You are on page 1of 1

TESTING AND COMMISSIONING REPORT

Project Name : LA FALISIA COMPOUND

Project Location: MURAYKH

Building Type: Club house Level : First Floor Pages 1

System Type: Daikin Package Unit Date of Measure: 16th May 2019 Revision 0
Measuring
Air Flow: Air flow pitot tube meter Temperature: Thermometer Pressure Readings: Guage manifold set Current Reading: Clamp meter
Instrument:

Set Room Suction Liquid Air Flow Measurments


Current Rating Area Served
POWER RATING.IN Kw- Temp. Temp. Pressure Pressure Air Design Data (CFM) Actual Readings (CFM) Operating
Unit model
Ph/Hz/V Compressor Blower Terminal Total Total % Total Condition
Level Location
L1/L2/L3(A) L1/L2/L3 (A) (°C) (°C) (PSI) (PSI) Type T1 T2 T3 T4 Flow T1 T2 T3 T4 Flow Flow
Refreshment Area SLG 1500 1500 N/A N/A 3000 1400 1380 N/A N/A 2780 93 Cooling
Main Lobby / Lounge
SLG 1250 1250 500 N/A 3000 1180 1230 460 N/A 2870 96 Cooling
area
Adminstration Office SLG 500 N/A N/A N/A 500 500 N/A N/A N/A 500 100 Cooling
UATQ210CGXY1 21.34 Kw-3P/50/415 12.3/12.4/11.8 3.2/3.3/3.3 20 20 125 305 First Floor Female Toilets SCD 150 N/A N/A N/A 150 130 N/A N/A N/A 130 87 Cooling

Male Toilets SCD 150 N/A N/A N/A 150 140 N/A N/A N/A 140 93 Cooling

Preparation area SCD 200 N/A N/A N/A 200 185 N/A N/A N/A 185 93 Cooling

Kitchen SCD 150 N/A N/A N/A 150 142 N/A N/A N/A 142 95 Cooling
Multipurpose
UATQ180CGXY1 18.60 Kw-3P/50/415 9.6/10/9.8 3.1/3.2/3.2 20 20 130 320 First Floor SLG 1750 1750 1750 1750 7000 1690 1640 1700 1665 6695 96 Cooling
hall/Playing area
Total System Flow 14150 Total System Flow 13442

Reviewed and Acceptance by:


For Main Contractor Mep Contractor
Name

Signature