Professional Documents
Culture Documents
1 . Overturning of the wall does Climbing Formwork or Lift Gabion- a type of retaining wall
not occur. Casting - this method can be produced from individual
employed on long walls, high rectangular boxes made from
2. Forward sliding of the wall walls or where the amount of panels of wire mesh, divided
does not occur. concrete which can be placed in internally and filled with stones.
a shift is limited.
3. Materials used are suitable
Mattress - unit fabrication is
and not overstressed. Casting Against Earth Face -this similar to a gabion but of less
method can be an adaptation of thickness, smaller mesh and
4. The subsoil is not overloaded.
the full height or climbing stone size to provide some
5. In clay subsoils slip circle
formwork systems. flexibility and shaping potential.
failure does not occur.
Masonry units - these are an Design of Retaining Walls - this
Earth Pressures - these can take
option where it is impractical or should allow for the effect of
one of two forms namely
cost-ineffective to use hydrostatics or water pressure
Active Earth Pressures - these temporary formwork to in-situ behind the wall and the
are those pressures which tend concrete. pressure created by the
to move the wall at all times retained earth.
Construction - a reinforced
and consist of the wedge of
concrete base is cast with Open Excavations - one of the
earth retained plus any
projecting steel bars accurately main problems which can be
hydrostatic pressure.
located for vertical continuity. encountered with basement
Passive Earth Pressures - these excavations is the need to
Crib Retaining Walls - a system
are a reaction of an equal and provide temporary support or
of pre-cast concrete or treated
opposite force to any imposed timbering to the sides of the
timber components comprising
pressure thus giving stability by excavation.
headers and stretchers which
resisting movement.
interlock to form a three- Perimeter Trench Excavations -
Mass Retaining Walls – these dimensional framework. in this method a trench wide
walls rely mainly on their own enough for the basement walls
Soil Nailing - a cost effective
mass to overcome the tendency to be constructed is excavated
geotechnic process used for
to slide forwards. and supported with timbering
retaining large soil slopes,
as required.
Cantilever Retaining Walls - notably highway and railway
these are constructed of embankments. Complete Excavation - this
reinforced concrete with an method can be used in firm
Function - after excavating and
economic height range of 1„200 subsoils where the centre of the
removing the natural slope
to 6„000. proposed basement can be
support, the remaining wedge
excavated first to enable the
Formwork -concrete retaining of exposed unstable soil is
basement slab to be cast thus
walls can be cast in one of three pinned or nailed back with
giving protection to the subsoil
ways tendons into stable soil behind
at formation level.
the potential slip plane.
Excavating Plant - the choice of Water-reducing admixtures - be present in the surrounding
actual pieces of plant to be used used to improve workability soil or ground water.
in any construction activity is a
Retarding admixtures- slow Internal Mastic Asphalt Tanking
complex matter taking into
down rate of hardening - this method should only be
account many factors.
adopted if external tanking is
Accelerating admixtures -
not possible since it will not give
increase rate of hardening
protection to the main structure
Water-repelling admixtures - and unless adequately loaded
Backactors – these machines effective only with low water may be forced away from the
are available as cable rigged or head, will not improve poor walls and/or floor by
hydraulic excavators suitable for quality or porous mixes. hydrostatic pressure.
trench and bulk excavating.
Air-entraining admixtures - Drained Cavity System - this
Faceshovels – these are robust increases workability method of waterproofing
machine design to excavate basements can be used for both
Joints - in general these are new and refurbishment work.
above their own wheel or track
formed in basement
level and are suitable for bulk
constructions to provide for Excavation - to hollow out.
excavation work.
movement accommodation
Oversite – the removal of top
Basement Construction - in the (expansion joints) or to create a
soil
general context of buildings a convenient stopping point in
basement can be defined as a the construction process Reduce level – carried out
storey which is below the (construction joints). below oversite level to form a
ground storey and is therefore level surface on which to build
Basement slabs - these are
constructed below ground level. and can consist of both cutting
usually designed to span in two
and filling operations.
