APCO Infratech pvt ltd.,VADODARA Mumbai pkg-XIv 344.35065 0 458.79481 669.

95325 0
Daily Concrete Production Report All plant Material Consumption Details
TOTAL 192.50 66.29 0.00 88.32 128.97 0.00

Structu
Plant
re Quantit Cement flyash 10 MM 20 MM 25 MM
SL.No. Date Month Activitive Side Type of strutcture Locatio Grade
Loactio y Mt Mt Mt Mt Mt
n
n

1 30-11-2022 22-Nov 20+136 PCC RHS Flyover Interchange A1 Camp-1 M15 PCC 11 3.69 - 5.05 7.37 -

2 2/12/2022 22-Dec 20+136 PCC BHS Flyover Interchange Camp-1 M15 PCC 15 5.03 - 6.89 10.05 -

3 2/12/2022 22-Dec 19+365 PCC BHS SVUP Camp-1 M15 PCC 16 5.36 - 7.34 10.72 -

4 3/12/2022 22-Dec 19+365 PCC BHS SVUP Camp-1 M15 PCC 35 11.73 - 16.07 23.45 -

Base
5 3/12/2022 22-Dec Steel Yard - Steel Yard Camp-1 M20 PCC 2.5 0.88 - 1.15 1.68 -
Camp-1

6 4/12/2022 22-Dec 20+136 PCC BHS Flyover Interchange Camp-1 M15 PCC 21 7.04 - 9.64 14.07 -

Base
7 4/12/2022 22-Dec R/Wall - R/Wall Bridge Camp-1 M25 PCC 2.5 0.88 - 1.15 1.68 -
Camp-1
Base
8 5/12/2022 22-Dec Steel Yard - Steel stacking Camp-1 M20 PCC 3.5 1.23 - 1.61 2.35 -
Camp-1
Base
9 5/12/2022 22-Dec Plant - Silo Foundation Camp-1 M30 PCC 29 10.73 - 13.31 19.43 -
Camp-2

10 5/12/2022 22-Dec 20+136 PCC Flyover Camp-1 M15 PCC 6 2.01 - 2.75 4.02 -

Base
11 5/12/2022 22-Dec R/Wall - Weigh bridge Camp-1 M25 PCC 3 1.05 - 1.38 2.01 -
Camp-1

12 6/12/2022 22-Dec 20+136 PCC RHS Flyover Camp-1 M15PCC 10 3.35 - 4.59 6.7 -

Base
13 6/12/2022 22-Dec Foundation - Steel Foundation Camp-1 M20 PCC 5 1.75 - 2.295 3.35 -
Camp-1
Base
14 7/12/2022 22-Dec Stacking beam - Steel Yard Camp-1 M20 PCC 4 1.4 - 1.836 2.68 -
Camp-1
Base
15 7/12/2022 22-Dec Silo Foundation - Plant Foundation Camp-1 M40 RCC 3 1.32 - 1.323 1.986 -
Camp-2
Base
16 8/12/2022 22-Dec Steel Yard - Steel stacking Camp-1 M20 PCC 5 1.75 - 2.295 3.35 -
Camp-1

17 8/12/2022 22-Dec 18+421 PCC of foundation RP19 - MJB Camp-1 M15 PCC 7.5 2.5125 - 3.4425 5.025 -

18 8/12/2022 22-Dec Base Labour shed - Labour Shed Camp-1 M15 PCC 2 0.67 - 0.918 1.34 -
Camp-1
Base
19 9/12/2022 22-Dec Camp-1 Steel Yard - Steel stacking Camp-1 M20 PCC 3.5 1.225 - 1.6065 2.345 -

Base
20 9/12/2022 22-Dec Flooring PCC 6 Seater Camp-1 M15 PCC 6 2.01 - 2.754 4.02 -
Camp-1
Base
21 9/12/2022 22-Dec Labour shed - Labour Shed Camp-1 M15 PCC 2 0.67 - 0.918 1.34 -
Camp-1

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -
- -

- -

- -

- -

- -

- -

- -
679.37143 2.7205195
mption Details
130.78 523.70 0.00 0.00 0.00 0.00
ERP
Corrosi
Crystalli Structu
on Sub
M. sand Admixt 31.5 ne Supplie re/ Remark
Fiber Inhibito Cont. ERP Doc No
Packeg No
Mt ure Kg MM Mt durabili r Cost s
r (TTCI) Name
ty centre
KG
Name
7.46 29.48 - - - -

10.17 40.2 - - - -

10.85 42.88 - - - -

23.73 93.8 - - - -

1.7 6.7 - - - -

14.24 56.28 - - - -

1.7 6.7 - - - -

2.37 9.38 - - - -

19.66 77.72 - - - -

4.07 16.08 - - - -

2.03 8.04 - - - -

6.78 26.8 - - - -

3.39 13.4 - - - -

2.712 10.72 - - - -

2.289 15.84 - - - -

3.39 13.4 - - - -

5.085 20.1 - - - -

1.356 5.36 - - - -
2.373 9.38 - - - -

4.068 16.08 - - - -

1.356 5.36 - - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -