Capacity Planning
Capacity Planning
PLANT LAYOUT
1. Functional Layout
2. Line Layout
3. Fixed-Position Layout
Lead time:
=1.50+0.75+1.00+0.50+2.00+2.75+2.00+1.00+2.00+2.50+
2.00 +1.75+0.50+2.00+1.50+1.00+1.00+1.50
=27.25
Cycle time:
= 2.75 minutes
Theoretical number of work
stations = 27.25/2.75
= 9.9 or 10