Professional Documents
Culture Documents
Module 3 :
CONSTRUCTION PROJECT PROCUREMENT
AND CONTRACT MANAGEMENT
PROJECT PREPARATION
2
Procurement/Tendering as Client/Owner
make sure that....
your requirements are well-defined
1
PROJECT PREPARATION
3
Bidding as a Contractor
make sure that....
you are aware of the rules for bidding
WHAT IS PROCUREMENT?
4
2
WHY UNDERGO THE PROCESS?
5
and yet many firms fall into the trap of not setting
aside time and resources for good selection
3
PROCUREMENT PREREQUISITES
7
a system of ______________
qualified evaluators
4
CONTRACTOR PROCUREMENT
9
CONTRACTOR PROCUREMENT
10
Contractor Pre-qualification
5
CONTRACTOR PROCUREMENT
11
Contractor Pre-qualification
Submittal Requirements
1. Legal Documents
PCAB License
Valid JV Agreements
Authorization to Verify Submitted Documents
2. Technical Documents
Statement of all completed projects (last 3 years)
Statement of ongoing projects
3. Financial Documents
Audited Financial Statements
Contractor’s NFCC Statement
CONTRACTOR PROCUREMENT
12
6
CONTRACTOR PROCUREMENT
13
CONTRACTOR PROCUREMENT
14
7
CONTRACTOR PROCUREMENT
15
Awarding of Contract
By Bid Contract
By __________ Contract
8
BONDS AND SECURITIES
17
Types
Bid Bond – during bidding
Performance Bond – during construction
9
BONDS AND SECURITIES
19
VARIATION ORDERS
20
Supplemental Agreement
10
CHANGE ORDERS
21
11
SUPPLEMENTAL AGREEMENT
23
OTHER TERMS
24
_________ Damages
amount due the Client for Contractor’s refusal or failure to
complete the work within the specified time (including time
extensions)
TLD = VUUP x [(1 + OCC) n – 1)] x K
Substantial Completion
refers to Contractor’s satisfactory completion of 95%
(quantity and value) of the works
This is not in RA9184 but is an industry-accepted
performance parameter
12
OTHER TERMS
25
Punch-list
document which specifies the remaining works, deficiencies
to be corrected and time of completion (considering
approved contract time)
Incentive Bonus
amount due the Contractor upon early completion (without
suspension orders/extension) of contract (works which saves
the Government expenses for engineering and allows early
use of the completed facility) – applicable only for major
and urgent projects
TIB = VCUP x [(1 + OCC) t – 1)] x K’
13