA
Infrared
Imagery
May 1997
Concrete
Concrete
Parking
Parking
Deck
Deck Concourses
Concourses
I-85
Terminal
Asphalt
Asphalt
Parking
Parking
Lots
Lots Concrete
Concrete
Parking
Parking
Deck
Deck
Asphalt
Asphalt
Parking
Parking Concrete
Concrete Runways
Runways
Lots
Lots
Atlanta
Airport
35
Life Cycle Assessment
¾ Wikipedia definition:
¾ Focus comments on energy use and CO2 footprints
Reduced Energy Consumption
¾ Athena Sustainable Materials Institute Update Study
¾ A Life Cycle Perspective on Concrete and Asphalt Roadways:
Embodied Primary Energy and Global Warming Potential:
¾ ACP uses more embodied primary energy than PCCP over a 50 year
Life Cycle Assessment
¾ Increased energy use ranges from 2.3 to 5.3 times more
¾ Increased energy use ranges from 31 to 81 % more if exclude
feedstock energy
Definitions:
Embodied primary energy = primary energy + feedstock energy
Primary denotes fossil fuel
Feedstock energy = liquid bitumen
Reduced Energy Consumption
Additional Embodied Primary Energy Used by
Asphalt Pavement Design Alternatives
Additional Embodied Primary Energy
Used by Asphalt Pavement Design Alternatives
Highway Classification Including feedstock Excluding feedstock energy
energy
Canadian Arterial Highway
Reference: A Life Cycle Perspective on Concrete and Asphalt Roadways: Embodied Primary
Energy and Global Warming Potential ,Athena Institute, September 2006
Canadian High Volume Freeways
800
T 600
o
n
400
n
e
s 200
0
AC CBR 3 PC CBR 3 AC CBR 8 PC CBR 8
Road Type
Portland cement (PC) Asphalt (AC)
Cement Sector GHG Emissions
• The Cement industry accounted for 12.4 MT of greenhouse gas
emissions in 2007:
43
Renewable and Alternative Fuels
More could be done in Canada
4
4
Supplementary Cementing Materials - SCM’s –
fly ash, slag and silica fume
¾ SCMs improves the properties of hardened concrete.
¾ Improve the performance of the concrete and reduce the
clinker demand of the mixture.
¾ Mitigates the effect of alkali silica reactivity (ASR) in concrete.
¾ The use of SCMs in concrete mix designs is recognised by
the LEED building rating system as an effective measure in
mitigating CO2 emissions and is awarded points towards
LEED certification.
Importance of SCMs Grows
¾ The important clinker / cement factor continues to improve via:
¾ 53% increase in the use of additions to blended cements, since 1990
¾ 120% increase in direct sales of cement substitutes, since 1990
4
6
Cement GHG Intensity has Improved..
¾ A 6.6% improvement in GHG intensity per tonne of cementitious product ,
since 1990:
4
7
New Portland Limestone Cement (PLC)
to Reduce Energy and CO2 Footprint
¾ First appeared in Germany in 1965
¾ 1979 First Appeared in French Standards
¾ 1983 5% Limestone permitted in CSA A5
¾ Used in Europe for 25 Years at over 20%
¾ Adopted in CSA A3000‐08 at levels up to 15%
¾ Must be adopted in Building Codes before it can be used
New Portland Limestone Cement (PLC)
¾ Portland‐limestone Cement (PLC) can be produced by intergrinding
or blending limestone with Portland cement.
¾ Key advantages with respect to GHG emissions and climate change. 4
9
¾ Less energy is expended in grinding limestone than clinker.
¾ Less clinker demand
¾ Lower CO2 emissions
¾ Equivalent performance to traditional cements
Portland Limestone Cement (PLC) Energy Savings
¾ Two lift concrete pavement
¾ NOx eating cement
¾ Ternary / quartnary blended cements
Do Not Expose yourself
look at all your options!
Thank you !!
Questions
?