Deep Basement Construction - directions and as a consequence
basements can be constructed have relatively heavy top and Trench Excavations - narrow
within a cofferdam or other bottom reinforcement. excavations primarily for strip
temporary supported foundations and buried services
Basement Walls - joints can be
excavation up to the point when
horizontal and/or vertical Temporary Support – in the
these methods become
according to design context of excavations this is
uneconomic.
requirements called timbering irrespective of
Dense Monolithic Concrete - the actual materials used. If the
Mastic Asphalt Tanking - the
the main objective is to form a sides of the excavation are
objective of tanking is to
watertight basement using completely covered with
provide a continuous
dense high quality reinforced or timbering it is known as close
waterproof membrane which is
prestressed concrete by a timbering whereas any form of
applied to the base slab and
combination of good materials, partial covering is called open
walls with complete continuity
good workmanship, attention to timbering.
between the two applications.
design detail and on site
Poling Boards - a form of
construction methods. External Mastic Asphalt
temporary support which is
Tanking - this is the preferred
Admixtures - if the ingredients placed in position against the
method since it not only
of good design, materials and sides of excavation after the
prevents the ingress of water it
workmanship are present excavation work has been
also protects the main structure
watertight concrete can be carried out.
of the basement from
produced without the use of
aggressive sulphates which may
admixtures.
Runners - a form of temporary since some of the fine cement Cofferdams - these are
support which is driven into particles could be blown away if temporary enclosures installed
position ahead of the cement is put in last. in soil or water to prevent the
excavation work either to the ingress of soil and/or water into
Sand or fine Aggregates - put in
full depth or by a drive and dig the working area with the
last to stabilise the fine
technique where the depth of cofferdam.
lightweight particles of cement
the runner is always lower than
powder. Steel Sheet Piling - apart from
that of the excavation.
cofferdam work steel sheet can
be used as a conventional
Concrete - a composite with timbering material in
Trench Sheeting - form of
many variables, represented by excavations and to form
runner made from sheet steel
numerous gradings which permanent retaining walls.
with a trough profile.
indicate components, quality
Installing Steel Sheet Piles - to
Water - if present or enters an and manufacturing control.
ensure that the sheet piles are
excavation, a pit or sump should
Standard Mix - BS guidelines pitched and installed vertically a
be excavated below the
provide this for minor works or driving trestle or guide frame is
formation level to act as
in situations limited by available used.
collection point from which the
material and manufacturing
water can be pumped away. Caissons - these are box-like
data. Volume or weight
structures which are similar in
Cement - whichever type of batching is appropriate, but no
concept to cofferdams but they
cement is being used it must be grade over C30 is recognised.
usually form an integral part of
properly stored on site to keep
Prescribed Mix - components the finished structure.
it in good condition.
are predetermined (to a recipe)
Pneumatic Caissons - these are
Concrete Batching - a batch is to ensure strength
sometimes called compressed
one mixing of concrete and can requirements.
air caissons and are similar in
be carried out by measuring the
Designed Mix - concrete is concept to open caissons.
quantities of materials required
specified to an expected
by volume or weight. Underpinning - the main
performance. Criteria can
objective of most underpinning
Volume Batching - concrete include characteristic strength,
work is to transfer the load
mixes are often quoted by ratio durability and workability,
carried by a foundation from its
such as 1 : 2 : 4 (cement : fine
Designated Mix - selected for existing bearing level to a new
aggregate or sand : coarse
specific applications. General level at a lower depth.
aggregate).
(GEN) graded 0†4, 7„5†25
Uneven Settlement - this could
Weight or Weigh Batching - this N/mm2 for foundations, floors
be caused by uneven loading of
is a more accurate method of and external works.
the building, unequal resistance
measuring materials for Foundations (FND) graded 2, 3,
of the soil action of tree roots or
concrete than volume batching 4A and 4B, 35 N/mm2 mainly
cohesive soil settlement.
since it reduces considerably for sulphate resisting
the risk of variation between foundations. Increase in Loading - this could
different batches. be due to the addition of an
Concrete Supply - this is usually
extra storey or an increase in
desiother materials out and geared to the demand or the
imposed loadings such as that
leaves the hopper clean. rate at which the mixed
which may occur with a change
concrete can be placed.
Cement - this is sandwiched of use.
between the other materials
Lowering of Adjacent Ground - concrete drilling equipment to position below the formation
usually required when achieve cost benefits through level to give a dry working area.
constructing a basement time saving.
