Professional Documents
Culture Documents
PROJECT REPORT
ON
BY
ANIKET CHAUDHARI
AAKASH BORUDE
SANJOG GAWADE
NEIL FERNANDES
DR. A.P.PANDHARE
2014 – 2015
CERTIFICATE
This project would not have been possible without the support and help of
many individuals and organizations. We would like to extend our sincere thanks
to all of them.
Also we would like to thank our project guide Prof. Amar Pandhare,
Smt.Kashibai Navale College of Engineering, Pune for his constant encouragement
and valuable guidance during the course of this work.
We also thank and appreciate our colleagues for help with few aspects of the
project and people who have willingly helped us out with their abilities.
ABSTRACT
In this Project we deal with the Design & Analysis of turbo generator for Fuzes
used in missiles. This is a new technology in which power is generated within the
warhead fuze. The projectiles have been powered by storage batteries traditionally.
But due to number of drawbacks of these storage batteries such as short life, leakage,
fire hazard, etc., a new technology was required which overcame these shortcomings.
Deep research was carried out, which resulted in the development of wind driven
turbo generator that could fit inside the fuze ogive.
The advantages of such a power source were long life, nonhazardous storage &
greater reliability. So, it has become the most preferred choice for use in artillery
munitions etc.
Very few countries such as US & Israel have been able to successfully develop
& use this technology. India is also trying to develop it for it’s obvious advantages.
Turbo generator consists of a turbine impeller mounted on a shaft. High velocity
air rotates the impeller, which rotates the shaft. A multi-pole permanent magnet rotor
is mounted on shaft, which is made to rotate at 10,000 to 15,000 rpm. The PM rotor
comprises the field winding of the alternator whose stator coil or armature is fixed to
the casing. The alternator functions according to Faraday’s Law of Electromagnetic
Induction; the rotating magnetic field/flux produces an emf in the stator coil, which is
used to power Fuze electronics.
This project report includes broad information about the turbo generator
construction and working, along with detailed design of the turbo generator and
analysis of the critical components.
Table of Contents Page No.
1.1 Introduction 1
1.1.1 Types of Fuzes 1
1.1.2 Alternate power sources 3
1.1.2.1 Fluidic generator 3
1.1.2.2 Reserve battery 4
1.1.2.3 Thermoelectric power supply 4
1.1.2.4 Thermal battery 4
1.1.2.5 Piezoelectric power supply 5
1.1.3 Turbo-generator 5
1.7 Results 41
1.8 Documentation 42
1.9 Conclusion 56
Assembly
Component 3: Rotor 9
Component 6: Shaft 11
1.1.1 Fuze:
1
b) Impact fuzes :
Impact or contact fuzes detonate when their forward motion rapidly decreases,
typically on physically striking an object such as the target. An instantaneous
"Superquick" fuze will detonate instantly on the slightest physical contact with the
target. A fuze with a graze action will also detonate on change of direction caused by
a slight glancing blow on a physical obstruction such as the ground. Impact fuzes in
artillery usage may be mounted in the shell nose ("point detonating") or shell base
("base detonating").
c) Proximity fuzes :
Proximity fuzes cause a missile warhead or other munition to detonate when it
comes within a certain pre-set distance of the target, or vice versa. Proximity fuzes
utilize sensors incorporating one or more combinations of the following: radar,
active sonar, passive acoustic, infrared, magnetic, photoelectric, seismic or
even television cameras.
d) Remote detonators :
Remote detonators use wires or radio waves to remotely command the device
to detonate Barometric fuzes cause a bomb to detonate at a certain pre-set altitude
above sea level by means of a radar, barometric altimeter or an infrared range finder.
2
The main components that make up a fuze are:
1. Electronic circuitry to initiate warhead,
2. Power supply for the electronic circuit,
3. Safe & arm unit
4. Detonator & lead charge.
The power supply unit is a very critical component of a fuze. It fulfils the power
requirements of the electronic circuit, which controls the warhead detonation.
3
causes the metallic reed to bang against the pole pieces. This leads to reel fatigue and
eventual failure, causing power loss.
