Professional Documents
Culture Documents
Life Cycle
Cost Analysis:
A Guide for Comparing
Alternate Pavement Designs
Time Present
Worth
%
American
Concrete
Pavement
Association
Engineering Bulletin
N CONC
CA
RI American Concrete Pavement Association
RE
E
★ AM
TE
ON
M
E
AT
EN I
T ASSOC
ABSTRACT: This engineering bulletin presents the concepts of Life Cycle Cost Analysis (LCCA) for the purpose of
comparing equivalent competing pavement design alternatives on an economic basis. All of the factors that should be
considered in an economic analysis are explained, and guidance is given on the selection of values for LCCA-
sensitive factors. Examples of three different analyses are given: highway, county road, and city street. Advanced
LCCA techniques are discussed, including the impacts of pavement type selection on a roadway network. Finally, life
cycle cost and pavement performance studies are summarized, showing the benefits of concrete’s low life cycle cost
and other economic benefits.
This publication is intended SOLELY for use by PROFESSIONAL PERSONNEL who are competent to evaluate the
significance and limitations of the information provided herein, and who will accept total responsibility for the
application of this information. The American Concrete Pavement Association DISCLAIMS any and all
RESPONSIBILITY and LIABILITY for the accuracy of and the application of the information contained in this
publication to the full extent permitted by law.
Chapter 1 Introduction 1
➣ Types of Economic Analyses 1
➣ Present Worth & Equivalent Uniform Annual Cost 1
➣ Performing a LCCA 2
Chapter 3 Examples 19
➣ Case 1 – Existing Interstate Pavement 19
➣ Case 2 – Rural County Pavement 20
➣ Case 3 – City Street Reconstruction 20
Engineering Bulletin
Table of Contents
Page
Chapter 6 Summary 29
References 30
Appendices 35
Chapter 1
Introduction
Life cycle cost analysis (LCCA) is an economic proce- Present Worth and Equivalent
dure used to compare competing design alternates, over
the lives of each alternate, considering all significant
Uniform Annual Cost
costs and benefits, expressed in equivalent dollars.(1) It The results of a LCCA can be presented in several ways.
is important to understand that LCCA is an economic The two most common are Present Worth (PW) and
tool that determines which alternate has the best value Equivalent Uniform Annual Cost (EUAC). Present Worth
and not an engineering tool that determines how long is the sum of all costs (and benefits) over the project life
an alternate will last or how well it will perform. in today's dollars (Figure 1). It combines initial costs
This does not mean that engineering is not an with discounted future maintenance costs, rehabilitation
important element of the life cycle cost analysis. Proper costs, and a salvage value. The future costs are dis-
engineering must be used to ensure that each rival counted to account for the time value of money using
alternate meets the design criteria and provides similar the discount (real interest) rate. Present worth analysis is
results. If the alternates do not provide similar perfor- limited to comparing alternates with equal analysis
mance, then an economic assessment using LCCA to periods. Equation 1 calculates the present worth.
compare them is not realistic or reliable. PW = IC + Σ[pwf (MC) + (UC) + (FRC)] - pwf(S)
(Eq. 1)
Types of Economic Analyses Where:
Life cycle cost analysis can be broken down into IC = Initial Cost
primary and secondary analysis.(1) Primary analysis MC = Maintenance Cost
determines if a certain set of actions should be done. UC = User Cost
For example, a primary analysis determines if a roadway, FRC = Future Rehabilitation Cost
a transit system, or neither should be built. Primary S = Salvage Value
analysis essentially determines if any improvements
need to be done at all. Therefore, in primary analysis, Initial Cost
a “do nothing” scenario is a viable alternate that should Periodic Rehabilitation Cost Yearly
Costs
Maintenance
be analyzed. Cost
Secondary analysis compares the alternates that
satisfy the primary analysis. It is the comparison that YEAR Salvage
shows which alternate provides the best value. Life cycle Value
cost analysis for pavement type selection (concrete or
Present Worth
Costs
Page 1
Engineering Bulletin
Maintenance
of strategies. A cash flow diagram shows the inflow and
Cost
outflow of cash due to construction and rehabilitation.
YEAR
Up arrows indicate major cash expenditures (con-
Salvage
struction, rehabilitation, etc.) and down arrows show
Value
cash inflows. With pavements, the only inflow of cash
Equivalent Uniform Annual Cost
Costs
* This is true for public highways. For toll roads, where user fees are being
collected, there is a continuous inflow, which should be taken into account in
the development of the expenditure streams. Likewise, a toll agency must take
into account lost revenues during rehabilitation activities (due to traffic dis-
Page 2 ruption or reduced level of service) when developing the expenditure streams.
Engineering Bulletin
Chapter 2
Basic Factors
The factors affecting the results of a LCCA for pavement land development, legal fees, etc. are incurred no matter
type selection are: which pavement alternate is selected. Therefore, these
• Agency costs (including engineering costs) costs do not affect the comparison results.
• User costs
• Discount rate Initial Cost
• Selection of rehabilitation activities Initial costs may be divided into pavement and non-
• Use of comparable sections pavement costs associated with the original development
• Length of the analysis period of the project. Pavement costs include subgrade prep-
aration; base, subbase, and surface materials; labor;
Agency costs should include engineering costs, which
equipment; drainage, etc. The non-pavement costs are
are often 15-20% of a project, especially on municipal
costs that affect the overall cost of the project, but are
projects. More frequent asphalt overlays often require
not necessarily part of the pavement structure. These
the use of a consultant, thereby driving up the agency’s
include extra fill or cut due to different grade elevations
cost. These engineering costs should also be included.
between the pavement types, traffic control, median &
Other considerations, such as smoothness over time,
fill slopes, utilities, guardrail and sign adjustments,
safety, and environmental friendliness, may enter the
lighting requirements, overhead structures and at-grade
pavement selection decision, but can be difficult to
structures, culvert extensions etc. Unless a non-
relate to cost or performance. When possible, it is
pavement cost item varies between alternates, it can be
preferable to use engineering adjustments on the
disregarded, as it will have no impact on the outcome.
alternates to account for these considerations before
performing the LCCA. After the adjustments are made, Effect of Initial Costs
LCCA will allow a fair comparison between the Initial costs drive the agency portion of a LCCA.
alternates.(1) Depending upon the pavement type and rehabilitation
activities chosen, as well as consideration of other non-
Agency Costs agency costs, initial costs can account for 50 to 90% of
Agency costs are all direct costs incurred by the agency the present worth or EUAC. For concrete pavements, a
over the lifetime of the project. These include: large portion of the initial cost is associated with the
design features chosen for the pavement (i.e. shoulders,
• Initial costs
subbase, etc). Therefore, it is important that the de-
• Operation and maintenance costs (including staffing)
signer choose pavement features that give the desired
• Rehabilitation costs (including engineering and traffic
performance without needlessly increasing the cost of
control for each rehabilitation)
the pavement.
• Salvage value.
In many cases, designers add features to concrete
When looking at agency costs, it is only necessary to pavements, but do not recognize the performance
include costs that are specific to the individual alternates benefit of the feature. Other times, expensive features
and set them apart. Common costs, such as public hear- are added that are unnecessary to satisfy the design
ing and informational meetings, permits, real estate and
Page 3
Engineering Bulletin
requirements. In either case, the results of the LCCA are To determine the relative costs, concrete paving
flawed because the benefits of the added design features contractors across the US were surveyed and given a
are not matched with the anticipated performance. “reference section,” which was assigned a relative cost of
While there are numerous research studies on how 100 (Figure 3). Next, a specific pavement feature was
pavement features affect performance, only one study(3) changed, and the contractors determined the relative
has looked into how pavement features affect initial cost of the modified section. In this study, the following
costs. The study was made in terms of relative costs, not design features were evaluated:
in actual costs or specific dollar values. • Slab thickness
There are three advantages of using relative costs over • Subbase Type
the actual costs. First, they allow costs to be compared • Shoulders
across the United States, regardless of labor and material • Transverse joint design (spacing and load transfer)
costs, contractor equipment and capabilities, project • Transverse joint sealant
size, etc. Second, relative costs allow general compari-
Figures 4 – 8 show the relative cost impacts of these
sons of one feature to another to be made easily, which
various design features on the “reference section.” All
helps in identifying their cost-effectiveness. Finally,
costs are presented in terms of total pavement costs. As
relative costs diminish the effect of interest and inflation
can be seen, some features, such as open-graded drain-
rate fluctuation, allowing the designer to use the same
able subbases dramatically add cost to concrete pave-
information year after year.
ments. If these features do not enhance performance
significantly, then they are not cost effective.
1.2 m 3.6 m (12 ft) 3.6 m (12 ft) 3.0 m (10 ft)
(4 ft)
Prepared Subgrade
Page 4
Engineering Bulletin
81 111
112
91
124
114
132
84
97 108
114
112
122
123 134
124
70 80 90 100 110 120 130 140 90 100 110 120 130 140
Average Relative Cost Average Relative Cost
None Lean Concrete 38 mm (1.5 in.) Dowels, 6.1 mm (20 ft.) Jt. Spacing
38 mm (1.5 in.) Dowels, 4.6 mm (15 in.) Jt. Spacing
Lime-Treated Soil Asphalt-Treated OGB
CRC – #6 bars at 200 mm (8 in.) Spacing
Unstabilized OGB Cement-Treated OGB
Reference Section: 150 mm (6 in.) thick dense-graded Reference Section: 250 mm (10 in.) thick undoweled
subbase. Cost = 100 6.1 m (20 ft.) joint spacing. Cost = 100
Figure 5. Effects of Subbase Type. Figure 7. Effects of Joint Design (spacing and load transfer).
Page 5
Engineering Bulletin
Olmsted Asphalt
curves for the two
$16,000
Olmsted Concrete counties do not match.