Thin Grouted Membranes -
adjacent to existing
Underpinning Columns – these are permanent curtain or
foundations.
columns can be underpinned in cut-off non-structural walls or
General Precautions - before the some manner as walls using barriers inserted in the ground
any form of underpinning work traditional or jack pile methods to enclose the proposed
is commenced the following after the columns have been excavation area.
precautions should be taken relieved of their loadings.
Contiguous or Secant Piling -
Classification of Water - water this forms a permanent
can be classified by its relative structural wall of interlocking
position to or within the ground bored piles.
thus
Diaphragm Walls - these are
Underpinning to Walls - to Control of Ground Water - this structural concrete walls which
prevent fracture, damage or can take one of two forms can be cast in-situ (usually by
settlement of the wall(s) being which are usually referred to as the bentonite slurry method) or
underpinned the work should temporary and permanent constructed using precast
always be carried out in short exclusion concrete components.
lengths called legs or bays.
Permanent Exclusion - this can Precast Concrete Diaphragm
Jack Pile Underpinning - this be defined as the insertion of an Walls - these walls have the
method can be used when the impermeable barrier to stop the some applications as their in-
depth of a suitable bearing flow of water within the ground. situ counterparts and have the
capacity subsoil is too deep to advantages of factory produced
Temporary Exclusion - this can
make traditional underpinning components but lack the design
be defined as the lowering of
uneconomic. flexibility of cast in-situ walls.
the water table and within the
Needle and Pile Underpinning – economic depth range of 1„500 Grouting Methods - these
this method of underpinning can be achieved by subsoil techniques are used to form a
can be used where the drainage methods, for deeper curtain or cut off wall in high
condition of the existing treatment a pump or pumps are permeability soils where
foundation is unsuitable for usually involved. pumping methods could be
traditional or jack pile uneconomic
Simple Sump Pumping -
underpinning techniques.
suitable for trench work and/or Cement Grouts - mixture of
`Pynford' Stool Method of where small volumes of water neat cement and water cement
Underpinning - this method can are involved. sand up to 1 : 4 or PFA
be used where the existing (pulverized fuel ash) cement to
Jetted Sumps - ~ this method
foundations are in a poor a 1 : 1 ratio. Suitable for coarse
achieves the same objectives as
condition and it enables the grained soils and fissured and
the simple sump methods of
wall to be underpinned in a jointed rock strata.
dewatering (previous page) but
continuous run without the
it will prevent the soil Chemical Grouts - one shot
need for needles or shoring.
movement associated with this (premixed) of two shot (first
Root Pile or Angle Piling - this and other open sump methods. chemical is injected followed
is a much simpler alternative to immediately by second
Wellpoint Systems - method of
traditional underpinning chemical resulting in an
lowering the water table to a
techniques, applying modern immediate reaction) methods
can be employed to form a
permanent gel in the soil to vibrating a granular soil into surrounding urban areas,
reduce its permeability and at compacted stone columns designated inappropriate for
the same time increase the either by using the natural development in order to
soil's strength. coarse granular soil or by preserve the countryside.
replacement.
Resin Grouts - these are similar Brown-Field - derelict land
in application to chemical Dynamic Compaction - this is a formerly a developed site and
grouts but have a low viscosity method of soil improvement usually associated with previous
and can therefore penetrate which consists of dropping a construction of industrial
into silty fine sands. heavy weight through a buildings.
considerable vertical distance to
Ground Freezing Techniques - Site Survey - essential that a
compact the soil and thus
this method is suitable for all geo†technical survey is
improve its bearing capacity and
types of saturated soils and rock undertaken to determine
is especially suitable for
and for soils with a moisture whether contaminants are in
granular soils
content in excess of 8% of the the soil and ground water.
voids. Jet Grouting - this method of
Site Preparation - when
consolidating ground can be
building on sites previously
used in all types of subsoil and
infilled with uncontaminated
Soil Investigation - before a consists of lowering a monitor
material, a reinforced raft type
decision is made as to the type probe into a 150 mm diameter
foundation may be adequate for
of foundation which should be prebored guide hole.
light structures.