4
1.1.2.4 Thermal battery :
Setback forces, which are generated when the round is fired, produce the
electric energy. A fuzed salt is released on setback, which subsequently causes an
electrical charge to be generated between two electrodes. This charge is stored in a
capacitor and used to set off the detonator upon of the warhead.
Drawback:
Requires a considerable volume of space, necessitating minimization of the
amount of explosive for a given warhead size. It also increases the weight of warhead.
1.1.3 Turbo-generator:
It comprises an electric generator assembly housed within a projectile. The
assembly includes an air driven turbine and an electric generator. A common shaft
carries the turbine and the permanent magnet of the electric generator. The generator
rotor is a small permanent magnet and the stator a series of coils. The principle of
power generation is similar to the wind turbine-generator unit except that the turbo-
generator assembly is very compact and operates at substantial rotational speed.
The impellers used in prior art electrical generators were very inefficient in that
most of the air taken in by the turbine is diverted rather than used to drive the
impeller.
The prior art turbines were placed outside the fuze resulting in increased size of the
projectile. The new developments in the case of the turbo-generator have resulted in
5
reducing the size of the fuze by incorporating the unit inside the fuze. The next
generation turbo-generator power supply makes use of an efficient turbine (centrifugal
unit). The next generation turbo-generator has improved dynamic balance than the
prior art generators. Since it has a life span equal to that of the whole fuze, and other
advantages as mentioned above, it has turned out to be the choice for the next
generation electronic fuze.
1.2.1 Turbine:
Includes a cylindrical centrifugal impeller having a plurality of vanes. The
vanes are of air foil shape. Each vane is oriented at an angle to a radius of the
impeller. The vanes are uniformly spaced around the periphery of the impeller and are
separated by air conduits terminating in centrifugal discharge apertures from which
air leaves the impeller. The flow of air through the impeller imparts rotational motion
to the impeller, which drives the turbine.
6
magnet. Magnetic flux paths are provided between the rotating magnet and the coil
housing by an inner armature member and an outer armature member. In operation,
the rotating magnet creates a rotating magnetic field, which is conducted through the
armature members to the coil wherein it generates an electric current.
1.2.3 Shaft:
The turbine also includes a generally cylindrical elongated shaft member or
shaft preferably formed from a high strength material such as steel. The shaft carries
the abovementioned members.
Wind turbines operate on a simple principle. The energy in the wind turns two
or three propeller-like blades around a rotor. The rotor is connected to the main shaft,
which spins a generator to create electricity
• The wind stream in flight provides both the mechanical power needed to arm the
Safety & Arming (S&A) and the electrical power needed for the fuze electronics.
• In this system, the Air Inlet directs the wind stream into a converging-diverging
nozzle (Venturi tube) that limits the mass flow rate (choked flow).
• The axial flow then rams the center of a flat impeller and flows radially through the
blades. The curvature of the blades continuously redirects the flow and the net
pressure on the concave surface area generates a torque that rotates a drive shaft.
• The drive shaft is also engaged with the S&A mechanism at the time of launch, but
disengages after a specific number of shaft revolutions. This action unscrews a
Jackscrew locking device and enables the explosive train to snap into alignment,
thereby completing the second step in mechanical arming.
7
Figure 3: Next Generation Proximity Fuze
8
Component 2: Sectional view of Turbo-generator assembly.
