Schedules
SCHEDULE - A
(See Clause 2.1 and 8.1)
1 THE SITE
1.1 Site of the Four-Lane Project Highway shall include the land, buildings,
structures and road works as described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in
Annex-II of this Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works,
trees and any other immovable property on, or attached to, the Site shall be
prepared jointly by the Authority Representative and the Contractor, and such
inventory shall form part of the memorandum referred to in Clause 8.2.1 of
this Agreement.
1.4 Additional land required for toll plaza, Traffic Aid post, medical aid post and
vehicle rescue post or for construction of works specified in the Change of
Scope Order issued under clause 16.2.3 of this Agreement shall be acquired in
accordance with the provisions of Clause 10.3.6 of this Agreement. Upon
acquisition, such land shall form part of the Site and vest in Authority.
Annexure – I
(Schedule-A)
[Note: Through suitable drawings and description in words, the land, buildings,
structures and road works comprising the Site shall be specified briefly but precisely
in this Annex-I. All the chainages / location referred to in Annex-I to Schedule-A
shall be design chainages.]
Terrain
2 Land
The site of the project highway comprises the land (sum total of land already
in possession and land to be possessed) is detailed in Annex-II of this Schedule
A.
3 Carriageway
4 Major Bridges
The Site includes the following ROB (road over railway line)/RUB (road under
railway line):
6 Grade separators
7 Minor bridges
Existing Existing
Sl.No
km Structure Type Span (m) Deck Width (m)
1 11+590 Slab 2 X 6.0 24.00
10 Culverts
11 Bus bays
Nil
S. No. Chainage (km) Length (m) Left Hand Side Right Hand Side
Nil
14 Major junctions
15 Minor junctions
16 Bypasses
The work has been left incomplete by earlier agency (UPSHA) after erecting
about 70 piers and 19 pier caps.
19 Referencing
Main built-up areas along the existing project stretch are given below:
Annexure - II
(Schedule-A)
The dates on which the Authority shall provide Right of Way to the Contractor on
different parts of the Site are stated below:
1 2 3 4 5
Annexure – III
(Schedule-A)
Alignment Plans:
Annexure – IV
(Schedule-A)
Environment Clearances
Not required as per recent guidelines issued by MoEF Gazette S. O. No. 2559 (E*)
dated 22.08.2013. Further as per State Level Environment Impact Assessment
Authority, Uttar Pradesh vide their letter No.: 558 / Parya / SEAC / Gen – 5 / 2012
dated 21-03-2012 (copy enclosed), the Environmental Clearance is not needed
SCHEDULE - B
(See Clause 2.1)
DEVELOPMENT OF THE PROJECT HIGHWAY
Annex – I
(Schedule – B)
1.1 The Project Highway shall follow the alignment shown in the alignment
plans specified in Annex III of Schedule-A, unless otherwise specified by the
Authority. Notwithstanding anything to the contrary contained in this
Agreement or Manual, the proposed profile of the project highway as
indicated in the Annexure-III of Schedule-A shall be deemed to be part of
this Schedule-B and shall be followed by the contractor with minimum FRL
as indicated in the Alignment Plan. Based on Design/Site requirements, the
contractor may, however, improve/upgrade upon the alignment plans and
profile as indicated in Annexure-III of Schedule-A and raise the finished
roadway level with approval from Authority’s Engineer within the available
ROW. Geometric deficiencies, if any, in the existing horizontal and vertical
profiles shall be corrected as per the prescribed standards for
Plain/Rolling/Hilly terrain to the extent land is available.
1.2.2 Provided that in the built-up areas the carriageway width is as indicated
below and referred to in Clause 2.12 of this Annex –I of Schedule–B and
Annex –I of Schedule–D.
Design Chainage
Sl No. Length (m) Built-up Location
From To
Entire Length falls within built
1 10+500 18+050 7550
up area.
1.2.3 Except as otherwise provided in this Agreement, the width shall be adjusted
to fit into appropriate plans and cross sections developed in accordance with
Schedule-D to accommodate all the features of four-laning described herein.
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh Page No.: | 13 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
2.1 General
The design speed shall be the ruling/minimum design speed specified in Clause
2.2 of the Manual.
2.7.1 Lateral and vertical clearances at over passes shall be as per paragraph 2.11
of the Manual.