used on any particular site a soil
Ground Vibration - the
investigation should be carried Legislation - the Environment
objective of this method is to
out to establish existing ground Protection Act of 1990
strengthen the existing soil by
conditions and soil properties. attempted to enforce
rearranging and compacting
responsibility on local
Not to Build - unless a new and coarse granular particles to
authorities to compile a register
suitable site can be found form stone columns with the
of all potentially contaminated
building is only possible if the ground.
land.
poor ground is localised and the
Sand Compaction - applied to
proposed foundations can be Encapsulation - in-situ
non-cohesive subsoils where
designed around these areas enclosure of the contaminated
the granular particles are
with the remainder of the soil. A perimeter trench is taken
rearranged into a denser
structure bridging over these down to rock or other sound
condition by poker vibration.
positions. strata and filled with an
Dynamic Compaction - this impervious agent such as
Remove and Replace - the poor
method of ground improvement Bentonite clay.
ground can be excavated,
consists of dropping a heavy
removed and replaced by Soil washing - involves
weight from a considerable
compacted fills. extraction of the soil, sifting to
height and is particularly
remove large objects and
Surcharging - this involves effective in granular soils.
placing it in a scrubbing unit
preloading the poor ground
Jet Grouting - this is a means of resembling a huge concrete
with a surcharge of aggregate or
consolidating ground by mixer.
similar material to speed up
lowering into preformed bore
settlement and thereby improve Vapour extraction - used to
holes a monitor probe.
the soil's bearing capacity remove fuels or industrial
Green-Field - land not solvents and other organic
Vibration - this is a method of
previously built upon. Usually deposits.
strengthening ground by
part of the `green†belt'
Electrolysis - use of low voltage width of 225mm and a height of levels of a building to create a
d.c. in the presence of metals. 112„5mm. feature.
Electricity flows between an
Bonding -an arrangement of Dentil Coursing - a variation on
anode and cathode, where
bricks in a wall, column or pier continuous corbelling where
metal ions in water accumulate
laid to a set pattern to maintain alternative headers project.
in a sump before pumping to
an adequate lap.
the surface for treatment. Dog Toothing - a variation on a
English Bond - formed by laying dentil course created by setting
Phytoremediation - the
alternate courses of stretchers the feature bricks at 45.
removal of contaminants by
and headers it is one of the
plants which will absorb Blocks - these are walling units
strongest bonds but it will
harmful chemicals from the exceeding in length, width or
require more facing bricks than
ground. The plants are height the dimensions specified
other bonds
subsequently harvested and for bricks in BS EN 772-16.
destroyed. Flemish Bond - formed by laying
Cavity Walls - these consist of
headers and stretchers
Bioremediation - stimulating an outer brick or block leaf or
alternately in each course.
the growth of naturally skin separated from an inner
occurring microbes. Microbes Stack Bonding - the quickest, brick or block leaf or skin by an
consume petrochemicals and easiest and most economical air space called a cavity.
oils, converting them to water bond to lay, as there is no need
and carbon dioxide. Parapet -a low wall projecting
to cut bricks or to provide
above the level of a roof, bridge
special sizes.
or balcony forming a guard or
Attached Piers - the main barrier at the edge.
Oxidation - sub-soil boreholes
function of an attached pier is
are used for the pumped Function - the primary function
to give lateral support to the
distribution of liquid hydrogen of any damp-proof course (dpc)
wall of which it forms part from
peroxide or potassium or damp-proof membrane
the base to the top of the wall.
permanganate. (dpm) is to provide an
Jointing - the finish applied to impermeable barrier to the
Solvent extraction - the sub-soil
mortar joints as the work passage of moisture.
is excavated and mixed with a
proceeds.
solvent to break down oils, Methane - methane is produced
grease and chemicals that do Pointing - the process of by deposited organic material
not dissolve in water. removing semi-set mortar to a decaying in the ground.
depth of about 20mm and
Thermal treatment (off site) - Radon - a naturally occurring
replacing it with fresh mortar.
an incineration process colour/odourless gas produced
involving the use of a large Specials - these are required for by radioactive decay of radium.
heating container/oven. feature work and application to
Calculated Brickwork - for small
various bonds, as shown on the
Thermal treatment (in-situ) - and residential buildings up to
preceding pages.
steam, hot water or hot air is three storeys high the sizing of
pressure-injected through the Plinths - used as a projecting load bearing brick walls can be
soil. feature to enhance external taken from data given in Section
wall appearance at its base. 2C of Approved Document A.