Component 3: Rotor
9
Component 4: Cover Plate
10
Component 6: Shaft
11
Component 6: Housing
12
Component 8: PCB Assembly
13
Comp No. Nomenclature
1. Rotor
2. Cover Plate
3. Housing
4. Washer
5. Thrust Ball Bearing
6. Foam Disc
7. Shaft and Magnet assy
8. Stamping Plate Assy
9. Bobbin Assy
10. Coil Assy
11. PCB Assy.
14
Component 12: Cut section of Air-intake valve
15
Component 14: Valve Housing
16
Component 16: Valve Plunger
17
Component 18: Adapter
18
1.4. ASSEMBLY PROCEDURE
1.4.1 Sub-Assemblies:
a) Bobbin Assembly :
Parts required :
i. Bobbin
ii. Enamelled copper wire
Procedure:
19
b) Stamping plate Assembly:
Parts required :
i. Bobbin Assembly
ii. Stamping plates
iii. Rivet
iv. Connecting wire
v. Glass epoxy sheet
Procedure:
20
c) Shaft & Magnet Assembly :
Parts required:
i. Shaft
ii. Magnet
iii. In-situ moulding
Procedure:
Place
21
d) PCB Assembly :
Parts required:
i. PCB
ii. Strip
iii. Terminal pin
iv. Body
v. Holder
Procedure:
22
1.4.2 Main Assembly :
Parts required:
i. Washer
ii. Bearing
iii. Housing
iv. Cover plate
v. Rotor
vi. Foam disc
vii. PCB Assembly
viii Shaft & magnet Assembly
ix. Stamping plate Assembly
Procedure:
23
1.4.3 Air-intake valve Assembly:
Parts required:
i. Air-intake tube
ii. Valve housing
iii. ‘O’ Ring ‘A’
iv. ‘O’ Ring ‘B’
v. Air flow body
vi. Valve plunger
vii. Spring
viii. Valve body
ix. Locking spring washer
x. Ring ebonite
xi. Ring washer
xii. Adapter
Procedure:
24
1.5. TEST PLAN FOR TURBO-GENERATOR
1.5.1 Introduction :
An air-driven power supply has been developed for fuze for Mortars that
converts the ram-air energy available to a projectile in flight into electrical energy to
power the fuze. This power supply also furnishes an arming signature based on
projectile velocity.
The basic features of several alternator designs are discussed, including the
means of achieving various power levels, reducing alternator size, limiting rotational
speed, attaining velocity discrimination, and using improved magnetic materials.
Initial tests of this device with other fuze components showed that rotational
speed reduction and proper bearing lubrication were needed in order to achieve
successful field-test results. These studies are discussed in this report, which also
gives the characteristics of the alternator with these improvements.
To further reduce the cost of the alternator in production, a new design was
developed that incorporated cheaper bearings instead of costly miniature precision
bearings and eliminated machined parts.
For this reason, the portion of the trajectory over which the power supply is
required to function must be specified. For the concept-feasibility design it was
necessary to demonstrate that the generator produced the required power when fired at
the lowest charge, and that it could initiate during descent when fired at the steepest
angle of elevation (85°). Hence, the turbine must start at a threshold velocity of about
120" ft/sec or lower, so that the generator can provide power to the fuzing system.
The generator must supply electrical power to the fuzing circuit and also
provide a mechanical output from the generator shaft to the safing and arming (S&A)
system. For the mechanical output the spinning shaft drives a gear reduction system
that aligns the firing pin with the detonator at a specified safe distance from the gun.
25
The requirements for the power supply are:
i. It must generate 0.600W with a 600-Ω load at flight velocities varying from
150 ft/sec to about 850ft/s.
ii. It must fit into a space no greater than 1 cu in.
iii. It must retain its integrity when spinning at velocities greater than 100, 000
rpm for at least 40 sec.
iv. It must be simple to manufacture and to assemble.
v. If the alternator stops during the low-velocity phase of the flight, it must
restart during the high-velocity phase in time to power a fuze,
vi. The fuze drag must not adversely affect the range and stability of the round.
vii. The alternator must have a long storage life and be rugged enough to
withstand the gun environment.
viii. It must not be adversely affected by flight through rain.
26
Figure 4: Laboratory test arrangement for measuring operating characteristics
The test item with instrumentation for these tests is shown in figure 1.
Regulated air from a settling chamber enters directly into the inlet of a fuze ogive,
which houses the T/A. The output frequency of the T/A is measured across a 600-ohm
resistor. Stagnation pressure in the settling chamber is monitored with a strain-gage
pressure transducer. Alternator frequency versus inlet stagnation pressure is then
recorded on an X-Y recorder. The turbine rotational speed may be obtained directly
from the alternator frequency by multiplying the alternator frequency by 20.
