Professional Documents
Culture Documents
The major components of an electric power system are shown in Figure 1.1.
Of these components, the distribution system has traditionally been char-
acterized as the most unglamorous component. In the latter half of the
20th century, the design and operation of the generation and transmission
components presented many challenges to the practicing engineers and
researchers. Power plants became larger, and transmission lines crisscrossed
the land, forming large interconnected networks. The operation of the large
interconnected networks required the development of new analysis and
operational techniques. Meanwhile, the distribution systems continued to
deliver power to the ultimate user’s meter with little or no analysis. As a
direct result, distribution systems were typically over-designed.
Nowadays, it has become very important and necessary to operate a dis-
tribution system at its maximum capacity. Some of the questions that need to
be answered are as follows:
1
2 Distribution System Modeling and Analysis
Interconnected
Bulk power Subtransmission Distribution Primary
Generation transmission
substation network substation feeders
system
FIGURE 1.1
Major power system components.
1.
High-side and low-side switching: In Figure 1.2, the high-voltage
switching is done with a simple switch. Substations that are more
extensive may use high-voltage circuit breakers (CBs) in a variety of
high-voltage bus designs. The low-voltage switching in Figure 1.2
is accomplished with relay-controlled CBs. In many cases, reclosers
will be used in place of the relay–CB combination. Some substation
designs include a low-voltage bus CB in addition to the CBs for each
feeder. As is the case with the high-voltage bus, the low-voltage bus
can take on a variety of designs.
2.
Voltage transformation: The primary function of a distribution substa-
tion is to reduce the voltage down to the distribution voltage level. In
Figure 1.2, only one transformer is shown. Other substation designs
will call for two or more three-phase transformers. The substation
transformers can be three-phase units or three single-phase units
connected in a standard connection. There are many “standard” dis-
tribution voltage levels. Some of the common ones are 34.5, 23.9, 14.4,
13.2, 12.47 kV, and, in older systems, 4.16 kV.
3.
Voltage regulation: Because the load on the feeders vary, the voltage
drop between the substation and the user will vary. In order to
maintain the user’s voltages within an acceptable range, the voltage
Introduction to Distribution Systems 3
Subtransmission line
Disconnect switch
Fuse
Transformer
Voltage regulator
Meters
Circuit breakers
Primary feeders
FIGURE 1.2
Simple distribution substation.
at the substation needs to vary as the load varies. In Figure 1.2, the
voltage is regulated by a “step-type” regulator that will vary the
voltage plus or minus 10% on the low-side bus. Sometimes this func-
tion is accomplished with a “load tap changing” (LTC) transformer.
The LTC changes the taps on the low-voltage windings of the trans-
former as the load varies. Many substation transformers will have
“fixed taps” on the high-voltage winding. These are used when the
source voltage is always either above or below the nominal voltage.
The fixed tap settings can vary the voltage plus or minus 5%. Mostly,
instead of a bus regulator, each feeder will have its own regulator.
This can be in the form of a three-phase gang-operated regulator or
individual phase regulators that operate independently.
4.
Protection: The substation must be protected against the occurrence
of short circuits. In the simple design in Figure 1.2, the only auto-
matic protection against short circuits inside the substation is by way
of the high-side fuses on the transformer. As the substation designs
become more complex, more extensive protective schemes will be
employed to protect the transformer, the high- and low-voltage
buses, and any other piece of equipment. Individual feeder CBs or
reclosers are used to provide interruption of short circuits that occur
outside the substation.
5.
Metering: Every substation has some form of metering. This may be
as simple as an analog ammeter displaying the present value of sub-
station current as well as the minimum and maximum currents that
have occurred over a specific time period. Digital recording meters
4 Distribution System Modeling and Analysis
With the breakers in their normal positions, each transformer is served from
a different subtransmission line and serves two feeders. If one of the sub-
transmission lines goes out of service, then breaker X or Y is opened and
breaker Z is closed. Now both transformers are served from the same sub-
transmission line. The transformers are sized such that each transformer
can supply all four feeders under an emergency operating condition. For
example, if transformer T-1 is out of service, then breakers X, 1, and 4 are
opened and breakers 2 and 5 are closed. With that breaker arrangement, all
Line 1
Line 2
X N.C. N.C. Y
N.O.