$14,000 This is because each
county has different
$12,000
maintenance practices
$10,000 and activities, and these
$8,000
different practices will
produce different
$6,000 results. This will hold
$4,000
true for all agencies and
as such, one agency’s
$2,000 maintenance curves
$0 cannot necessarily be
0 5 10 15 20 25 30 substituted for
Years since Last Major Rehabilitation another’s. Finally, it is
Figure 9. Concrete and Asphalt Maintenance Costs for Two Minnesota Counties. important to note that
Page 6
Engineering Bulletin
the two counties’ concrete and asphalt curves remain not possible. Finally, as the underlying structure is
relatively constant. That is, the asphalt curve is from 2.5 deteriorating, the pavement is losing its structural
to 19 times higher than the concrete’s curve.(4) capacity. Therefore, it is unlikely that the second and
The current Federal highway Administration (FHWA) third rehabilitation activities will last as long as the first
position is to exclude maintenance and operation costs one for any alternate.
in a LCCA.(2) Their reasoning is that the difference in Two other important costs, often overlooked when
maintenance and operation costs are very small in com- determining the rehabilitation costs, are traffic control
parison to initial construction and rehabilitation costs and engineering. Because every pavement deteriorates
for the typical alternates analyzed. As such, the FHWA differently, each rehabilitation is unique and therefore
suggests that their impact on LCCA results is very needs to be engineered. Likewise, because traffic is
minor. For large projects, where initial construction and increasing, future rehabilitation may require more
rehabilitation costs are in the millions of dollars, this complicated traffic control.
may be true. However, for smaller projects (rural and Selection of Rehabilitation Activities
municipal roadways) with lower initial cost, this is likely The rehabilitation activity selection should be based on
not to be true. Maintenance costs can be influential on the type, severity, and extent of distress in the pavement
small agencies/projects. Furthermore, large maintenance because as a pavement deteriorates, the appropriate type
costs can drain off funding for new future projects. of rehabilitation changes. For concrete pavement, the
first rehabilitation activities should be some form of
Rehabilitation Costs Concrete Pavement Restoration (CPR).*
Rehabilitation costs are larger future periodic costs CPR is used early in the life of a pavement when it is
associated with keeping the project in a usable con- in reasonably good condition with only slight deterior-
dition.(1) Rehabilitation raises the condition of the ation. It consists of 8 different techniques that repair
facility and increases its level of service. In an ideal isolated sections of deteriorated pavement, or prevent or
LCCA, the rehabilitation activities and their timing slow overall deterioration, as well as to reduce the
would be based on the predicted distress that will impact loadings on the pavement. The eight CPR
develop in the pavement. That is, in the design phase, techniques are:
the engineer would calculate the rate of distress 1. Full-depth repair
development in the pavement, determine the year in 2. Partial-depth repair
which the critical distress level is reached, then apply 3. Diamond grinding
the appropriate rehabilitation activity for that distress. 4. Joint & crack resealing
Unfortunately, this level of sophistication is not available 5. Slab stabilization
to most pavement design engineers. 6. Retrofitting dowels
For this reason, the stream of rehabilitation activities 7. Retrofitting concrete shoulders
used in LCCA varies greatly from agency to agency and 8. Cross-stitching longitudinal cracks/joints
most apply a standard scheme to all pavements
(Appendix 2). However, a standardized scheme is not The choice of which CPR activity to implement
realistic for three reasons. First, standard rehabilitations depends upon which distresses are present in the pave-
rarely address the cause of the problem and therefore, it ment. For CPR to be most effective, proper engineering
is unlikely that same standard rehabilitation is appro- and timing are critical. For more information on CPR
priate for all pavement types, at all times. see references 8 – 14.
Second, because traffic is always increasing, it is not Resurfacing, or overlaying, is the second category of
possible for the same standard rehabilitation to last the rehabilitation. Resurfacing is used when a pavement has
same length each time it is applied. If it did, it would medium to high levels of distress and CPR can no longer
mean that each subsequent rehabilitation activity would be cost-effective. Concrete overlays fall into two basic
carry more traffic than the previous activity, and this is categories: concrete overlays for concrete pavements and
* CPR can be used more than once on the same pavement. The state of Georgia has used
CPR extensively for more than 20 years and has used it as many as three times on the
same road. They have found CPR techniques to be one-fourth to one-third the cost of a
150 mm (6 in.) asphalt overlay. CPR projects in Georgia typically last between seven and
10 years, and some have performed for more than 17 years before a second CPR.(6,7) Page 7
Engineering Bulletin
concrete overlays for asphalt pavements. Within each of and secondary roads, intersections, etc. as well as major
these categories there are two overlay types. airport and general aviation runways, taxiways, and
For concrete overlays on concrete, there are “Bonded apron areas.
Concrete Overlays” and “Unbonded Concrete Overlays.” The main advantage of a conventional whitetopping
Bonded concrete overlays consist of a thin concrete layer is that it requires a minimal amount of pre-overlay
(100 mm [4.0 in.] or less) bonded to the top of an repair before the overlay is placed. Furthermore, the
existing concrete pavement to increase its structural concrete slabs will bridge problems that the asphalt
capacity. Good candidates for bonded overlays are cannot. The existing asphalt surface becomes an ex-
pavements that have little deterioration, but are too thin cellent base course for the whitetopping, with reduced
for increasing traffic volumes. For example, an existing potential for pumping, faulting, and loss of support
pavement is 150 mm (6.0 in.) thick, but new traffic vol- underneath the concrete. Finally, because the con-
umes indicate that it should be 230 mm (9.0 in) thick. struction contractor can maintain traffic on the existing
Bonded concrete overlays are not recommended surface during paving, many reconstruction problems,
when the existing slab is deteriorated or has a significant such as rain delays, are avoided.
amount of durability problems (e.g., “D” cracking or An ultra-thin whitetopping overlay (UTW) is a con-
reactive aggregates). For more information on bonded crete overlay, normally 50 mm to 100 mm (2 to 4 in.)
concrete overlays, see reference 15. thick, placed on top of the existing asphalt pavement.
An unbonded concrete overlay consists of a thicker In addition to the thinness of the concrete, two other
concrete layer (125 mm [5 in.] or greater) on top of an factors differentiate UTW from normal whitetopping.
existing concrete pavement. The major advantage of an These are:
unbonded overlay is that it can be applied to a 1. Bonding between the concrete overlay and the
deteriorated pavement and require very little, if any existing asphalt pavement
preoverlay repair. Unbonded overlays use a thin asphalt 2. Joint spacings that are much shorter than normal
“separation interlayer” between the new and existing (i.e. 0.9 to 1.8 m [3 to 6 ft.]).
concrete so that concrete layers act independently of
each other. This separation interlayer also acts as a The bonding of the concrete overlay to the asphalt
cushioning layer and prevents distresses from the pavement creates a composite pavement in which the
underlying pavement reflecting into the overlay. load is shared between the concrete and existing
Unbonded overlays are most cost effective when the asphalt. The close joint spacing allows the slabs to
existing concrete pavement is badly deteriorated. Because deflect instead of bend. Together, these effects reduce
the two concrete layers are independent, unbonded slab stresses to reasonable values.
overlays react structurally as if built on a strong, non- UTW is a good application for normal traffic loads on
erodable base course. This advantage makes unbonded residential streets and low-volume roads. Other applica-
overlays a much better option for deteriorated concrete tions include intersections, ramps, bus pads, etc. (where
pavements than rubblization with an asphalt overlay. For rutting and washboarding is a problem), general aviation
more information on unbonded concrete overlays, see pavements, and parking areas. However, in order to
reference 16. form the composite action needed, UTW’s must be
Concrete overlays of asphalt pavements consist of placed at locations where at least 75 mm (3.0 in.) of
“Conventional Whitetopping Overlays” and “Ultra-Thin asphalt exists. For more information on conventional
Whitetopping Overlays” (UTW). Conventional white- and ultra-thin whitetoppings, see reference 17.
topping is a thick concrete layer (100 mm [4.0 in.] or Reconstruction is the most invasive rehabilitation
greater) on top of an existing asphalt pavement. They option. It is used when the pavement has high levels of
are applicable in almost all situations and have been distress and overlays are no longer effective.* Recon-
successfully used on interstate highways, state primary struction can involve either the complete removal and
replacement of the existing pavement or partial removal programmed in year 32, but actually done in 31, the
and replacement. Partial removal and replacement is increase in present worth is only $11,650. This is over
called an inlay. For more information on inlays, see 40% less than when the rehabilitation occurred in the
reference 18. analysis period.
Reconstruction is usually necessary to correct items Accurate assessment of service life for alternate
such as subgrade and subbase deficiencies, roadway pavement sections and rehabilitation activities is
geometrics, roadside safety features, drainage, etc. Other necessary if the results of the LCCA are to be credible.
advantages with reconstruction are that it controls the Typically, the service life for a concrete pavement is cited
final elevation and minimizes roadside appurtenance at about 20 to 30 years. However, many concrete
adjustments. Furthermore, it gives the agency and pavements, originally designed for 20 years, have lasted
contractor the option to recycle the old pavement either longer and carried significantly more traffic than for
as an aggregate for the subbase or the new concrete. which they were designed. A recent study found that
Figure 10 shows this concept of where each rehabili- the concrete pavements on Illinois’ interstates carried
tation activity is done in the life of the pavement. almost 4 times more traffic than they were intended for,
and lasted an average of 23 years.(19) A similar study in
Restoration New York state found that their concrete pavements
Structural/Functional Condition
Resurfacing
lasted 29 years and carried 3.4 times more traffic than
for which they were designed.(20) Table 1 shows some
Reconstruction comparisons between asphalt and concrete
pavements.(21)
Page 9
Engineering Bulletin
Page 10
Engineering Bulletin
Page 11
Engineering Bulletin
Page 12
Engineering Bulletin
* The analysis only looked at time to complete the paving portion of the project. No attempt was made to
look at grading, shouldering, drainage work, or final clean-up, in an effort to isolate comparisons to pave-
ment type only. Furthermore, the time taken for non-paving construction events can be diminished through
pre-design work and value engineering. It should be noted that future comparisons including these other
events could likely show concrete paving to be an even faster process than reported in the study.