This turbine was tested over the required operating temperature range (-60°to
160°F, -51 to 71°C). Figure 2 shows the instrumentation preconditioning coils were
located within a temperature conditioning chamber. For these tests, dry nitrogen was
used as the working fluid. The nitrogen is temperature conditioned as it passes
through the copper coils to the T/A, so that its temperature is nearly identical to the
conditioning chamber temperature when it enters the T/A inlet.
27
Figure 5: Experimental arrangement for studying effect of temperature on alternator output
When conducting these tests, the test unit is temperature conditioned for a
minimum of two hours; then the inlet pressure to the T/A is set to correspond to the
expected maximum flight velocity. The unit is then operated at this pressure for 60 s,
and its frequency is recorded as a function of inlet pressure. Each unit is tested at
temperatures of -60, 70, and 160 F (-51, 21, and 71°C). Although turbine speeds at a
given inlet pressure varies with temperature, the power delivered at the temperature
extremes is sufficient to operate the fuze.
28
on cold-temperature T/A operation. Three methods of bearing lubrication were
investigated to identify whether or not bearing lubrication contributed to the arming
problem, and to select an alternate method of lubricating the bearings if necessary.
The three lubrication methods investigated consisted of
a. soaking the bearings in oil (as supplied by the manufacturer)
b. lubricating the bearings with a film of Anderoil 501, obtained by dipping bearings
in a 96-percent Freon, 4-percent Anderoil 501 mixture
c. removing all lubrication so that the bearings were dry
Test units were assembled with bearings lubricated as described, and start-up
characteristics were obtained, employing the instrumentation as shown in figure 3.
Starting characteristics of the T/A were generated by first setting the inlet
pressure while maintaining the rotor stationary. The rotor was then released and
allowed to rotate, and the turbine speed was monitored as a function of time.
The previous method of lubrication adversely affected arming time, and an
improved lubrication method was needed.
The two alternate lubrication methods were further investigated. This
investigation consisted of subjecting four samples of T/A's assembled with bearings
lubricated with 4-percent Ander oil 501 and 96- percent Freon, and four test samples
of T/A's assembled with dry bearings to the testing procedure specified for turbine
validation in section 3.
29
This test procedure consisted of pre-temperature-conditioning each unit at -60,
70, and 160 F (-51, 21, and 71°C) and then operating the unit at each conditioned
temperature for 60 s. The inlet pressure to the unit for each run was set to correspond
to the expected maximum flight velocity at that temperature. Alternator frequency
was recorded as a function of inlet pressure for each run. If each unit's performance
was not degraded as a result of these tests, then the probability of a similar unit
performing adequately during actual flight environments would be very high. All
samples exhibited satisfactory performance based on these tests. Bearing lubrication
with 4-percent Ander oil 501 and 96-percent Freon was selected for the XM734 T/A.
This light film lubrication is considered sufficient to protect the bearings during
storage. The increase in alternator start-up time at -40°F (-40°C) with this method of
lubrication was considered acceptable.
b) Test Hardware :
For the rain test, each alternator was housed in a fuze ogive having an entrance
port 0.380 in. in diameter and rectangular exit ports (0.500 in.x 0.130 in.) uniformly
spaced around the circumference. The entrance and exit ports were completely open
to simulate firing from a mortar. To monitor the alternator output during the sled run,
a special circuit was designed that would reduce the rectified alternator output by a
factor of 20 and supply 0 to 7 V de, the voltage limit of the telemetry system. The
30
circuits shown in figure 9. All alternators were mounted in fuze ogives and tested in
the laboratory.
Pressures corresponding to the flight velocity expected in a sled were supplied
to the alternators and the output voltage was recorded. The alternators were also
checked when mounted on the sled, to ensure that the telemetry recording equipment
was operating properly. Laboratory tests were conducted after the device had flown in
the rain to determine any damage to the alternator parts from passage through the rain
field.
c) Tests :
The Holloman test track is 37, 000 ft long, and the , rain-field section of the
track extends over some 2000 ft. Rain was simulated by forming water through a
series of nozzles on both sides of the track. The entry and exit points of the sled in the
rain field were located 25, 032 and 23, 032 ft from the end of the track, respectively.