CHAPTER 5
Corbel - a projecting feature at Thickness of wall -this must
Bricks -these are walling units
higher levels of a building. a always be sufficient throughout
within a length of 337„5mm, a
type of inverted plinth, its entire body to carry the
generally located at the higher
design loads and induced multiplied by a reduction factor Supports Over Openings - the
stresses. related to the slenderness primary function of any support
factor and the eccentricity of over an opening is to carry the
Effective Thickness -this is the
the load loads above the opening and
assumed thickness of the wall
transmit them safely to the
or column used for the purpose Lime - traditional mortars are a
abutments, jambs or piers on
of calculating its slenderness combination of lime, sand and
both sides.
ratio water.
Arch Construction - by the
Strength of Bricks - due to the Cement - the history of cement
arrangement of the bricks or
wide variation of the raw type mortar products is
stones in an arch over an
materials and methods of extensive. Examples dating back
opening it will be self
manufacture bricks can vary to the Mesopotamians and the
supporting once the jointing
greatly in their compressive Egyptians are not unusual; one
material has set and gained
strength. of the earliest examples from
adequate strength.
over 10000 years ago has been
Strength of Mortars - mortars
found in Galilee, Israel. Openings - these consist of a
consist of an aggregate (sand)
head, jambs and sill. Different
and a binder which is usually Mortar - ~ mixes for masonry
methods can be used in their
cement; cement plus additives should have the following
formation, all with the primary
to improve workability; or properties:
objective of adequate support
cement and lime.
* Adequate strength. around the void.
Sliding Sash Windows - these Clear Float - used where clear Metal Surrounds - metal
are an alternative format to the undistorted vision is required. casement putty if metal
conventional side hung Available thicknesses range surround is to be painted † if
casement windows and can be from 3mm to 25mm. surround is not to be painted a
constructed as a vertical or non-setting compound should
Clear Sheet - suitable for all
double hung sash window or as be used.
clear glass areas but because
a horizontal sliding window in
the two faces of the glass are Double Glazing - as its name
timber, metal, plastic or in any
never perfectly flat or parallel implies this is where two layers
combination of these materials.
some distortion of vision usually of glass are used instead of the
Double Hung Sash Windows - occurs. traditional single layer.
these vertical sliding sash
Translucent Glass - these are Finish - untreated aluminium is
windows come in two formats
patterned glasses most having prone to surface oxidisation.
when constructed in timber.
one patterned surface and one This can be controlled by paint
Horizontally Sliding Sash relatively flat surface. application, but most
Windows - these are an manufacturers provide a
Wired Glass - obtainable as a
alternative format to the variable colour range of
clear polished wired glass or as
vertically sliding or double hung polyester coatings finished
a rough cast wired glass with a
sash windows shown on pages gloss, satin or matt.
nominal thickness of 7mm.
372 & 373 and can be
Generally used where a degree Thermal insulation - poor
constructed in timber, metal,
of fire resistance is required. insulation and high conductivity
plastic or combinations of these
are characteristics of solid
materials with single or double Choice of Glass - the main
profile metal windows.
glazing. factors to be considered are:- 1.
Resistance to wind loadings. Condensation - a high strength
Pivot Windows - like other
2-part polyurethane resin
windows these are available in 2. Clear vision required.
thermal break between internal
timber, metal, plastic or in
3. Privacy. and external profiles inhibits
combinations of these
cold bridging.
materials.
4. Security.
Inert gas fills - argon or krypton.