Page 13
Engineering Bulletin
was still 258% faster than the highest average produc- 20.0
tion for asphalt.(33) Long-term
16.0
Applying the above to a hypothetical five miles of US Government
divided highway paving demonstrates the time and cost 12.0 Securities
(Interest Rate)
associated with completing the project with either con-
8.0
crete or asphalt. By choosing concrete, the public might
see the paving completed in less than 20 working days as 4.0
opposed to over 60 for asphalt. The user cost for asphalt
would be over $1.62 million, versus less than $540,000 0.0
Produces Price Index
on average for concrete pavement construction. (Inflation Rate)
-4.0
Public expectations have increased the importance of 1945 1955 1965 1975 1985 1995 2005
reducing interruptions in the service provided by our Year
transportation infrastructure. Concrete pavements can Figure 13. Long-term interest and inflation rates.
have a very beneficial impact on reducing the amount
of time a facility may be out of service, because they
require less frequent maintenance, have longer service Second, the discount rate takes into account the
lives, and are often quicker to build. competing forces of interest and inflation. This allows
the person performing the analysis to use constant, or
Discount Rate today’s, dollars in an analysis.
The discount rate accounts for the time value of money. When using the discount rate, the analyst must
$100 today is not worth $100 one year from now due realize the results are artificial values on the total costs
to inflation.* The discount rate takes into account the of ownership. That is, the results are not the actual
fluctuation of the inflation and interest rates to show the dollars that will be needed in the future to complete
actual or real rate of increase in the value of money over each of the operations. As such, LCCA can only be used
time.(1) It is one of the most hotly-contested and highly- to compare alternates, and not determine precisely how
debated aspects of life cycle cost analysis. Equation 3 much a pavement will cost over its total life.(1)
calculates the discount rate (Note: subtracting the in-
flation rate from the interest rate is commonly used to Choosing a Discount Rate – The Traditional View
approximate the discount rate). The debate over the discount rate centers around
DR = (INT - IFL) / (1 + IFL) (Eq. 3) selecting the appropriate interest and inflation rates. As
Where: such, to avoid biased outcomes, designers must choose
DR = Discount rate the interest and inflation rates so that they reflect the
INT = Nominal interest rate cost of funds to the agency/owner of the pavement.(34)
IFL = Inflation rate Interest Rates
The discount rate has two advantages associated with The interest rate should reflect the cost of borrowing
its use. First, it is not the absolute values of the interest money for the agency building the pavement. Factors
and inflation rates that matter, but rather their difference that need to be considered are:(34)
that is important.(34) Historically, this difference has • Whether the project is being financed by a public or
remained relatively constant at about 3.0% over the last private entity
century. Over the last 2 centuries, it has averaged • Whether the project is being financed by borrowed
1.5%.(35) Figure 13 shows this difference in interest money or capital assets
rates and the inflation rate since 1952.(36) • The rate of return for the industry or project.
* Inflation is the general increase in the price of goods and services over time. It lowers the value of a dollar, and raises the true cost
of future expenses. It is the reason you are not able to buy as much with $100 one year form now, as you are today. Interest is more
or less the opposite: it is the return on an investment. Interest raises the value of a dollar and lowers true cost of future expenses.
Page 14
Engineering Bulletin
If a state or local government is undertaking a consumers.(32) Some economists might argue that the
project, an appropriate interest rate is the municipal CPI (Consumer Price Index) is a better indicator of the
bond rate.* If a federal agency is involved, an appro- inflation rate. However, there are two reasons why the
priate rate is the rate for long-term U.S. Government PPI is a better indicator:
Securities.** Finally, if a private firm is financing a sub- 1. The CPI monitors the change in prices of goods
stantial portion of the project, then a good indicator is sold directly to the consumer. Both asphalt and
the Corporate Bonds rate.***(36) concrete are intermediate products used by con-
When selecting the value for the interest rate, it is tractors to build pavements, which is the final
important not to confuse the selection of the rates with product used by the driving public.
market or social opportunity cost. LCCA is used to 2. The CPI accounts for differing market or social
select between alternates for a given project. As such, opportunity costs that can be gained from various
the interest rate is not based on the return that can be alternatives. The CPI is an appropriate rate to use
gained by the owner/agency from investing in the in the primary analysis when an agency is deciding
market or the “social opportunity cost” of using the whether to build a roadway, a school, or invest in
funds for something else. The opportunity to invest in the market. However, once the decision to invest in
the market or for some social issue was lost in the a section of pavement has been decided, all other
primary analysis when it was decided to construct or opportunity costs have been lost and the compar-
rehabilitate the pavement, instead of the “do nothing” ison is between pavement alternates.
option.(1,34)
For these reasons, the PPI is the appropriate deflator
Inflation Rates and reflects costs for materials sold to contractors.
A good overall indicator of the appropriate inflation rate PPI's are available for a wide variety of products in-
is the Producers Price Index (PPI). The PPI indicates cluding concrete products and asphalt paving mixtures.
price changes for materials (product goods and In this analysis, the PPI for Commodities Materials and
commodities) sold directly to manufacturers at Components for Construction was used†.(36)
intermediate levels of processing. These manufacturers Table 4 summarizes the historical discount rate for
then produce a final good and sell it to the the state, federal and private sectors. During the 41-year
Table 4. Forty-one Year Average Historical Discount Rates (Derived using data
from ref. 37)
State Agencies U.S. Government Moody’s
Municipal Bond Rate Securities Seasoned AAA
(%) (%) Corporate Bonds
1997-2001* 4.37 4.88 6.09
1987-1996 3.69 4.79 5.45
1977-1986 3.16 4.98 5.57
1967-1976 -0.92 -0.45 0.80
1957-1966 2.80 3.44 3.78
45 Year Average:
1957-2001 2.42 4.88** 4.14
Recommended
2.25 3.00 4.00
Discount Rate
* 5 year average. ** 25 year average.
* Bond Buyer Index, 20 years to maturity, mixed † This is a subset of the PPI for All Commodities. The PPI for All Commodities includes non-construction
quality. items such as clothing, food, etc. The PPI for Commodities Materials and Components for Construction is
** U.S. Government Securities, over 30 years. a weighted average of 204 different items used specifically in the construction industry. In this weighted
***Moody’s Seasoned AAA Corporate Bonds. average, concrete and asphalt paving mix are two of the top 10 of weights and therefore,
any price movements in either concrete or asphalt will be reflected in this PPI.
Page 15
Engineering Bulletin
period from 1957 through 1997, the discount rate based savings in a new plant, new machine, or the stock
on the municipal bond rate averaged 2.21 %. For long- market. In deciding which to do, a private sector
term U.S. Government Securities, the discount rate company will choose the option that provides the
averaged 3.14%, and the discount rate based on the highest rate of return to cover future rehabilitation costs.
AAA Corporate Bond Rate averaged 3.93%. For public-financed, government-run highway
The FHWA suggests using discount rates in the range systems, this is not true. The Highway Revenue Act
of 3 to 5 percent.(2) However, the upper ranges of this of 1956, which established the Highway Trust Fund,
value are probably too high. Another federal agency, adopted the pay-as-you-go principle for highway
the Office of Management and Budget (OMB), which funding. That is, Congress decided that it was better to
provides guidance for discount rates for benefit-cost finance the highway system with user fees (i.e. gas
analysis to the Executive Branch of the Federal taxes) than to pay for it with tolls or bonds issued by a
Government, publishes recommended discount rates federal corporation.(37) As such, the State Departments
every year. Table 5 shows recent trends in their of Transportation must spend their available capital or
published rates. As can be seen, their rates average risk having it reduced.
between 3 and 4 percent, which is consistent with Although the Departments of Transportation in the
US Government Securities. US have been extremely successful at building the road
network in the US without a large use of borrowed
Table 5. Trends in the OMB real money, this procedure also has some inherent de-
discount rates(2) ficiencies. First, it means that public agencies can not
Analysis Period act like the private sector and compare the different
opportunities for higher rates of return. They do not
Year 3 5 7 10 30
’92 2.7 3.1 3.3 3.6 3.8 have the option to invest it in long-term, interest-
’93 3.1 3.6 4.0 4.3 4.5 bearing accounts*.
’94 2.1 2.3 2.5 2.7 2.8 Secondly, it means that when government agencies
’95 4.2 4.5 4.6 4.8 4.9 invest in highways that require more future
’96 2.7 2.7 2.8 2.8 3.0 rehabilitation, they are mandating where future budgets
’97 3.2 3.3 3.4 3.5 3.6
will be allocated. In some cases, all future budgets may
’98 3.4 3.5 3.5 3.6 3.8
’99 2.6 2.7 2.7 2.7 2.9 be earmarked for maintenance and rehabilitation, which
’00 3.8 3.9 4.0 4.0 4.2 does not allow for expansion or improvement. This
’01 3.2 3.2 3.2 3.2 3.2 generates the need to raise taxes for the reconstruction
’02 2.1 2.8 3.0 3.1 3.9 or expansion projects.
Avg. 3.0 3.2 3.4 3.5 3.7 A simpler way to look at this is that the money saved
from the lower priced alternative is not being invested
and retrieved later to do rehabilitation work. In order to
Discount Rate Selection for State DOT’s keep the alternate with the lower initial price in a safe
The discount rate described above is an interest- and usable condition throughout the analysis period, the
adjusted discount rate. The main assumption with an government agencies must pay for future work out of
interest-adjusted discount rate is that the cost savings of their yearly working capital.
the lower priced alternate is invested at the discount For this reason, future rehabilitation work is subject
rate to help pay for future maintenance and only to the effects of future inflation. Thus, every dollar
rehabilitation costs. spent by a government agency is invested in a depreci-
For the private sector, this is a reasonable assump- ating asset. A newly constructed highway starts to wear
tion. A private company or corporation can invest its out immediately and the investment is worth less the
* Governmental agencies do invest their money over the year. However, their
yearly funding is invested for the short term only. The anticipated future main-
tenance and rehabilitation costs are not invested for the long term and can
never gain the long-term return as indicated by the discount rate.
