TCD - 033 INV V-phase IGBT Error(DI4,5) Application


Detection ● Speed CPU ● DI4,5

[Meaning] [Actions to take]


1. Check the VG connector status of DPC-300(INV) PCB with power OFF.
When V-phase +IGBT and -IGBT are turned on simultaneously, or when IGBT driving
power has failed or INV output(U, V, W) is short. 2. Verify that the optical cable is well connected to stack section such as
U+,U-,V+,V-,W+,W- , respectively.
[Diagram] 3. Check the VA, GX, GAI, and GCI connectors in DPP-300(GDC) PCB.
4. Verify if GAI and GBI cable are well connected to FG PCB of
V Stack
GX3
GP1 U-phase IGBT.
DPP-300 GX5 AC 29V

GAI7 5. Check the U-phase power(Verify if the voltage is AC29V between


GET-E18
GAI4 U-phase stack GX3 to 5 in DPP-300 PCB, and AC29V between
U GCI7
6 7 GX1
IM V GCI4
GX4 AC 29V
GX1 and 4(If power is not correct, replace the transformer. Yet, in
GET-E18
W GAI5
6
7
permissible voltage dropping range.)
GAI1
6. Verify if HCT cable is well connected to HCT(Verify if U-phase cable is
GCI5
GCI1
connected to U-phase HCT and V-phase and W-phase in the same way ).
VA1 VA5 INV+ INV-
7. Check the HCT’s direction(Normally, HCT is directed downward to CP
광케이블
Optical Cable
VBN-3
floor.) (Refer to TCD30.)
VG4 VG13 U+ U- V+ V- W+ W-
VBN-7
OPT1 8. Inspect IGBT.
VBN-11 DPC-300 9. Replace DPP-300(GDC) PCB.
10. Replace DPC-300(INV) PCB.
[How to inspect IGBT]
Be sure to open the resistance of FG PCB attached to IGBT before
inspection.

Condition + - Analog Tester Digital Tester


C1-C2E1 C2E1 G ∞ ∞
Short G C2E1 ∞ ∞
G-C2E1 C2E1 C1 ∞ Around 10k Ω
Short C1 C2E1 10 Ω or less ∞
C2E1-E2 E2 G ∞ ∞
Short G E2 ∞ ∞
G-E2 E2 C2E1 ∞ Around 10k Ω
Short C2E1 E2 10 Ω or less ∞