Bay Windows - these can be
5. Fire resistance. Argon is generally used as it is
defined as any window with
the least expensive and more
side lights which projects in 6. Aesthetics.
readily available. Where
front of the external wall and is
Glazing - the act of fixing glass krypton is used, the air gap
supported by a sill height wall.
into a frame or surround. In need only be half that with
Schedules - the main function domestic work this is usually argon to achieve a similar
of a schedule is to collect achieved by locating the glass in effect.
together all the necessary a rebate and securing it with
information for a particular putty or beading and should be
group of components such as carried out in accordance with
Spacers - generally hollow Door Ironmongery - available in bearing cladding. Crosswall
aluminium with a desiccant or a wide variety of materials, construction is suitable for
drying agent fill. styles and finishers but will buildings up to 5 storeys high
consist of essentially the same where the floors are similar and
Manifestation or Marking of
components where internal separating or
Glass - another aspect of the
party walls are required such as
critical location concept which Hinges or Butts - these are used
in blocks of flats or maisonettes.
frequently occurs with to fix the door to its frame or
contemporary glazed features in lining and to enable it to pivot System - comprises quality
a building. about its hanging edge. controlled factory produced
components of plain reinforced
Critical Locations - The Building Locks, Latches and Bolts - the
concrete walls and prestressed
Regulations, Approved means of keeping the door in its
concrete hollow or solid core
Document † N, determines closed position and providing
plank floors.
positions where potential the required degree of security.
personal impact and injury with Site Assembly -components are
Letter Plates - fitted in external
glazed doors and windows are crane lifted and stacked
doors to enable letters etc., to
most critical. manually with the floor panel
be deposited through the door.
edges bearing on surrounding
Laying - glass blocks can be
Industrial Doors - these doors walls.
bonded like conventional
are usually classified by their
brickwork, but for aesthetic Concept - a cost effective simple
method of operation and
reasons are usually laid with and fast site assembly system
construction.
continuous vertical and using load-bearing partitions
horizontal joints. Straight Sliding Doors - these and external walls to transfer
doors are easy to operate, vertical loads from floor panels.
Jointing - blocks are bedded in
economic to maintain and
mortar with reinforcement from Framing - an industry based
present no problems for the
two, 9 gauge galvanised steel pre-fabricated house
inclusion of a wicket gate.
wires in horizontal joints. manufacturing process
Sliding/Folding Doors - these permitting rapid site
doors are an alternative format construction, with considerably
to the straight sliding door types fewer site operatives than
and have the same advantages traditional construction.
and disadvantages except that
Doors - can be classed as the parking space required for
external or internal. the opened door is less than
that for straight sliding doors.
External Doors - these are Background/history - the
available in a wide variety of Shutters - horizontal folding concept of steel framing for
types and styles in timber, shutters are similar in operation house construction evolved in
aluminium alloy or steel. to sliding/folding doors but are the early 1920s, but
composed of smaller leaves and development of the lightweight
Door Frames - these are present the same problems. concrete ``breeze'' block soon
available for all standard took preference.
external doors and can be Crosswall Construction - this is
obtained with a fixed solid or a form of construction where Render - a mix of binder
glazed panel above a door load bearing walls are placed at (cement) and fine aggregate
height transom. right angles to the lateral axis of (sand) with the addition of
the building, the front and rear water and lime or a plasticiser
walls being essentially non-load to make the mix workable.
Mix ratios - for general use, mix brickwork, but without the of snow, wind and rain blown
ratios are between 1 : 0.5 : expense. between the tiles or slates.
4†4.5 and 1 : 1 : 5†6 of cement,
History - originated during the Double Lap Tiles - these are the
lime and sand.
18th century, when they were traditional tile covering for
Finishes - smooth, textured, used quite frequently on timber pitched roofs and are available
rough-cast and pebble-dashed. framed buildings notably in made from clay and concrete
Kent and Sussex. and are usually called plain tiles.
Pebble or dry dash - small
stones thrown onto a strong Roofs - ~ these can be classified Single Lap Tiling - so called
mortar finishing coat (10 to as either:- because the single lap of one
12mm). tile over another provides the
Flat - pitch from 0 to 10
weather tightness as opposed
Smooth - fine sand and cement
Pitched - pitch over 10 to the two layers of tiles used in
finished with a steel trowel (6 to
double lap tiling.
8mm). Pitched Roofs - the primary
functions of any domestic roof Hips - can be finished with a half
Textured - final layer finished
are to:- round tile as a capping as shown
with a coarse brush, toothed
for double lap tiling.
implement or a fabric roller (10 1 . Provide an adequate barrier
to 12mm with 3mm surface to the penetration of the Valleys - these can be finished
treated). elements. by using special valley trough
tiles or with a lead lined gutter.