T-1 T-2
1 2 3
FD-2 FD-4
FIGURE 1.3
Two-transformer substation with breaker and a half scheme.
Introduction to Distribution Systems 5
four feeders are served by transformer T-2. The low-voltage bus arrangement
is referred to as a “breaker and a half scheme,” because three breakers are
required to serve two feeders.
There is an unlimited number of substation configurations possible. It is
up to the substation design engineer to create a design that provides the five
basic functions and provides the most reliable service economically possible.
Fuse
Substation
Transformer
Voltage regulator
Circuit breaker
Single-phase lateral
Node
“V” phase lateral
b b
c c
a a
Three-phase lateral
c
b b Capacitor bank
c
Underground cables ab c Fuse
b Distribution
transformer
c
b
a
Secondary
Customers
In-line transformer
FIGURE 1.4
Simple distribution feeder.
800′ 67 5′
25 475′ 25
50
50
325′ 50
50 c
275′ 25 0′ 25
400′ 50 a c 250′ 50
c
300′ 25 225′ 17 5 ′ a
50 475′ a 50
325′ 50 c
50 b b b
a c 100′
50 b 50 350′
b
700′ 50
525′ ′ ac b
275′ 700
400′ 0
50 0 b 25
550' 3–1
50 275′
25 ′
50 a c 200 450′
bc 200′
′
25 50 a 275 b
575′ a
325′ 0′ 50
300′ 25 M
275′ a
c 1 75 ′ a
25 275′
50 b 50
c ′ 3–50
50 225′ 250 350′
3-Phase OH
a
3-Phase UG
′
500 2-Phase OH
50 1-Phase OH
Voltage regulator
FIGURE 1.5
IEEE 123 node test feeder.
8 Distribution System Modeling and Analysis
c. Details
i. Conductor sizes (not on this map)
ii. Phasing
2. Distribution transformers
a. Location
b. kVA rating
c. Phase connection
3. In-line transformers
a. Location
b. kVA rating
c. Connection
4. Shunt capacitors
a. Location
b. kvar rating
c. Phase connection
5. Voltage regulators
a. Location
b. Phase connection
c. Type (not shown on this map)
i. Single-phase
ii. Three-phase
6. Switches
a. Location
b. Normal open/close status
1.5 D
istribution Feeder Electrical Characteristics
Information from the map will define the physical location of the vari-
ous devices. Electrical characteristics for each device will have to be
determined before the analysis of the feeder can commence. In order
to determine the electrical characteristics, the following data must be
available:
b. Diameter (in.)
c. Resistance (Ω/mile)
3. Voltage regulators
a. Potential transformer ratios
b. Current transformer ratios
c. Compensator settings
i. Voltage level
ii. Bandwidth
iii. R and X settings in volts
4. Transformers
a. kVA rating
b. Voltage ratings
c. Impedance (R and X)
d. No-load power loss
1.6 Summary
As the smart grid [1] becomes a reality, it becomes increasingly more important
to be able to accurately model and analyze each component of a distribution
system. There are many different substation designs possible; however, for the
most part, the substation serves one or more radial feeders. Each component of
a feeder must be modeled as accurately as possible in order for the analysis to
have meaning. Sometimes the most difficult task for the engineer is to acquire
all of the necessary data. Feeder maps will contain most of the needed data.
Additional data such as standard pole configurations, specific conductors used
on each line segment, phasing, three-phase transformer connections, and volt-
age regulator settings must come from stored records. The remaining bits of
information are the values of the loads. Chapter 2 will address the loads in a
general sense. Again, when the smart grid, along with smart meters, becomes
a reality, the load values will become much more accurate, which in turn will
make the analysis more accurate. Once all of the data have been acquired, the
analysis can commence by utilizing system models of the various devices that
will be developed in later chapters.
Reference
1.
Thomas, M. S. and McDonald, J. D., Power System SCADA and Smart Grids, CRC
Press, Boca Raton, FL, 2015.