Professional Documents
Culture Documents
905 015 2 Bored Cast in Place Concrete Piles
905 015 2 Bored Cast in Place Concrete Piles
concrete piles
The Task In the past the position of a building - Large point loads have to be trans-
was generally chosen according to the ferred into the subsoil.
suitability of the ground. Nowadays - The subsoil is contaminated from
High difficult ground or the presence of ex- past industrial pollution.
isting buildings close to the site - Deep basements have to be exca-
structural boundaries are no longer considered
as obstacles. Whether it is a question
vated close to the existing buildings
which must be protected against
Excavation
close to
existing
buildings
Front cover:
Tunnel project in Lugano, Switzerland
Back cover:
Top left:
Construction of a pile wall for the BMW-Welt,
Munich, Germany
Top right:
EUROVEA International Trade Centre in
Bratislava, Slovakia
Bottom left:
Bored pile foundation for the Tampa Museum
of Art, USA
Bottom right:
Construction of bored piles in rock for a new
building of SWR in Stuttgart, Germany Pasing Arcaden, Munich, Germany
2
The Solution Deep foundations Bored piles
These are several ways of transferring
Deep foun- structural loads into the subsoil on
sites where ground conditions are
In general bored piles offer the most
economical foundation as they can be
constructed in a wide choice of diam-
dations to unfavourable.
The bearing capacity of the subsoil
eters, typically ranging from 300 to
1,800 mm, and to depths of up to
Retaining walls
The problem of providing stable re-
taining structures close to existing
buildings or of constructing watertight
excavation pits can be solved in a
number of ways. However, the most
appropriate solution is almost always
the installation of a bored pile retaining
wall.
"Friction pile" "End bearing pile"
3
Techniques Piling systems differ in respect of the three main steps, drilling, placing rein-
techniques used (e. g. grab, rotary drill, forcement and concreting. Some of
direct circulation drill); the method these stages may be carried out si-
Cast-in- used to support the borehole (with or multaneously. Selection of the most
without drill casing, dry, hydrostatic appropriate piling technique depends
place pressure, slurry stabilisation), and
method of concreting (poured or in-
on the prevailing soil conditions, the
technical specifications relating to the
concrete jected). Pile construction comprises site and the overall cost.
piles
4
Rotary dril- Standard cast-in-place pile
Main applications: Special features:
ling with kelly All types of soil
Where site conditions are restricted
Vibration free drilling
High output with casings installed by
a) Cased rotary drive
Casing oscillator can be used for
larger pile diameters and greater
depths
Pile diameter generally 600 - 1,800 mm
Depths generally up to 40 m but grea-
ter depths are possible
Concrete
Install casing tubes Remove spoil with Insert reinforcing Place concrete by Completed pile
by rotating and drilling tools attached cage into borehole tremie and with-
crowding using to kelly bar with bore- draw casing using
rotary drive hole stabilisation by rotary drive
temporary casing
Rotate starter Remove drilling spoil Recycle slurry to Place concrete Completed pile
casing to depth with bucket attached remove soil and ins- simultaneously
to kelly bar with bore- ert reinforcing cage displacing slurry
hole supported by
slurry
5
Rotary drilling Drilling with double rotary head
Main applications: Special features
using twin All types of soil
On restricted sites
Vibration free
Continuous flight auger and casing
rotary head installed simultaneously by counter
rotating twin rotary drives
Can be installed against existing walls
Depth generally up to 15 m
Drilling diameter 620 - 880 mm (DKS)
Vibrator
Install casing and continu- Inject concrete Insert reinforce- Completed pile
ous flight auger to required through hollow stem ment cage into
depth using counter-rotat- auger, simultaneously concreted borehole
ing drives withdrawing auger
and casing
Vibrator
Concrete Pump
6
Displace- Displacement pile
Main applications: Special features:
ment pile Contaminated soils to avoid dispo-
sal of drill spoil
High bearing capacity through
highly compacted skin area
Limited space, e. g. track con- Avoiding drill spoil
struction High performance
Soft soils Drilling diameter 420, 510, 610 mm
Drilling without tremors
Drilling depth up to 34 m
Reduced concrete consumption
compared to auger cast-in-situ piles
Pump
Concrete
7
Planning
considera-
tions
8
Increasing Shaft grouting End bearing resisteance (%)
Settlement (mm)
soil this can result in a considerable
piles increase in shaft friction which en-
hances the bearing capacity and thus
the performance of the pile.
Base grouting
The end-bearing resistance of the pile
can also be increased by injecting
cement grout under pressure into the
100 % end-bearing resistance maximum endbe-
contact zone between the toe of the aring resistance of an ungrouted pile in sand with
pile and the underlying soil. Base a settlement s = d/10 where (d = pile diameter)
grouting not only offsets the almost
inevitable softening of the material at
the borehole toe but also reduces Skin friction resistance (%)
some of the early settlement.
Preparatory works
for piling Pile without
Pressure grouting
Settlement (mm)
Injection hoses for skin grouting Bauer Lift-Cell to pre-stress the pile bottom
9
Pile load tests
The most cost-effective bored pile de-
signs are those based on load tests on
site. They are generally only economic
for large construction projects. As a
result of the large number of pile load
tests we have carried out over many
years we are able to design bored
piles for all types of ground conditions
so as to achieve the greatest possible
economy. The diagrams below illus-
trate typical pile test results.
Skin friction
Marine clay
Moraine
shaft pressure
grouted
Pile shaft
Settlement
pressure
grouted
Load cell
Pile base
pressure grouted
Distribution of force and skin friction versus settlement chart of a pile diameter
1,180 mm in stiff marine clay, 5 m socketed in moraine
10
Quality- Pile installation is carried out by quali-
fied personnel whose technical experi-
in place continuous flight auger (CFA),
Front of wall (FOW) or mixed in place
ence is constantly monitored and (MIP) piles, all the parameters relating
assurance improved by in-house seminars and
quality audits. To ensure both site
to construction are displayed for the
rig operator on a monitor and are
safety and optimum production levels, stored in a data logger developed by
all drilling rigs and tools are regularly Bauer Spezialtiefbau. The stored data
tested. All construction materials are are computer processed, evaluated for
selected on the basis of the specified technical content and plotted out in
structural and process criteria to main- a standardised format. All other pro-
tain quality to the standards required. cesses are recorded by the piling su-
The pile production is documented ac- pervisor in accordance with standard
cording to EN 1536 (previously: procedures.
DIN 4014). During construction of cast
11
BAUER Spezialtiefbau GmbH
BAUER-Straße 1
86529 Schrobenhausen, Germany
Telephone: +49 8252 97- 0
Telefax: +49 8252 97-1496
BST@bauer.de
www.bauer.de
11/2011
905.015.2
12