Professional Documents
Culture Documents
SCHEDULE DEVELOPMENT The primary advantage of using a bar chart is that it is simple
to read. The plan, schedule, and progress of the program or
Tools for Developing Schedules project can be depicted graphically on a single chart. Figure
Computer software for developing, progressing, and updat- 13.1 shows the six-activity plan, 15-week schedule, and cur-
ing schedules is affordable and readily available. Although rent status. The current status shows that Activity B has not
computers are the tools, and software provides the means for started and is behind schedule (by 5 weeks), Activity C is
developing schedules, the individual user must understand slightly ahead of schedule (by 1 week), Activity E is slightly
what the computer is performing. behind schedule (by 2 weeks), and all other activities are on
schedule. However, it cannot be determined if Activity B or
While numerous scheduling methodologies exist for develop- Activity E will have an impact on another activity or on the
ing project schedules, two of the most common are bar charts project completion. This graphical representation of work
and critical path. A third method, project evaluation review versus time is easy to read and provides a simple, under-
technique (PERT), is mostly used by government agencies for standable way to schedule small undertakings.
calculating the most likely duration for networks.
Bar charts have not been used successfully for large-scope,
Bar Chart (Gantt Chart) Method one-time-through projects primarily due to the following
The bar chart, also called a Gantt chart, is primarily meant to reasons:
control only time elements of a program or project. However,
since there are no relationships between the activities, it is • The inherent simplicity precludes including sufficient
not possible to assess the impact of one activity on another detail to enable timely detection of schedule slippages
nor on the time of completion of the project. on activities of relatively long duration.
• The dependent relationships between activities cannot
When preparing a bar chart, the work effort must be divided adequately be shown; thus, it is difficult to determine
into components, which are then scheduled against time. how progress delays in individual activities affect proj-
Preparing a bar chart involves several steps: ect completion.
• Developing bar charts is essentially a manual, graphical
1. Analyze the program or project and specify the basic procedure, which makes them difficult to establish and
approach to be used in its execution. maintain for large projects; they also tend to become
2. Segment the program or project into a reasonable num- quickly outdated, thus diminishing their usefulness.
ber of activities that can be scheduled.
3. Estimate the time required to perform each activity. Many large and technically demanding undertakings, such
4. Place the activities in time order, considering both as developing weapons systems or constructing power
sequential and parallel performance. plants, require schedules showing thousands of activities
5. Adjust the diagram until the specified completion date, that take place in widely dispersed locations. Manually
if one exists, is satisfied. developed bar charts cannot adequately display this data,
and are thus unsuitable for anything other than a summary
Figure 13.1 below depicts a typical bar chart. display of information.
With today’s computer technology, however, if a network
13.2