Annex-A

work started after


Date of Start of Date of removal of Overlapping Period, Net Period (in days) Weightage of Net effective days of
S. No. Nature of Hindrance mobilization of
Hindrance Hindrance If any of Hindrance Hindrance hindrance
workers

1 Building approval plan approval from Noida Authority 4/22/2022 9/22/2022 10/2/2022 0 163 55.82% 163

Ban on Construction in Delhi-NCR as per GRAP order


2 120017/27/GRAP/2021/CAQM/9709-9857 DT 10/29/2022 11/14/2022 11/24/2022 0 26 8.90% 26
29.10.22

Ban on Construction in Delhi-NCR as per GRAP order


3 12/4/2022 12/7/2022 12/17/2022 0 13 4.45% 13
120017/27/GRAP/2021/CAQM DT 04.12.22

Ban on Construction in Delhi-NCR as per GRAP order


4 120017/27/GRAP/2021/CAQM-530DT dated 12/30/2022 1/4/2023 0 5 1.71% 5
30.12.2022
Ban on Construction in Delhi-NCR as per GRAP order
5 120017/27/GRAP/2021/CAQM/11568-11707 dated 1/6/2023 1/15/2023 1/25/2023 0 19 6.51% 19
06.01.2023 dated 06.01.2023

Site was closed due to the visit of Hon'ble Home


6 8/18/2023 8/18/2023 8/28/2023 0 10 3.42% 10
Minister Shri Amit Shah at KRIBHCO on 18.08.2023

Ban on Construction in Delhi-NCR as per GRAP order


7 11/2/2023 11/28/2023 12/8/2023 0 36 12% 36
120017/27/GRAP/2021/CAQM DT 02.11.2023

Ban on Construction in Delhi-NCR as per GRAP order


8 120017/27/GRAP/2021/CAQM/2096-2249 DT 12/22/2023 1/1/2024 1/11/2024 0 20 7% 20
22.11.2023

Ban on Construction in Delhi-NCR as per GRAP order


9 1/14/2024
120017/27/GRAP/2021/CAQM DT 14.01.2024

Total days lost 292