Page 16
Engineering Bulletin
following year than it is now. The same is true for the The Wisconsin procedure outlined in the “User Costs
equipment, buildings, and even the employee labor. All due to the Deterioration of the Roadway” section may be
costs are increased the following year due to the effects useful in addressing this issue.
of inflation and the lack of long-term investment that Currently, the only national design procedure that
can gain interest for the benefit of the public agency. directly compares flexible and rigid pavement designs is
Based on this situation, the true time value of money the AASHTO Pavement Design Procedure.(38) However,
to a state DOT is not the discounted cost, but the in the early analysis of the LTPP GPS test sections, it has
inflated cost so that the work can be done in the future. been found that the current AASHTO flexible design
Because the government cannot gain long-term interest equation consistently over predicts the amount of traffic
on their savings, the only costs they can account for are that asphalt pavement can carry. In 112 out of 244
the true costs or actual dollars spent on the project. As sections evaluated, the flexible pavement equation over-
such, public agencies should not discount future costs predicted traffic that a flexible pavement could carry by
with the discount rate, but rather inflate future costs more than 100%. For rigid pavements, the AASHTO
with the inflation rate (i.e. PPI) in order to determine pavement design equation does better. It accurately
the actual expenditures of the alternates. predicts the traffic, showing no bias to over prediction,
or under prediction, but it has wide variability.(24) The
Comparable Sections AASHTO 2002 Design Guide aims to improve the
In order to perform a realistic and reliable life cycle cost predictive reliability and consistency.
analysis, the two alternates must have equivalent and
comparable designs and should provide similar results Length of Analysis Period
over the analysis period. That is, they should be The analysis period is the time frame over which all
designed for the same: costs are compared. It does not have to be equal to the
• Structural (traffic-carrying) capacity design or service life and in most cases it is not. The
• Reliability main criterion is that it be long enough to reflect the
• Subgrade properties cost differences between the two pavement types. For
• Terminal condition this reason, it should be long enough to include at least
one rehabilitation cycle for all alternates.
Furthermore, they need to provide the same or
Though the analysis period can be based on
reasonably similar levels of service over the analysis
component life or a common multiple of component
period. If the two designs being compared do not have
life, facility life, or investment life, most government
these same characteristics over the analysis period, the
agencies base their analysis period on an arbitrary time
resulting LCCA is erroneous.
frame that is equal for each alternate. Typical values are
Typically, most agencies consider alternates with the
30-40 years for highways, 20-30 years for streets, and
serviceability curves shown in Figure 12 to be
30 years for airports. In general, costs that are incurred
equivalent. Though the two pavements meet all the
25-30 years or beyond play a minimal role in the life
comparable section requirements, they do provide
cycle cost analysis.
different “Quality of Service” (Figure 11). Ideally, this
If an agency is performing a LCCA on alternates
difference in the “Quality of Service” should be taken
where the analysis periods are not equal, then the life
into account in a LCCA. Unfortunately, this is difficult
cycle cost analysis must be performed with equivalent
because of the complexity in:
uniform annual cost. However, in doing this, the analyst
1. Precisely calculating performance over time, and must realize that this procedure assumes that each
2. Quantifying the difference in performance between alternates’ activities will be repeated indefinitely (i.e. the
alternates. activity streams will be repeated forever).
Page 17
Engineering Bulletin
Page 18
Engineering Bulletin
Chapter 3
Examples
The following examples demonstrate LCCA for three The discount rates are from Table 4 and cost data
hypothetical pavement sections – an interstate were derived using actual cost data from local agency
application, a rural county application, and a city street bid tabulations and inflated to 2001 prices.(39,40,41)
application. These costs are used for illustration only and are not
Each case represents a different project with different intended as guideline values. Actual costs will vary
conditions. The solutions shown are for strategies based on local project conditions, material costs, and
applied at condition levels appropriate for the labor costs.
techniques. Detailed life cycle cost analyses are shown in For brevity and simplicity, no user costs or
appendices 3, 4, and 5. maintenance costs are shown in the examples. However,
The LCCA for each alternative was calculated as in normal practice, they should be included whenever
outlined on page 2. The steps are:* possible and practical.
1. Design equivalent pavement sections
2. Develop expenditure streams for the analysis
Case 1 – Existing Interstate
period. Pavement
a. Determine the maintenance and rehabilitation An existing interstate pavement is a 31-year old concrete
strategies (activities and timing) to be used on pavement, with concrete shoulders, that is approaching
the pavement over the analysis period. its terminal serviceability. It has been determined that it
b. Estimate agency costs for each activity. requires a significant structural overlay or replacement.
3. Estimate user costs The highway is a bypass of a large city.
4. Compute Present Worth or Equivalent Uniform Two rehabilitation alternatives are examined for Case 1:
Annual Cost an unbonded concrete overlay, and a crack-and-seat of
5. Analyze results the existing concrete followed by a thick asphalt overlay.
6. Re-evaluate strategies. Comparisons are made based on costs over a 35-year
The time to first rehabilitation for the concrete analysis period using a discount rate of 3.0%. Appendix
alternatives is assumed to be 20 years for both cases. In 3 shows the calculation of traffic to determine when to
the asphalt alternatives, in case 1, it is assumed that the do future rehabilitation activities, the spreadsheet show-
initial AC pavement life is 10 years and case 2, it is ing the construction items, life cycle costs calculations,
assumed to be 15 years. The life of each rehabilitation and a cash flow diagram of the results.
activity in Case 1 is determined by assuming that each Comparisons between the alternative strategies are
activity will carry as much traffic as the original made using Present Worth Analysis. The unbonded
pavement (as outlined in Table 2 on page 10). For Case concrete overlay alternative proves to be the most cost-
2, the rehabilitation activities were assumed to occur at effective based on present worth. A couple of advantages
specific times and last only to the end of the analysis that the unbonded concrete overlay has over crack-and-
period (no salvage value). This simplification is common seat with asphalt overlay is the limited pre-overlay
practice, but not recommended. repair and the much lower requirement for extensive
future rehabilitation. The minimal future rehabilitation
Page 19
Engineering Bulletin
in this urban area also limits the user delay and traffic Based on comparisons of present worth, the concrete
control costs. alternative costs less when considered over its entire life
cycle. The analysis shows that the concrete option costs
Case 2 – Rural County Pavement 6% less in Present Worth calculations, even though it is
Case 2 involves an existing asphalt concrete roadway in 5% more in Initial Cost.
poor condition. It is a two-lane farm-to-market road.
During most of the year the pavement experiences a low Table 6. Results of LCCA Examples
volume of truck traffic. In the fall, farm equipment and (See App. 3-5 for Calculations)
grain trucks use the road extensively. Case 1 Case 2 Case 3
Example Analysis
Two rehabilitation alternatives are considered for this Interstate County City
rural road: a conventional PCC whitetopping overlay Initial Concrete $829,521 $167,065 $294,850
and staged asphalt overlays. Comparisons are made Cost Asphalt $753,351 $110,510 $278,893
based on costs over a 30-year analysis period using a Present Concrete $1,027,162 $176,190 $408,976
discount rate of 2.5%. Appendix 4 shows the Worth Asphalt $1,576,029 $171,303 $435,190
construction items for each alternative, life cycle cost
calculations, and the results.
Based on comparisons of present worth, there was no These case studies illustrate that all anticipated costs
clear distinction between the concrete and asphalt must be considered when selecting a rehabilitation
overlay alternatives. The analysis showed that both alternative: initial, future, pavement materials, and non-
options were within 3% of being equivalent based on pavement costs such as traffic control and engineering.
life-cycle cost. In such cases where a life cycle cost Consideration should also be given to items such as user
analysis produces results so close, additional costs and delays, especially in urban areas. All items will
considerations such as safety, risk, and other factors may have an influence on the annual or present worth cost
enter into the selection of the rehabilitation strategy. In and selection of the preferred restoration, resurfacing, or
the case of a rural road carrying some truck traffic, reconstruction strategy.
seasonal weight restrictions should be considered.
Annual maintenance costs, which have not been
included in the analysis, may also need to be included
in order to aid in the selection process.
Page 20
Engineering Bulletin
Chapter 4
Advanced LCCA Features
Probabilistic Analysis The results are not just one value, but a distribution on
what possible values could be.
The Life Cycle Cost Analysis procedure as described to
The basic idea with probabilistic LCCA is to put more
this point has been a “Deterministic Approach.” In a
emphasis or weight on the costs and activities that are
deterministic approach, the engineer selects a single
more certain, and less emphasis to riskier factors such as
value for each input (e.g. initial cost, maintenance and
future rehabilitation costs.
rehabilitation costs, the timing of the maintenance and
The FHWA’s probabilistic LCCA procedure uses a
rehabilitation activities, discount rate, etc.) and
“Monte Carlo Simulation.” A Monte Carlo Simulation is
computes a single PW or EUAC.
a computerized procedure that takes each input, assigns
For example, an agency states that a particular
a range of values, and then runs several thousand
pavement type will last 17 years before rehabilitation is
analyses with combinations of all inputs to generate a
needed. At that time it will require an overlay, which
probability distribution (Figure 14).
will last 10 years, and then it will require a second
overlay, which will last 8 years. If the agency uses a 3%
discount rate, an analysis period of 35 years, an initial
cost for the pavement of $2,000,000, and a cost of
$500,000 for each overlay, then the present worth of $
that pavement system is $2,530,000. However, if the
discount rate is changed to 5%, the present worth
changes to $2,350,000. This results in a 7.6% differ-
ence, which is large enough to alter a strategy selection
Time Present
decision.