Weather stations, located in the rain section of the track at intervals of approximately
1000 ft, provided information about wind speed and direction, the velocity of the sled
during the test was measured every 200 ft along the full length of the track. The
telemetered output of the alternators was recorded at a ground station on oscillograph
charts and on magnetic tapes. The time of entry and time of exit of the sled from the
rain field was marked on the oscillograph charts and magnetic tapes.
31
1.6 DESIGN CALCULATION:
a) Structural Analysis:
The total forces acting on the shaft can be categorized into 2 groups:
i) Direct forces: generated due to the weights of the individual components.
ii) Shear forces: due to the torque generated by rotation of turbine.
i) Direct forces:
Assuming the weights of the individual components acting at their individual centre
of gravity, the FBD can be represented as:
Cover
Magnet & In-
plate Washer
situ
Turbine Washer Bearing Moulding Bearing Housing
32
Sr.No Component Material Volume[3] Mass Weight
. Name Density (m3) (kg) (N)
(kg/m3)
1. Turbine 1140[4] 6.978*10-7 7.9549*10-4 7.8037*10-3
2. Washer 8450[8] 1.178*10-8 9.9541*10-5 9.7649*10-4
3. Cover plate 2770[5] 1.438*10-8 3.9833*10-3 0.03907
4. Magnet 6900[6] 5.223*10-7 3.6038*10-3 0.03539
5. In-situ 1140[4] 1.169*10-7 1.3326*10-4 1.3073*10-3
Moulding
6. Housing 2770[5] 4.869*10-6 0.013487 0.1323
For turbine the starting Torque value of the impeller is kept as low as possible
so that it can start early and most importantly can work at higher Altitudes (~30 km)
where atmospheric density drops to nearly 1.5% of MSL value and projectile speed is
least of the trajectory. From the graph obtained during testing of the Turbo-generator
we observe that the starting and hence the running pressure of the turbine can be
accounted close to 1 bar.
33
Figure 7: Pressure availability curve above Stop Pressure line means continuous operation during full
projectile flight path.
The above 2 forces are used to do a detailed analysis in ANSYS. The results are
obtained as:
34
Figure 8: Von-Mises Stress
35
Therefore from the above results it is seen that the equivalent stress is
104.09MPa<122.Mpa.
By using Von-Mises stress criterion the design is safe.
b) Vibration analysis:
The angular speed corresponding to the first node is given by: ω = (g/δ) 0.5,
Where:
g=gravitational acceleration=9.81 (m/s2)
δ=total deformation (m) =1.4746*10-6 (m)
ω= angular speed (rad/s)
ω= (9.81/1.4746*10-6)0.5 =2579.273 rad/s.
N=60* ω/(2*π)=24630.247 rpm.
Thus to avoid the sudden failure of shaft due to node formation the speed of 24630
rpm must be avoided which is observed during the projectile speed of 580-620 m/s.
36
1.6.3. Calculations :
When the projectile travels through the atmosphere at supersonic speeds, it sets
up a normal shock wave in front of it. The air pressure just in front of the projectile
and air entering in inlet is represented by P2. At subsonic speeds no shock wave is
formed & air pressure just in front of the projectile and air entering in inlet is equal to
P1.During supersonic operation the generator, inside the projectile ogive, is exposed
to a total pressure at the ogive air inlet equal to P2. Pressure P2 is determined by the
flight Mach number and altitude expressed by the equation:
Where:
P2 = free stream static pressure at a given flight altitude;
M=projectile velocity expressed in terms of the local Mach number;
k =1.4 (k is the ratio of specific heat capacities for air).
For a given flight Mach number and altitude, the corresponding pressures of P2
and P1 determine the amount of ram air mass flow that enters the generator, and thus
the amount of electrical energy generated.
Since the missile behaves like a projectile the missile will attain its maximum
velocity at the launch where P1 will be atmospheric pressure. Considering standard
atmospheric conditions from ISA chart we have:
Pressure=1.01325 bar
Temperature: 288.15K
Density of air= 1.225
Speed of sound=340.294 m/s.
