Professional Documents
Culture Documents
Presented By:
ALIM, JANEIL S.
GARCIA, REHAN D.
PINEDA, JUAN CARLOS R.
TOLENTINO, GEOCEL A.
Adviser:
ENGR. CRISPIN S. LICTAOA
PLANNING & SCHEDULING
PLANNING
- is the process of defining the goals and objectives of a project,
determining the resources required to achieve them, and creating
a timeline for completion.
▪ DEFINE THE PROJECT SCOPE: It's important to clearly define the project
scope, including the project goals, deliverable, and constraints. This
information is crucial for developing an accurate project schedule.
▪ DEVELOP A PROJECT SCHEDULE: Once you have identified the tasks, task
dependencies, and resource requirements, you can develop a detailed
project schedule that includes start and end dates, duration, and
resource assignments.
PERT CPM
BASIS FOR COMPARISON PERT CPM
6. There are three times estimates in PERT, i.e. optimistic time (to),
most likely time ™, pessimistic time (tp). On the other hand, there
is only one estimate in CPM.
11. PERT is best for research and development projects, but CPM is
for non-research projects like construction projects.
CPM
(EXAMPLES)
FIND THE CRITICAL PATH
FIND THE CRITICAL PATH USING FORWARD-BACKWARD PASS
PERT
(EXAMPLES)
FIND THE CRITICAL PATH
𝑧 = 0.76 ; 𝜓 𝑧 = 0.7764
𝑧 = 0.77; 𝜓 𝑧 = 0.7794
0.7764 + 0.7794
𝜓 𝑧 = = 0.7779 ≡ 77.8%
2
- The actual s-curve ends at the project’s cut-off date, which is the
last day that the production schedule is updated. The actual s-
curve meets the target s-curve at the end of the project.
THANK YOU!