As can be seen, the values chosen for the various Worth
inputs can have significant impact on the final results. %
Simply changing any one of the inputs changes the re-
sults. For this reason, almost all arguments over LCCA
Figure 14. Schematic of Monte Carlo Simulation.
deal with the selection of the inputs. However, because
there is so much variability in all of the inputs, it is very
hard to argue the validity of inputs unless actual perfor- By using a probabilistic LCCA procedure, an agency
mance data from pavement management systems is used. determines a life cycle cost distribution for each alterna-
To address the variability and reliability of the inputs, tive. By comparing the distribution of each alternative,
the FHWA developed a new LCCA procedure called the agency is able to understand the most likely cost,
“Probabilistic Life-Cycle Cost Analysis.”(2) Probabilistic and the probable high and low cost for each alternative.
LCCA takes into account the variability of each input by They are also able to understand the spread of life cycle
combining the variability of the individual inputs to cost distributions and determine which alternative has
generate a probability distribution for the LCCA results. the lowest risk. Often times, an alternative may have a
Page 21
Engineering Bulletin
higher life cycle cost, but it is a better choice because it for asphalt and concrete PPIs dating back to 1958.(35)
has less risk (Figure 15). For more information on Since 1958, the monthly percent change for concrete
performing a probabilistic LCCA, see reference 2. ingredients and related products has ranged from
between -2.43% to 6.73%. For paving asphalt, the
monthly percent change has ranged from between
0.50
Narrow Distribution -.93% to 39.41%.
is less Risk Another basic rule is that events that are closer to the
beginning of the analysis period are more “certain” and
less “risky” than events later in the analysis period.
Probability
8%
6% Simplified Risk Analysis
4% Another way to determine where the risks are is to take
2%
0% the ratio of initial costs to the present worth value.
-2% When this ratio is high (i.e. 80% or higher), the
-4%
-6% majority of the present worth value is with the initial
90
91
92
93
94
95
96
Ja 7
98
99
00
01
02
n.
n.
n.
n.
n.
n.
n.
n.
n.
n.
n.
n.
Ja
Ja
Ja
Ja
Ja
Ja
Ja
Ja
Ja
Ja
Ja
Ja
Page 22
Engineering Bulletin
50
45
Percent of Network Needing Repair
40
35
30
25
20
15
10
0
<2 3-7 8-12 13-17 18-22 23-27 29-32
Remaining Years Before Repairs are Needed
Figure 17. Schematic of Time Frame for Network Repairs.
*Structural holes. By filling the structural holes and building long-lasting pavements (greater than 32 years), the yearly rehab/construction
budget of the agency remains constant.
Page 23
Engineering Bulletin
Page 24
Engineering Bulletin
Chapter 5
Life Cycle Cost and
Performance Studies
Several states have looked at their historical pavement history (distress information as well as IRI or roughness
costs on both project and network levels the last several information), and finally the costs.
years. These include Michigan, Minnesota, Iowa, The researchers conducted two basic types of
Florida, Tennessee, South Dakota, Utah, and Georgia. analysis: life-cycle cost analysis and survival analysis.
The following summaries highlight these studies and Survival analysis is a way to assess the risk that a
give general overall conclusions. pavement section will fail in different years. The key
output of survival analysis is the mean age of pavement
Comparative Performance of failure. For this study, the definition of failure for the
In-Service Highway Pavements original pavements was placement of first overlay or
This research project consisted of a series of studies major CPR. For the rehabilitation activities, failure
undertaken to look at the long-term performance of in- constituted placement of next overlay, major CPR, or
service pavements on four rural interstate corridors and reconstruction. Figures 19 and 20 show the results of
to compare the relative costs expended on the different these analysis.
pavement types in those corridors.(43,44,45,46) From the survival analysis (Figure 19), one can see
The criteria for the projects were that the corridors that the concrete sections in these studies lasted
had to be rural interstate sections, greater than 20 years between 1.6 and 2.6 times longer than the asphalt
old; be approximately 100 centerline miles long; have sections, with an average of 2.2 times longer life. From
an approximate 50/50 split between jointed plain the LCCA analysis, the concrete sections were from 14%
concrete pavement (JPCP) and asphalt concrete to 250% more cost-effective (cheaper) than the asphalt
pavement (ACP) and approximate equal traffic loadings; pavements, with an average savings of 103%.
and finally, there needed to be no known material or
construction problems on either pavement type.
JPCP (mean) ACP (mean)
The four corridors were chosen so that they repre-
40
sented different geographical and climactic zones in the
US. The corridors selected were: 30
• I-40 in Western Tennessee
Age
Page 25
Engineering Bulletin
JPCP (mean) ACP (mean) Another Michigan study looked at the actual cost for
14,000 two pavement sections (one asphalt, one concrete) on I-
12,000 75, Gaylord to U.S. 31.(48) The asphalt section was 29.9
10,000 miles long and was built in 1961. The first maintenance
Age
8,000 contract was done in 1977 and in total there have been
6,000 9 different contracts. The concrete was built in 1960
4,000 and is 23.3 miles long. Its first and only rehabilitation
2,000 activity was done in 1987. The cost per mile for the
0 asphalt section was $188,267 and the cost per mile of
TN UT OK GA GA the concrete section was $69,460.
I-985 SR-400
Figure 20. 40-Year Life Cycle Cost Analysis. Case Study Comparisons of the
Life-Cycle Costs of HMAC and
Michigan Studies PCC Pavements on Lower Volume
In the study,(47) Michigan State University took the
Roads in Minnesota
actual costs (on a per lane, per mile basis) that the
Michigan DOT spent on approximately 3219 km (2000 This research project, which was performed by the
miles) of their highway system over the last 30 years. University of Minnesota and was cited earlier for its
The costs included the original construction cost as well procedure to determine maintenance costs, had the
as all the rehabilitation costs (i.e. reconstruction, resur- objective to perform and document comparisons of
facing, etc.). To account for age differences in the costs associated with AC and PCC pavements
pavement sections, the total costs were divided by the constructed and maintained by local highway road
average age to yield a cost per lane mile per year. agencies in Minnesota. The study looked at road
Figure 20 shows the average overall cost of Michigan networks from two counties: Olmsted County and
pavements, adjusted to 1997 dollars. As can be seen in Waseca County.(5)
Figure 21, significantly more has been spent on the The cost data collected included the initial construc-
asphalt roadways. tion costs (i.e. base, bituminous surfacing, and concrete
surfacing), the rehabilitation costs, (i.e. bituminous
overlay costs) and the maintenance costs. Because the
researchers wanted to isolate strictly the pavement costs,
3000
they only considered costs associated with construction
2500 above the finished mainline subgrade. The researchers
Cost/lane km per year
2000
performance data.
1500 The data analysis consisted of splitting the roadway
into uniform sections, proportioning all costs and ADT
1000
by section length and number of lanes, selection of an
500 analysis period that coincided with the performance life,
and calculating the net present value and equivalent
0
uniform annual cost. Because of the different structural
Bituminous (1578.6 km)
Concrete (1475.6 km)
sections, ADT, etc., the researchers grouped the roadway
into 3 general cases for each county.
Figure 21. Average overall cost per lane km per year for Michigan
(1 km = .621 mile).
Page 26
Engineering Bulletin
Table 7. Life Cycle Cost Comparisons of AC and PCC Pavements for Olmsted and
Waseca Counties.
Olmsted County
EUAC/Lane EUAC/Lane/million vehicles
Case AC PCC % Difference AC PCC % Difference
1 $ 6,886 $ 6,572 4.6% $ 597 $ 574 3.9%
2 $ 5,831 $ 6,257 -7.3% $ 3,629 $ 1,199 67.0%
3 $ 6,697 $ 6,562 2.0% $ 852 $ 720 15.5%
General $ 7,903 $ 8,412 -6.4% $ 1,858 $ 776 58.2%
Waseca County
EUAC/Lane EUAC/Lane/million vehicles
Case AC PCC % Difference AC PCC % Difference
1 $ 8,684 $ 7,405 14.7% $ 2,766 $ 2,179 21.2%
2 $ 4,681 $ 6,679 -29.9% $ 2,248 $ 2,399 -6.3%
3 $ 6,359 $ 5,414 14.9% $ 2,619 $ 1,428 45.5%
Cost comparisons were done two ways: cost per lane The specifics looked at in each county’s system were
mile and cost per lane mile per million vehicles. Costs performance* over a 40-year period from 1954-1994,
were normalized to traffic to account for the fact that construction costs, and maintenance costs. Figure 22
concrete was put onto roads that carried more and shows the cost results for County A and County B. As
heavier traffic. Results are presented in Table 7. can be seen, County A (concrete) had lower construc-
In general, the favored pavement type for the EUAC / tion and maintenance costs. On the performance side,
Lane analysis for both Olmsted and Waseca Counties both systems performed well. County A (concrete) had a
fluctuated between PCC and AC depending on which Pavement Condition Index (PCI) rating of 97 (Excellent)
case is analyzed. However, when the results were and County B (asphalt) had a rating of 84 (Very Good).
normalized for traffic, the PCC pavements were more
cost-effective in all cases for Olmsted County and for all
but one case for Waseca county. 16
14
Iowa County Road Study – Impact
Cost (millions $)
12
of Pavement Type on County Road 10
8
Systems 6
This was a study of three representative counties in Iowa 4
to evaluate their individual pavement systems in order 2
to determine the effect of a concrete policy vs. an 0
County A County B
asphalt policy.(49) The first county, County A, had a Construction Costs
system primarily concrete with “whitetopping” overlays. Maintenance Costs
County B consisted of a system primarily asphalt with Figure 22. Construction and Maintenance Costs from the Iowa
asphalt overlays, and County C had an approximate County Road Study.
even split between asphalt and concrete. The results
presented here will focus on counties A and B.