The projectile with the increasing velocity and pressure build up at the launch will
also experience a temperature rise which is given by the equation :
37
Using the above 2 equations we obtain the values of turbine rpm and pressure
experienced by turbine and temperature rise is given in tabulated from as:
The above parameters are used to carry a detailed analysis of the turbine in ANSYS.
From the above results it can be seen that the maximum stresses obtained are for 700
m/s. Hence the results are shown for this value:
38
Figure 11: Von- Mises Stress
39
Figure 13: Total Deformation
From the above results the maximum principal stress and the von-mises stress
(4.7e7, 6.3e7)<9e07
Hence the design is safe
40
Material Maximum Residual Coercive Working
Energy Flux Force Temperature
Product Density Hc(Koe) °C
Bhmax Br(G)
(MGOe)
Ceramic 5 3.4 3950 2400 400
1.7 RESULTS :
The results of the analysis done in ANSYS are obtained as follows:
41
b) The maximum principal stress and the von-mises stress
(4.7e7,6.3e7)Pa<9e07Pa
Hence the design is safe
1.8 Documentation :
Production documentation is the organised collection of records that describe the
structure, purpose, operation, maintenance, and data requirements for easy and
efficient communication between designer and manufacturer. Following figures show
some features of Production Document.
42
43
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION
CLASS TO IS:2102 CONFORM AS PER JSG:0104
DIMS IN mm UNLESS
OTHERWISE STATED.
COMP. DESCRIPTION
NO
1 ROTOR
2 COVER PLATE
3 HOUSING
4 WASHER
5 THRUST BALL
BEARING
6 FOAM DISC
7 SHAFT AND
MAGNET ASSEMBLY
8 STAMPING PLATE
ASSEMBLY
9 BOBIN ASSEMBLY
10 COIL ASSEMBLY
11 PCB ASSEMBLY
APPROVED BY MATERIAL:
PROTECTIVE FINISH:
(Dr. Virendra Kumar)
Scientist ‘F’
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN TURBO GENERATOR
AUTHORITY: ASSEMBLY
ARDE
44
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm
UNLESS OTHERWISE STATED.
APPROVED BY MATERIAL:
NYLON 66 TO SPEC IS:13464
PROTECTIVE FINISH:
ARDE
DRG. NO.
45
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm
UNLESS OTHERWISE STATED.
APPROVED BY MATERIAL:
AL ALLOY TO SPEC IS:733-
24345 WP
PROTECTIVE FINISH:
(Dr. Virendra Kumar) TO BE ANODIZED TO SPEC
Scientist ‘F’ IS:1868 Gd AC 10
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN COVER PLATE
AUTHORITY:
ARDE
DRG. NO.
46
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm
UNLESS OTHERWISE STATED.
APPROVED BY MATERIAL:
AL ALLOY TO SPEC IS:733-
24345 WP
PROTECTIVE FINISH:
(Dr. Virendra Kumar) TO BE ANODIZED TO SPEC
Scientist ‘F’ IS:1868 Gd AC 10
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN HOUSING
AUTHORITY:
ARDE
DRG. NO.
47
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm
UNLESS OTHERWISE STATED.
APPROVED BY MATERIAL:
BRASS TO SPEC IS 319 Gd 1
HALF HARD
PROTECTIVE FINISH:
(Dr. Virendra Kumar) TO BE CROMATE
Scientist ‘F’ PASSIVATED TO SPEC IS:1340
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN WASHER
AUTHORITY:
ARDE
DRG. NO.
48
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm
UNLESS OTHERWISE STATED.
APPROVED BY MATERIAL:
PROTECTIVE FINISH:
ARDE
49
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm UNLESS
OTHERWISE STATED.
APPROVED BY MATERIAL:
PROTECTIVE FINISH:
ARDE
DRG. NO.
50
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION
CLASS TO IS:2102 CONFORM AS PER JSG:0104
DIMS IN mm UNLESS
OTHERWISE STATED.
