You are on page 1of 1

COMMISIONING REPORT-DX/Package

PROJECT VILLA NO. & TYPE


LOCATION REPORT DATE
CUSTOMER COMM. DATE

Equipment's Details Pre Commissioning Details


Location Total Pipe Length (m)
Outdoor/ Package Unit Model No. Vertical Pipe Length (m)
Outdoor / Package Unit Serial No. Nitrogen Pressure Test Readings for 24 Hours
Indoor Unit Model No. Leak Test Result ( OK / NG )
Indoor Unit Serial No. Vacuum of the System ( Yes / No )
Piping Connections (Liquid / Gas) Additional Gas Charge ( if applicable)
General Inspection Electrical Inspection
Ambient Temperature ( ̊C) Rated Voltage (V)
Supply Air Temperature ( ̊C) Actual Voltage (V)
Room Temperature ( ̊C) Rated Ampere (A)
Running Fan Speed ( H/M/L/Auto) Actual Ampere (A)
High Pressure Readings (PSIG) Electrical Cable Size
Low Pressure Readings (PSIG) Electrical Breaker Rating (A)
Ventilation Space for ODU(OK/NG)
Remarks

Thermostat Set Point = _____ ̊C

Tadmur -Seyana

SIGNATURE :

NAME :
DATE :
* By signing this Commissioning sheet, the contractor/installer certifies that the installation is based on Daikin Standard installation and practice. Daikin reserves the right
to void warranty in case there is any discrepancy on the information
* Field Electrical Safety components such as ELCB/RCCB are responsibility of the installer and should be installed to avoid risk of fire or human injury.

You might also like