Page 27
Engineering Bulletin
Page 28
Engineering Bulletin
Chapter 6
Summary
Life Cycle Cost Analysis (LCCA) is a procedure to Other factors, such as construction duration, ride-
economically compare competing design alternates ability over time, safety, and environmental friendliness
considering all significant costs and benefits over the can also enter into pavement type selection. However, it
economic life of each alternate. LCCA equates all present is difficult to relate these factors to cost or performance
and future costs (and benefits) over the life of a project and put them into an economic analysis. When
by accounting for the effects of the time value of money. possible, it is better to make adjustments on each
Because life cycle costing compares alternates, it is alternate to account for these factors while developing
necessary that each alternate is equivalently designed and the strategy before LCCA.
provides similar performance results. Comparing Enhancements to LCCA include probabilistic LCCA
alternates that do not provide similar performance results and network impact analysis. These techniques improve
is neither realistic nor reliable because the two alternates the understanding of the cost/benefit of specific projects
are not equivalent. An economic assessment between
or alternates and how they fit into the broader scope of
non-equivalent alternates yields erroneous results.
an agency’s decisions.
Present Worth (PW) and Equivalent Uniform Annual
Cost (EUAC) are the two most common methods to
express the time value of money. PW is the sum of all
costs over the project life in today's dollars. It combines
initial costs with the anticipated costs of future rehabili-
tation. Future costs are discounted to present costs using
the discount rate. Present worth analysis is limited to
comparisons of alternates with equal service lives.
EUAC spreads all costs (initial, rehabilitation, and
anticipated rehabilitation) to an annual cost over the
analysis period. EUAC is advantageous because it
more effectively compares alternates with different
service lives.
The fundamental factors that should be considered in
LCCA are:
• Agency costs (initial cost, rehabilitation and operation
costs, and maintenance costs)
• User costs (delay-of-use, roadway deterioration, and
accident costs)
• Discount rate
• Rehabilitation election and service life between
rehabilitations
• Comparable sections
• Analysis period
Page 29
Engineering Bulletin
References 1. Kirk, Stephen J., and Dell’isola, Alphonse J., Life Cycle Costing for
Design Professionals, 2nd Edition, McGraw-Hill, New York, NY, 1995.
2. Walls, J., and Smith, M., Life Cycle Cost Analysis in Pavement Design –
In Search of Better Investment Decisions, Demonstration Project 115,
Federal Highway Administration, Washington D.C., 1998.
3. Cole, L., and Hall, M., Relative Costs of Various Concrete Pavement
Features, TRR 1574, TRB, NRC, Washington D.C., 1997.
5. Embacher, Rebecca A., and Snyder, Mark B., Case Study Comparisons of
the Life-Cycle Costs of HMAC and PCC Pavements on Lower Volume
Roads, University of Minnesota Dept. of Civil Engineering.
12. Joint and Crack Sealing and Repair for Concrete Pavements, TB012P,
American Concrete Pavement Association, Skokie, IL, 1993.
Page 30
Engineering Bulletin
19. Gharaibeh, N. G.; Darter, M. I.; LaTorre, F.; Vespa, J. W.; and Lippert,
D. L., Performance of Original and Resurfaced Pavements on the Illinois
Freeway System, Research Report 540-1, University of Illinois at
Urbana-Champaign, February 1997.
20. Chen, H.; Bendana, L.; and McAuliffe, D., Adapting the AASHTO
Pavement Design Guide to New York State Conditions, Research Report
164, Transportation Research and Development Bureau, New York
State DOT, 1995.
22. Rao, S.; Yu, H. T.; and Darter, M. I., The Longevity and Performance of
Diamond-Ground Pavements, RD118P, Portland Cement Association,
Skokie, IL 1999.
Page 31
Engineering Bulletin
26. 1996 Highway Funding Methods, Condition, and Use, The Road
Information Program (TRIP), Washington D.C., 1996.
28. Graham, J. L.; Paulson, R. J.; and Glennon, J. C., Accident Analysis of
Highway Construction Zones, Transportation Research Record 693,
Transportation Research Board, National Research Council,
Washington D.C., 1978.
30. Wang, J. J., and Abrams, C. M., Planning and Scheduling Work Zone
Traffic Control – Technical Report, Report No. FHWA/RD/81/0049,
Federal Highway Administration, 1981.
32. Andrew, L. B., and Bryden, J. E., Managing Construction Safety, and
Health: Experience of New York State Department of Transportation,
Transportation Research Record 1585, Transportation Research Board,
National Research Council, Washington D.C., 1997.
33. “How Fast Can We Built It? A Completion Time Comparison – PCC
vs. HMA,” Iowa Scene Project Report #25, Iowa Concrete Paving
Association, November, 2001.
34. Kerr, W. O., and Ryan, B. A, Avoiding the Pitfalls of Life Cycle Cost
Analysis, Washington Economic Research Consultants, October, 1987.
35. Tips for Retirement Planning, PC World Magazine, Volume 15, Number
1, January, 1997.
36. Federal Reserve Statistical Release, H.15 (519), Selected Interest Rates,
The Federal Reserve System, Washington D.C.
Page 32
Engineering Bulletin
43. Gharaibeh, N. G., and Crow, T. L., Comparative Performance and Costs
of In-Service Highway Pavements I-40, Tennessee, PCA R&D Serial No.
2209, Portland Cement Association, 2000.
44. Hoerner, T. E.; Darter, M. I.; Gharaibeh, N. G.; and Crow, T. L.,
Comparative Performance and Costs of In-Service Highway Pavements
I-15, Utah, PCA R&D Serial No. 2209a, Portland Cement Association,
2001.
45. Smith, K.; Gharaibeh, N. G.; Crow, T. L.; and Ayers, M. E.,
Comparative Performance and Costs of In-Service Highway Pavements I-
40, Oklahoma, PCA R&D Serial No. 2209b, Portland Cement
Association, 2001.
47. Snook, R., and Buch, N., Long-Term Cost Comparison of Pavement Types
in Michigan, Michigan State University, May, 1998.
Page 33
Engineering Bulletin
50. Peterson, Lloyd, E., P.E., Kansas Rigid Pavements Serve Years Without
Ills, Roads and Bridges, Scranton-Gillette, Des Plaines, IL, September
1986.
Page 34
Engineering Bulletin
APPENDICES
Appendices
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 4 0 42 44 46 48 50
Page 35
Engineering Bulletin
Appendix 2
The following timelines show the expenditure streams used by several states in their LCCA procedures. As can be
seen, some states have clearly defined and detailed guidelines, while others are much broader. The timelines herein
are not to be interpreted as suggestions for your use. ACPA does not endorse these timelines. Rather, they are shown
here to demonstrate the variety of practice by state agencies.
Concrete
30 yr analysis
30 yr design 5 10 15 20 25 30
CPR & 3% slab replacement Crack & seal with 100 mm asphalt overlay
Concrete
Rural 5 10 15 20 25 30 35 40
Mill 50 mm & 30 mm binder & Mill 50 mm & 30 mm binder &
25 mm wearing asphalt overlay 25 mm wearing asphalt overlay
Florida
Asphalt
40 yr analysis
Urban 5 10 15 20 25 30 35 40
Mill 50 mm & 80 mm binder & Mill 50 mm & 80 mm binder &
15 mm wearing asphalt overlay 15 mm wearing asphalt overlay
Asphalt
Rural 5 10 15 20 25 30 35 40
Mill 80 mm & 100 mm binder & Mill 80 mm & 100 mm binder &
15 mm wearing asphalt overlay 15 mm wearing asphalt overlay
Asphalt
Limited 5 10 15 20 25 30 35 40
Access
Joint resealing
Concrete
5 10 15 20 25 30
Georgia
5 10 15 20 25 30 35
Asphalt overlay
1" Aslphalt overlay (1/3 original thickness -1") 35 yr analysis
Asphalt
>10,000 5 10 15 20 25 30 35
ADT
Page 36
Engineering Bulletin
CPR (pressure grout 70% of joints & Rout & seal all joints, pavement
Rout & seal all joints, grind pavement surface), rout & seal patching 2.5%, shoulder patching 1.5%
pavement patching 1%, all joints, pavement patching 4%,
shoulder patching 1% shoulder patching 4%
Pavement Pavement Pavement patching 1.5% Pavement patching 3.5%
patching 0.5% patching 1.5% shoulder patching 1% shoulder patching 2%
Concrete
All Traffic 5 10 15 20 25 30 35 40
Levels
Pavement Pavement patching 3% Policy overlay (mill .75" & lay 3.25" Rout & seal all longitudinal shoulder
patching shoulder patching 2% or 2" of AC surface), pavement & centerline cracks, 100% of thermal/
0.5% patching 4%, shoulder patching transverse cracks,
Rout & seal all
4% & 50% of random cracks
longitudinal
shoulder & Rout & seal
centerline 50% of Rout & seal all longitudinal Rout & seal all longitudinal
cracks & 15% of thermal/ shoulder & centerline cracks, shoulder & centerline cracks,