APPROVED BY MATERIAL:
PROTECTIVE FINISH:
(Dr. Virendra Kumar)
Scientist ‘F’
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN SHAFT AND MAGNET
AUTHORITY: ASSEMBLY
ARDE
51
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm
UNLESS OTHERWISE STATED.
APPROVED BY MATERIAL:
STAINLESS STEEL Gd 304S15
TO B.S. 970
PROTECTIVE FINISH:
(Dr. Virendra Kumar) NOT REQUIRED
Scientist F
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN AUTHORITY: SHAFT
ARDE
PART NO. DS CAT NO. AHSP
52
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION CONFORM
CLASS TO IS:2102 AS PER JSG:0104 DIMS IN mm
UNLESS OTHERWISE STATED.
APPROVED BY MATERIAL:
ALNICO-5
ALLOY MAGNETIC
MATERIAL
(Dr. Virendra Kumar) PROTECTIVE FINISH:
Scientist ‘F’
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN MAGNET
AUTHORITY:
ARDE
53
GEN.TOL.MEDIUM/COARSE/FINE DRAWING CONVENTION COMP.N DESCRIPTION QTY
CLASS CONFORM AS PER JSG:0104 O
1 GLASS EPOXY SHEET 2
TO IS:2102 DIMS IN mm UNLESS
2 CONNECTING WIRE 2
OTHERWISE STATED.
3 STAMPING PLATE ASSY 1
4 BOBIN ASSY 4
5 INSITU MOULDING ON COIL ASSY 1
NOTE:- A PIECE OF COPPE
APPROVED BY MATERIAL:
PROTECTIVE FINISH:
ARDE
54
GEN.TOL.MEDIUM/COARSE/FINE CLASS DRAWING CONVENTION
TO IS:2102 CONFORM AS PER JSG:0104 DIMS
IN mm UNLESS OTHERWISE
STATED.
COMP. DESCRIPTION QT
NO Y
1 PCB 1
2 STRIP 1
3 TERMINAL PIN 1
4 BODY 1
5 HOLDER 1
APPROVED BY MATERIAL:
AMSI Gd FR4 TO
SPECN
DS:7409-1990
(Dr. Virendra Kumar) PROTECTIVE FINISH:
Scientist ‘F’ GLASS EPOXY
FOR DIRECTOR
SCALE: EST. MASS TITLE:
1:1
DESIGN PCB ASSEMBLY
AUTHORITY:
ARDE
55
1.9 CONCLUSION :
56
1.10 FUTURE SCOPE :
This report contains information about the turbo-generator currently in use, and
already in production. Further changes can be made in design, manufacturing and
other aspects, so as to make it more reliable, more efficient and also cheaper.
For further increase in power generated, pressure is needed to be increased,
which would require redesign & reanalysis of turbine.
Turbine analysis has been done successfully up till 2.06 mach, and results show
that it can sustain much larger pressures.
57
1.11 REFERENCES :
[1] Dr.Virendra Kumar, "Fuze Power Supply Systems" ARDE Technical Report No.
1127 of 2004 (unpublished).
[2] http://www.interlloy.com.au/our-products/stainless-steel/304-austenitic-stainless-
steel-bar
[5] Material Density (kg/m3) of Aluminum alloy and Brass are computed using
ANSYS WORKBENCH 14.5 .
[6] http://www.magnetsales.com/alnico/alprops.htm
[7] Sudhir Dhamija, IJME, Volume 1, Spl. Issue 1 (2014), e-ISSN: 1694-2302 | p-
ISSN: 1694-2418, ‘CHARACTERIZATION OF TURBO-GENERATOR BASED
POWER SOURCE FOR ARTILLERY FUZES’, Ballistics Group, Armament
Research & Development Establishment, Pune, Maharashtra, India.
[8] pub-117---the-brasses_whole_web-pdf
[9] 'Turbo-generator for Electronic Fuze' by Virendra Kumar, DN Joshi, Sunil Kumar
Nema, Armament Research & Development Establishment, Pune, India.
[10]www.rare-earth-magnets.com/permenant-magnet-selection-and-Design-
Handbook.pdf
58