REFURBISH RAMP 9 KERATONG

Duration
Task Name Start Finish Workdone Claim (RM) Remarks
Day

Site Clearence 2 2022-11-30 2022-12-02

Ground Slab

Excavation 2 2022-12-03 2022-12-05 30% RM 31,863.60 Site Mobilization 30%

Fixing rebar 4 2022-12-06 2022-12-10


Formwork 3 2022-12-11 2022-12-14
Manual Concreting (No Supplier From any Ready Mix Batching
Ground Slab concreting 4 2022-12-15 2022-12-19
Plant)
Backfilling With Crusher Run 2 2022-12-20 2022-12-22
BRC at Slab 2 2022-12-23 2022-12-26
Manual Concreting (No Supplier From any Ready Mix Batching
Concrete Slab and Stoper Beam (Broom Finish) 3 2022-12-27 2022-12-30
Plant)
Walkway

Dismantling of Working Platform 5 2022-12-08 2022-12-13

Installation of Working Platform 5 2022-12-14 2022-12-19


Painting 3 2022-12-20 2022-12-23
Ramp Rust Remover
Door 1 5 2022-12-14 2022-12-19
Door 2 5 2022-12-20 2022-12-25
Painting 3 2022-12-26 2022-12-29 60% RM 31,863.60 Workdone 60%
Below Ramp Area
(Brick) Change to RC Beam 4 2022-12-30 2023-01-03 Will complete with item no *12
Base For H Beam 2 2023-01-03 2023-01-05
BRC at Slope 3 2023-01-06 2023-01-09
Manual Concreting (No Supplier From any Ready Mix Batching
Slope / Base Concreting 4 2023-01-10 2023-01-14
Plant)
Painting 3 2023-01-15 2023-01-18
Site Clearence 1 2023-01-19 2023-01-20
Handover 1 2023-01-21 2023-01-21 100% RM 37,174.20 Workdone 100%
CCC 6 Month 180 2023-07-20 2023-07-20 5% RM 5,310.60