thermal/trans- transverse 100% of thermal/transverse 100% of thermal/transverse Pavement patching 3%
verse cracks cracks cracks, & 50% of random cracks, & 50% of random shoulder patching 3%
cracks cracks
Asphalt
Traffic factor 5 10 15 20 25 30 35 40
<15.0 (rural)
<10.0 (urban)
Pavement Surface mill .75" & 1.5" asphalt Policy overlay (mill .75" & lay 3.25" Surface mill .75" & 1.5" asphalt
patching overlay, pavement patching 3%, or 2" of AC surface), pavement overlay, pavement patching 3%,
Rout & seal all 0.5% shoulder patching 2% patching 4%, shoulder shoulder
longitudinal patching 4% patching 3%
shoulder & Rout & seal
centerline 50% of Rout & seal all longitudinal Rout & seal all longitudinal
cracks & 15% of thermal/ shoulder & centerline cracks, shoulder & centerline cracks,
thermal/trans- transverse 100% of thermal/transverse 100% of thermal/transverse
verse cracks cracks cracks, & 50% of random cracks, & 50% of random
Illinois
cracks cracks
Asphalt
40 yr analysis
Traffic factor 5 10 15 20 25 30 35 40
>15.0 & <24.5 (rural)
>10.0 & <16.3 (urban)
Surface mill .75" & 1.5" asphalt Policy overlay (mill .75" & lay Surface mill .75" & 1.5" asphalt
overlay, pavement patching 3.25" or 2" of AC overlay, pavement patching
3%, shoulder patching 2% surface), pavement 3%, shoulder patching 3%
Pavement patching 0.5% Rout & seal all patching 4%,
Rout & seal all longitudinal longitudinal shoulder patching 4%
Rout & seal all shoulder & centerline cracks, shoulder &
longitudinal 50% of thermal/transverse centerline
shoulder & cracks, & 50% of random cracks, 100% Rout & seal all longitudinal Rout & seal all longitudinal
centerline cracks of thermal/ shoulder & centerline cracks, shoulder & centerline cracks,
cracks & 15% of transverse 100% of thermal/transverse 100% of thermal/transverse
thermal/trans- Rout & seal 50% of cracks, & 50% cracks, & 50% of random cracks, & 50% of random
verse cracks thermal/transverse of random cracks cracks
Asphalt cracks cracks
Traffic factor 5 10 15 20 25 30 35 40
>24.5 & <34.0 (rural)
>16.3 & <22.7 (urban)
Page 37
Engineering Bulletin
5 10 15 20 25 30
Additional
Maintenance 2-1/2" Overlay Maintenance 1" Overlay maintenance 33 yr analysis
Asphalt
5 10 15 20 25 30
Saw & reseal joints Saw & reseal joints and grind
Concrete
North Carolina
5 10 15 20 25 30
30 yr analysis
Mill 2-1/2" & overlay 2-1/2" Mill 2-1/2" & 4-1/2" asphalt overlay
Asphalt
5 10 15 20 25 30
5 10 15 20 25 30
30 yr analysis
1-1/4" asphalt overlay Mill 1" & 2-3/4" asphalt overlay
Asphalt
5 10 15 20 25 30
5 10 15 20 25 30 35 40
40 yr analysis
Asphalt overlay Asphalt overlay Asphalt overlay
Asphalt
5 10 15 20 25 30 35 40
Drained 5 10 15 20 25 30 35 40 45 50
50 yr analysis
Overlay Mill & overlay Mill & overlay Reconstruct
Asphalt
Undrained 5 10 15 20 25 30 35 40 45 50
Page 38
Engineering Bulletin
Appendix 3
Case 1: Existing 4-Lane Interstate
Alternative A – Unbonded PCC Overlay
Timing of Rehabilitation Activities
Avg. Daily Traffic (ADT) 20,000
Growth Rate 3%
Life Estimate of Original Pavement 20 years
Yearly Cumulative Traffic Carried by
Year Traffic Traffic Pavement/Rehab. Activities
1 7,300,000 7,300,000
2 7,519,000 14,819,000
3 7,744,570 22,563,570
4 7,976,907 30,540,477
5 8,216,214 38,756,691
6 8,462,701 47,219,392
7 8,716,582 55,935,974
8 8,978,079 64,914,053
9 9,247,422 74,161,475
10 9,524,844 83,686,319
11 9,810,590 93,496,909
12 10,104,907 103,601,816
13 10,408,054 114,009,870
14 10,720,296 124,730,166
15 11,041,905 135,772,071
16 11,373,162 147,145,234
17 11,714,357 158,859,591
18 12,065,788 170,925,378
19 12,427,761 183,353,140
20 12,800,594 196,153,734 196,153,734 1st Rehab
21 13,184,612 209,338,346 13,184,612
22 13,580,150 222,918,496 26,764,762
23 13,987,555 236,906,051 40,752,317
24 14,407,182 251,313,233 55,159,499
25 14,839,397 266,152,630 69,998,896
26 15,284,579 281,437,208 85,283,475
27 15,743,116 297,180,325 101,026,591
28 16,215,410 313,395,734 117,242,001
29 16,701,872 330,097,606 133,943,873
30 17,202,928 347,300,535 151,146,801
31 17,719,016 365,019,551 168,865,817
32 18,250,587 383,270,137 187,116,403 2nd Rehab
33 18,798,104 402,068,241 18,798,104
34 19,362,047 421,430,289 38,160,151
35 19,942,909 441,373,197 58,103,060 End
36 20,541,196 461,914,393 78,644,256
37 21,157,432 483,071,825 99,801,688
38 21,792,155 504,863,980 121,593,842
39 22,445,919 527,309,899 144,039,762
40 23,119,297 550,429,196 167,159,059
41 23,812,876 574,242,072 190,971,935 3rd Rehab
Year 35 End of Analysis — 6 Years of Salvage Value
Page 39
Engineering Bulletin
Example – Case 1
Alternative A – 4-Lane Interstate, Unbonded PCC Overlay Expected Life: 35 yrs. Discount Rate: 3.0%
Total Total Year Present
Cost Units Quantity Cost/Mile Applied Worth
Pavement Items:
9 PCC Unbonded OL, Furnish/Mainline $65.00 CY 4693.3 $305,067 $305,067
9 PCC Unbonded OL, Placement/Mainline $6.00 SY 14080.0 $84,480 $84,480
1.5 Epoxy Coated Dowel Bars, Mainline $1.50 SY 14080.0 $21,120 $21,120
9 PCC Unbonded OL, Furnish/Shoulder $65.00 CY 2737.8 $177,956 $177,956
9 PCC Unbonded OL, Placement/Shoulder $6.00 SY 8213.3 $49,280 $49,280
Full-Depth Repair (1% of Mainline) $65.00 SY 70.4 $4,576 $4,576
1.0, Asphalt Concrete Separation Layer $22.00 Ton 1254.0 $27,588 $27,588
Prime Coat, Mainline $0.80 Gallons 7431.1 $5,945 $5,945
Edge Drains $3.50 LF 5280.0 $18,480 $18,480
TOTAL COST PAVEMENT ITEMS = $694,491
Non-Pavement Items:
Select Fill (Trucked) $8.00 CY 7335.0 $58,680 $58,680
Guard Rail Beam, Posts, and Anchors
(Remove and Replace) $7,500.00 LS 1.0 $7,500 $7,500
Delineators, Mileposts, and Signs
(Remove and Replace) $750.00 LS 1.0 $750 $750
24 Concrete Culvert (Extend) $25.00 LF 40.0 $1,000 $1,000
24 Dia. Concrete Apron
(Remove and Replace) $120.00 Each 5.0 $600 $600
User Delay Cost $27,000.00 Day 2.0 $54,000 $54,000
Traffic Control $12,500.00 Mile 1.0 $12,500 $12,500
TOTAL COST NON-PAVEMENT ITEMS = $135,030
1st Rehab — CPR and Diamond Grinding (Year 20)
PCC Joint Saw & Seal — Transverse $1.00 LF 8448.0 $8,448 20 $4,677
Centerline $1.00 LF 5280.0 $5,280 20 $2,923
Shoulder, Long $1.00 LF 10560.0 $10,560 20 $5,847
Shoulders, Trans. $1.00 LF 4928.0 $4,928 20 $2,729
Full Depth Repair (1.5% of Area) $65.00 SY 211.2 $13,728 20 $7,601
Partial Depth Repair (0.5% of Area) $16.50 SF 633.6 $10,454 20 $5,788
Diamond Grind entire surface $3.50 SY 14080.0 $49,280 20 $27,285
User Delay Cost $27,000.00 Day 6.0 $162,000 20 $89,695
Traffic Control $2,000.00 Mile 1.0 $2,000 20 $1,107
Engineering (@ 10%) $26,667.84 LS 1.0 $26,668 20 $14,765
TOTAL COST YEAR 20 ITEMS = $293,346
2nd Rehab — CPR and Diamond Grinding (Year 32)
PCC Joint Saw & Seal — Transverse $1.00 LF 8448.0 $8,448 32 $3,281
Centerline $1.00 LF 5280.0 $5,280 32 $2,050
Shoulder, Long $1.00 LF 10560.0 $10,560 32 $4,101
Shoulders, Trans. $1.00 LF 4928.0 $4,928 32 $1,914
Full Depth Repair (3.0% of Area) $65.00 SY 422.4 $27,456 32 $10,662
Partial Depth Repair (1.0% of Area) $16.50 SF 1267.2 $20,909 32 $8,120
Diamond Grind entire surface $3.50 SY 14080.0 $49,280 32 $19,137
User Delay Cost $27,000.00 Day 6.0 $54,000 32 $20,970
Traffic Control $2,000.00 Mile 1.0 $2,000 32 $777
Engineering (@ 10%) $18,286.08 LS 1.0 $18,286 32 $7,101
TOTAL COST YEAR 32 ITEMS = $201,147
Residual Life Value (6 years) -$120,688.13 LS 1.0 -$120,688 35 -$42,891
*Example costs are for use in the examples presented in this bulletin. Initial Cost: $829,521
They are not intended as a guideline. Actual costs vary based on Present Worth: $1,027,162
local project conditions, material and labor costs. IC/PW 80.8%
R1/PW 15.8%
R2/PW 3.4%
100%
Page 40
Engineering Bulletin
Example – Case 1
Alternative A – 4-Lane Interstate, Unbonded PCC Overlay
The cash flow diagram (below) shows the inflow and outflow of cash due to
construction and rehabilitation. Arrows indicate a major cash expenditure
(construction, rehabilitation, etc.). An up arrow indicates the outflow of cash.
Down arrows show inflows.
Initial Construction
$829,521
CPR 2
CPR 1 $201,147
$293,346
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 4 0 42 44 46 48 50
-$120,688
Salvage Value
IC 9" Unbonded PCC Overlay
Doweled Joints. 15' joint spacing
CPR 1 Reseal PCC Joints
Full Depth Repair (1.5% of Area)
Partial Depth Repair (0.5% of Area)
Diamond Grind Entire Surface
CPR 2 Reseal PCC Joints
Full Depth Repair (3.0% of Area)
Partial Depth Repair (10% of Area)
Diamond Grind Entire Surface
PW is calculated using the following formula:
PW = Rehab Cost / (1 + i) n
Where
i = discount rate
n = year rehab takes place
Discount Rate = 3.0%
Yr Cost (1 + i) n PW
Initial Const. 0 $829,521 1.000 $829,521
Rehab1. 20 $293,346 1.806 $162,419
Rehab2. 32 $201,147 2.575 $ 78,113
Rehab3.