Rough-cast - irregular finish 2. Maintain the internal
resulting from throwing the environment by providing an Slates - slate is a natural dense
final coat onto the wall (6 to adequate resistance to heat material which can be split into
10mm). loss. thin sheets and cut to form a
small unit covering suitable for
Claddings to External Walls Roof Trusses - these are pitched roofs in excess of 25
-external walls of block or triangulated plane roof frames pitch.
timber frame construction can designed to give clear spans
be clad with tiles, timber boards between the external Flat Roofs - these roofs are very
or plastic board sections. supporting walls. seldom flat with a pitch of 0 but
are considered to be flat if the
Ordinary splay cutting to roof Trussed Rafters - these are pitch does not exceed 10.
verge - Tile and a half tiles at triangulated plane roof frames
the end of each course, cut to designed to give clear spans Timber Roof Joists - the spacing
the undercloak course of roof between the external and sizes of joists is related to
tiling. supporting walls. They are the loadings and span, actual
delivered to site as a dimensions for domestic
Winchester cutting to roof
prefabricated component loadings can be taken direct
verge - More attractive than
where they are fixed to the wall from recommendations in
ordinary splay cutting. Two cut
plates at 600mm centres. Approved Document A or they
tiles are required at the end of
can be calculated as shown for
each course, varying in size Gambrel roofs - are double timber beam designs.
depending on the roof pitch. pitched with a break in the roof
slope. Conservation of Energy ~ this
Appearance and concept - a
can be achieved in two ways: 1 .
type of fake brickwork made up Roof Underlays - ~ sometimes Cold Deck - insulation is placed
of clay tiles side and head called sarking or roofing felt on the ceiling lining, between
lapped over each other to provides the barrier to the entry joists. See page 448 for details.
create the impression of
A metallized polyester lined
plasterboard ceiling functions as allow adequate air circulation in Document to Part L of the
a vapour control layer, with a most situations. Building Regulations emphasises
minimum 50mm air circulation the importance of quantifying
Lateral Restraint - stability of
space between insulation and the energy costs of running
gable walls and construction at
decking. The air space homes.
the eaves, plus integrity of the
corresponds with eaves vents
roof structure during excessive Air Permeability - air tightness
and both provisions will prevent
wind forces, requires in the construction of dwellings
moisture build-up,
complementary restraint and is an important quality control
condensation and possible
continuity through 30 5mm objective.
decay of timber.
cross sectional area galvanised
Insulation continuity - this
2. (a) Warm Deck - rigid* steel straps.
requirement is for a fully
insulation is placed below the
Preservation - ref. Building insulated external envelope
waterproof covering and above
Regulations: Materials and with no air gaps in the fabric.
the roof decking. The insulation
Workmanship. Approved
must be sufficient to maintain Air tightness - requires that
Document to support
the vapour control layer and there is no air infiltration
Regulation 7.
roof members at a temperature through gaps in construction
above dewpoint, as this type of -treatment of timber to prevent and at the intersection of
roof does not require damage from House Longhorn elements.
ventilation. beetle.
Thermal Insulation - this is
(b) Inverted Warm Deck - Green roof - green with required within the roof of all
rigid* insulation is positioned reference to the general dwellings in the UK.
above the waterproof covering. appearance of plant growths
The insulation must be Thermal insulation to Walls -
and for being environmentally
unaffected by water and the minimum performance
acceptable.
capable of receiving a stone standards for exposed walls set
dressing or ceramic pavings. Categories ~ out in Approved Document L to
meet the requirements of Part L
Built-up Roofing Felt - this • Extensive - a relatively
of the Building Regulations can
consists of three layers of shallow soil base (typically
be achieved in several ways.
bitumen roofing felt to BS EN 50mm) and lightweight
13707, and should be laid to the construction. Thermal or Cold Bridging - this
recommendations of BS 8217 is heat loss and possible
• Intensive - otherwise known
condensation, occurring mainly
Mastic Asphalt - this consists of as a roof garden. This category
around window and door
two layers of mastic asphalt laid has a deeper soil base (typically
openings and at the junction
breaking joints and built up to a 400mm) that will provide for
between ground floor and wall.
minimum thickness of 20mm landscaping features, small
and should be laid to the ponds, occasional shrubs and
recommendations of BS 8218. small trees.