Professional Documents
Culture Documents
GROUP 1
1. READY-MIXED CONCRETE
A ready-mixed concrete supply PAK, supplied Grade G25 concrete to the contractor EW for all
their structural works. Slump Tests and Cube Tests were successfully carried out for all
batches. However when cracks appeared in the completed slabs, structures and walls, EW
claimed that the ready-mixed concrete supplied did not comply with specifications and not fit for
purpose. EW refused to pay PAK. EW conducted Core Test on the structures and it failed. PAK
argued that the Core Test failed due to the contractor’s poor workmanship and not the quality
of the supplied concrete. But EW later implied that the slump and cube test had been
manipulated and there was fraud.
Should EW pay PAK since the structure did not pass the Core Test? Explain the reason for
your answer.
Ans:
EW shall not pay PAK since the structure did not pass the Core Test.
PAM 2006 : Clause 6.0 – Materials, Goods and Workmanship To Conform To Description,
Testing And Inspection.
• HELD: The court awarded in favour of PAK. To determine quality of concrete is Slump Test
and Cube Test. PAK is not liable for Core Test as this involve EW workmanship.
• There has never been any written protest from EW on allegation of fraud.
• HELD: High Court judge awarded in favour of YBK and held that KS had no right to
suspend work and YBK was not in breach in not honouring payment certificate.
Subsequently KS appeal.
• HELD: . Court of Appeal awarded in favour of KS. It held that the notice of termination by
YBK was unlawful since KS has the right to suspend works under PAM2006 and given
notice of suspension which was valid.