Rehab4.
Rehab5.
Rehab6.
Rehab7.
Rehab8.
Rehab9.
Rehab10.
Salvage 35 -$120,688 2.814 -$ 42,891
Total Cost $1,203,326 Total NPV $1,027,162
Page 41
Engineering Bulletin
Example – Case 1
Alternative B – Crack and Seat PCC with AC Overlay
Timing of Rehabilitation Activities
Page 42
Engineering Bulletin
Alternative B – 4-Lane Interstate, Crack & Seat PCC with AC Overlay Expected Life: 35 yrs. Discount Rate: 3.0%
Total Total Year Present
Cost Units Quantity Cost/Mile Applied Worth
Pavement Items:
3" Asphalt Concrete Surface, Mainline $31.50 Tons 2376.0 $74,844 $74,844
9" Asphalt Concrete Binder, Mainline $30.00 Tons 7128.0 $213,840 $213,840
Prime Coat, Mainline $0.80 Gallons 4693.3 $3,755 $3,755
3" Asphalt Concrete Surface, Shoulder $31.50 Tons 1386.0 $43,659 $43,659
9" Asphalt Concrete Binder, Shoulder $30.00 Tons 4158.0 $124,740 $124,740
Prime Coat, Shoulder $0.80 Gallons 2737.8 $2,190 $2,190
Crack and Seat, Mainline $1.00 SY 14080.0 $14,080 $14,080
Crack and Seat, Shoulder $1.00 SY 8213.3 $8,213 $8,213
Edge Drains $3.50 LF 5280.0 $18,480 $18,480
TOTAL COST PAVEMENT ITEMS = $503,801
Non-Pavement Items:
Select Fill (Trucked) $8.00 CY 8150.0 $65,200 $65,200
Guard Rail Beam, Posts, and Anchors
(Remove and Replace) $7,500.00 LS 1.0 $7,500 $7,500
Delineators, Mileposts, and Signs
(Remove & Replace) $750.00 LS 1.0 $750 $750
24" Concrete Culvert (Extend) $25.00 LF 40.0 $1,000 $1,000
24" Dia. Concrete Apron (Remove & Replace) $120.00 Each 5.0 $600 $600
User Delay Cost $27,000.00 Day 6.0 $162,000 $162,000
Traffic Control $12,500.00 Mile 1.0 $12,500 $12,500
TOTAL COST NON-PAVEMENT ITEMS = $249,550
1st Rehab — Overlay at Year 10:
3" Cold-Milling $1.50 SY 14080.0 $21,120 10 $15,715
3" Asphalt Surface, Mainline $31.50 Tons 2376.0 $74,844 10 $55,691
Tack Coat, Mainline $0.80 Gallons 4693.3 $3,755 10 $2,794
3" Cold-Milling, Shoulders $1.50 SY 8213.3 $12,320 10 $9,167
3" Asphalt Surface, Shoulders $24.00 Tons 1386.0 $33,264 10 $24,752
Tack Coat, Shoulders $0.80 Gallons 2737.8 $2,190 10 $1,630
User Delay Cost $27,000.00 Day 6.0 $162,000 10 $120,543
Traffic Control $2,000.00 Mile 1.0 $2,000 10 $1,488
Engineering (@ 10%) $31,149.29 LS 1.0 $31,149 10 $23,178
TOTAL COST YEAR 10 ITEMS = $342,642
2nd Rehab — Overlay at Year 18:
3" Cold-Milling $1.50 SY 14080.0 $21,120 18 $12,406
3" Asphalt Surface, Mainline $31.50 Tons 2376.0 $74,844 18 $43,963
Tack Coat, Mainline $0.80 Gallons 4693.3 $3,755 18 $2,205
3" Asphalt Surface, Outer Shoulder $1.50 SY 8213.3 $12,320 18 $7,237
3" Asphalt Surface Inner Shoulder $24.00 Tons 1386.0 $33,264 18 $19,539
Tack Coat, Shoulders $0.80 Gallons 2737.8 $2,190 18 $1,287
User Delay Cost $27,000.00 Day 6.0 $162,000 18 $95,158
Traffic Control $2,000.00 Mile 1.0 $2,000 18 $1,175
Engineering (@ 10%) $31,149.29 LS 1.0 $31,149 18 $18,297
TOTAL COST YEAR 18 ITEMS = $342,642
Page 43
Engineering Bulletin
(Continued)
Page 44
Engineering Bulletin
Example – Case 1
Alternative B – 4-Lane Interstate, Crack and Seat PCC with AC Overlay
The cash flow diagram (below) shows the inflow and outflow of cash due to
construction and rehabilitation. Arrows indicate a major cash expenditure
(construction, rehabilitation, etc.). An up arrow indicates the outflow of cash.
Down arrows show inflows.
Initial Construction
$753,351 Reconstruct
$701,281
1st 2nd 3rd
Mill/AC Mill/AC Mill/AC
$342,642 $342,642 $342,642
End of Analysis Period
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 4 0 42 44 46 48 50
-$280,512
Salvage Value
Yr Cost (1 + i) n PW
Initial Const. 0 $753,351 1.000 $753,351
Rehab1. 10 $342,642 1.344 $254,958
Rehab2. 18 $342,642 1.702 $201,266
Rehab3. 24 $342,642 2.033 $168,557
Rehab4. 29 $701,281 2.357 $297,586
Rehab5.
Rehab6.
Rehab7.
Rehab8.
Rehab9.
Rehab10.
Salvage 35 -$280,512 2.814 -$ 99,689
Total Cost $2,202,046 Total NPV $1,576,029
Page 45
Engineering Bulletin
Appendix 4
Case 2: 2-Lane Rural/Local County Pavement
Alternative A – Whitetopping PCC Overlay Expected Life: 30 yrs. Discount Rate: 2.5%
Non-Pavement Items:
Guard Rail Beam, Posts, and Anchors
(Remove and Replace) $7,500.00 LS 1.0 $7,500 $7,500
Delineators, Mileposts, and Signs
(Remove & Replace) $750.00 LS 1.0 $750 $750
Traffic Control $12,500.00 Mile 1.0 $12,500 $12,500
TOTAL COST NON-PAVEMENT ITEMS = $20,750
*Example costs are for use in the examples presented in this bulletin. Initial Cost: $167,065
They are not intended as a guideline. Actual costs vary based on Present Worth: $176,190
local project conditions, material and labor costs. IC/PW 94.8%
R1/PW 5.2%
100.0%
Page 46
Engineering Bulletin
Non-Pavement Items:
Guard Rail Beam, Posts, and Anchors
(Remove and Replace) $7,500.00 LS 1.0 $7,500 $7,500
Delineators, Mileposts, and Signs
(Remove & Replace) $750.00 LS 1.0 $750 $750
Traffic Control $12,500.00 Mile 1.0 $12,500 $12,500
TOTAL COST NON-PAVEMENT ITEMS = $20,750
Crack Sealing:
AC Crack Sealing (Year 10) $1.00 LF 95.0 $95 10 $74
Traffic Control $500.00 Mile 1.0 $500 10 $391
AC Crack Sealing (Year 25) $1.00 LF 950.0 $950 25 $512
Traffic Control $500.00 Mile 1.0 $500 25 $270
*Example costs are for use in the examples presented in this bulletin. Initial Cost: $110,510
They are not intended as a guideline. Actual costs vary based on Present Worth: $171,303
local project conditions, material and labor costs. IC/PW 64.5%
R1/PW 34.8%
R2/PW 0.7%
100.0%
Page 47
Engineering Bulletin
Appendix 5
Case 3: City Street Reconstruction
Alternative A – City Street Reconstructed with Concrete Expected Life: 30 yrs. Discount Rate: 2.25%
Total Total Year Present
Cost Units Quantity Cost/Mile Applied Worth
Pavement Items:
5" Plain Concrete Pavement $8.00 SY 28160.0 $225,280 $225,280
TOTAL COST PAVEMENT ITEMS = $225,280
Non-Pavement Items:
Select Fill (Trucked) $8.00 CY 7040.0 $56,320 $56,320
Delineators, Mileposts, and Signs
(Remove & Replace) $750.00 LS 1.0 $750 $750
Traffic Control $12,500.00 Mile 1.0 $12,500 $12,500
TOTAL COST NON-PAVEMENT ITEMS = $69,570
*Example costs are for use in the examples presented in this bulletin. Initial Cost: $294,850
They are not intended as a guideline. Actual costs vary based on Present Worth: $408,976
local project conditions, material and labor costs. IC/PW 72.1%
R1/PW 27.9%
100%
Page 48
Engineering Bulletin
Alternative B – City Street Reconstructed with Asphalt Expected Life: 30 yrs. Discount Rate: 2.25%
*Example costs are for use in the examples presented in this bulletin. Initial Cost: $278,893
They are not intended as a guideline. Actual costs vary based on Present Worth: $435,190
local project conditions, material and labor costs. IC/PW 64.1%
R1/PW 19.8%
R2/PW 0.3%
R3/PW 15.8%
100.0%
Page 49
Metric Conversion Factors
The following table provides metric conversion factors for common English units used in pavement engineering, and
concrete pavement design and construction. Where possible the values given reflect standard conversions
provided by IEEE/ASTM SI-10.
WinPAS™
Pavement Analysis Software
ACPA’s Windows™ Pavement Analysis Software
(WinPAS™ ) includes the latest information and
design parameters for the pavement design
engineer. WinPAS incorporates the pavement
design methods from the 1993 AASHTO Guide
for Design of Pavement Structures.
Alternatively,
By fax: 1-847-966-9666 (Fax orders may be sent 24 hours per day, 7 days per week.)
By mail: American Concrete Pavement Association, P.O. Box 726, Skokie, Illinois 60076-0726
American
Concrete
Pavement
Association
5420 Old Orchard Road
Suite A100
Skokie, Illinois 60077-1059
Phone: 847-966-2272
Fax: 847-966-9970
www.pavement.com