set objectives:
1. We want to build the Pandaan - Malang toll road with a total length of
38,488 km, to carry out toll road construction in order to finish on time
then we dividing 5 sections, that is:
Section 1 of Pandaan - Purwodadi (STA 0 + 000 to STA 15 + 475)
with a length of 15,475 km.
Section 2 of Purwodadi - Lawang (STA 15 + 475 to STA 23 + 525)
with a length of 8.050 km.
Section 3 of Lawang - Pakis I (STA 23 + 525 to STA 30 + 625) with a
length of 7,100 km.
Section 4 of Ferns I - Ferns II (STA 30 + 625 to STA 35 + 375) with a
length of 4,750 km.
Section 5 of Pakis II - Madyopuro (STA 35 + 375 to STA 38 + 488)
with a length of 3,113 km.
There are several work plans item that will be carried out during the
Pandaan-Malang toll road construction process, that is:
In the toll road construction process a lot of concrete work, for example
rigid pavement work with spec concrete class P, bridge work with spec
concrete K-250, K-350, K-400, K-500, etc. So In the construction
process need near batching plan from the project area, because make
easily for delivery, so it can save time. Include cut and fill job because cut
and fill is important to became foundation for the toll rood project.
2. we have 720 calendar days to carry out the Pandaan-Malang toll road
project. during the construction process section 1 - section 4 ran smoothly
according to schedule but for section 5 there were problems because the
temple was found at the project site so the project was stopped and made
our work is delay for 6 months
kami mempunyai waktu 720 hari kalender untuk melaksanakan proyek
jalan tol Pandaan-Malang. selama proses konstruksi seksi 1 - seksi 4
lancar sesuai jadwal tetapi untuk seksi 5 mengalami kendala karena
ditemukan candi di lokasi proyek sehingga proyek di hentikan dan
membuat pekerjaan kita terlambat selama 6 bulan
list alternative strategies:
1. if we continue the project according to the initial plan then we must wait
for the temple to be moved, but it will take a long time and the costs
incurred will increase
jika kita tetap melanjutkan proyek sesuai perencanaan awal maka kita
harus menunggu candi tersebut untuk di pindah, tetapi akan membutuhan
waktu yang lama dan biaya yang dikeluarkan akan bertambah
2. No, we want the Pandaan - Malang toll road project to be completed in a
timely manner so that the people immediately enjoy the toll road for their
daily needs
Tidak, kita maunya proyek jalan tol Pandaan - Malang selesai sesuai tepat
waktu agar masyarakat segera menikmati jalan tol untuk kebutuhan sehari-
hari
3. alternative that can be taken so that the Pandaan-Malang toll road project
is completed 100% on time is by planning a new alignment by adding
engineers and workers so that planning and implementation run quickly so
that the Pandaan-Malang toll road construction project is completed on
time and does not damage the condition of the temple which was found