Nil
nil
2.10.1 Grade separated structures shall be provided as per paragraph 2.13 of the
Manual. The requisite particulars are given below:
Nil
Nil
Design Chainage
(KM) Length
TCS Type Remark
(m)
From To
Improvement of Existing Four Lane in
10+500 10+900 400 TCS 1
Built-Up (Overlay with 40mm BC)
Widening & Improvement of Existing
10+900 11+584 684 TCS 2
Four Lane in Built-Up
11+584 11+596 12 TCS 15 Minor Bridge
Widening & Improvement of Existing
11+596 11+770 174 TCS 3
Four Lane in Built-Up (Below Metro Line)
Improvement of Existing Four Lane in
11+770 11+930 160 TCS 4
Built-Up (Retrofit with Metro Station)
Widening & Improvement of Existing
11+930 12+710 780 TCS 3
Four Lane in Built-Up (Below Metro Line)
Improvement of Existing Four Lane in
12+710 12+870 160 TCS 4
Built-Up (Retrofit with Metro Station)
Widening & Improvement of Existing
12+870 13+150 280 TCS 3
Four Lane in Built-Up (Below Metro Line)
Widening & Improvement of Existing
13+150 13+500 350 TCS 5
Four Lane in Built-Up
Widening & Improvement of Existing
13+500 14+500 1,000 TCS 6
Four Lane in Built-Up
Widening & Improvement of Existing
14+500 15+100 600 TCS 7
Four Lane in Built-Up
Widening & Improvement of Existing
15+100 15+350 250 TCS 8
Four Lane in Built-Up
Widening & Improvement of Existing
15+350 16+220 870 TCS 9
Four Lane in Built-Up
Widening & Improvement of Existing
16+220 16+350 130 TCS 14
Four Lane in Built-Up
Widening & Improvement of Existing
16+350 16+610 260 TCS 10
Four Lane in Built-Up
Widening & Improvement of Existing
16+610 16+660 50 TCS 14
Four Lane in Built-Up
Improvement of Existing Four Lane in
16+660 16+950 290 TCS 11
Built-Up (Retrofit with Existing Piers)
Note: Above length of indicative TCS to be followed for the project highway is
indicative. The actual length of each TCS shall be determined based on the
Major Intersections:
Existing Side
Type of
S.No. Chainage (LHS/RHS) Remarks
Junction
(Km)
1 10+500 X Both Ghaziabad to Wazirabad
Minor Intersections :
Existing
Type of Side
Sr No Chainage Remarks
Junction (LHS/RHS)
(km)
1 11+620 Y LHS
2 13+570 Y RHS
3 14+400 T RHS
4 15+260 T LHS
Existing
Type of Side
Sr No Chainage Remarks
Junction (LHS/RHS)
(km)
5 15+910 T LHS
6 16+690 T LHS
7 17+330 T LHS
Note:
(i) Type of Junction to be improved as per manual and MOST type design for
intersection on National Highways, 1992.
(ii) Any other junction not mentioned above but observed during the
construction of the project shall be improved as per manual requirements.
The same shall not constitute a Change of Scope, save and except any
variations in the length arising out of a Change of Scope expressly
undertaken in accordance with the provisions of Article 13.
(iii) The concessionaire shall take up ‘Detailed Engineering study’ to ascertain
further details of all intersections and treatment of the intersections shall
be designed in accordance with the latest guidelines mentioned out in
section-3 of Manual. The same shall not constitute a Change of Scope,
save and except any variations in the length arising out of a Change of
Scope expressly undertaken in accordance with the provisions of Article 13.
(iv) Junction improvement shall be carried out as per IRC Manual under grade
separators with proper entry/exit to cross roads and slip/service roads.
4.1.1 Raising of the existing road shall be in accordance with alignment plan and
profile drawings provided in Annex III of schedule A. The Cut Section
Stretches are also mentioned therein.
5. Pavement
(i) Flexible pavement shall be provided for the entire length of Project
Corridor.
(ii) The treatment to the existing pavement shall be limited to
improvement of its riding quality only including maintenance as
indicated below.
6. Median
Raised median as shown in the drawings shall be provided as per details given
below:
Drainage system including surface and subsurface drains for the Project Highway
shall be provided as per section 6 of the Manual. RCC covered Drains shall be
provided in the following stretches as specified in the TCS of the project
Highway.
LHS
Retain
From To
Total 400
New Construction
From To
Total 570
Re Construction
From To
Total 1400
From To
Total 1610
RHS
Retain
Chainage (km)
Length (m) Remarks
From To
10+500 10+900 400 RHS
Total 400
Re Construction
Chainage (km)
Length (m) Remark
From To
Total 3570
Chainage (km)
Length (m) Remarks
From To
Note: 1. Above length of the lined drains shall be determined by the Contractor in
accordance with the applicable Typical Cross-section and Manual
requirements with approval from the Authority’s Engineer. Any increase in
the length specified in this Clause of Schedule-B shall not constitute a
Change of Scope, save and except any variations in the length arising out of
a Change of Scope expressly undertaken in accordance with the provisions of
Article 13. Unlined drain shall be proposed in the balance locations as per
manual requirements.
3. Contractor shall clean and make the drain functional wherever the
existing drains are retained.
8. Median Drain:
9. Design of structures
9.1 General
9.1.4 The following structures shall be designed to carry utility services specified
in table below:
9.1.5 Cross-section of the new culverts and bridges at deck level for the Project
Highway shall conform to the typical cross-sections given in section 7 of the
manual and TCS in para 2.11.
9.2 Culverts
9.2.1 Overall width of all culverts shall be equal to the roadway width of the
approaches.
Pipe
4 14+604 1.2 dia 29 Reconstruction
Culvert
5 15+204 RCC BOX 1 X 2.5 29 Reconstruction
Pipe
6 16+230 1.2 dia 29 Reconstruction
Culvert
Reconstruction
7 16+277 RCC BOX 1 X 2.5 29 of Balance
work)
Nil
New culverts (given in table below) shall be constructed for width equal to
the roadway width of the project highway and as per typical cross section
given in the TCS specified in para 2.11 and alignment plan.
Note:
1. The overall width of the above culverts shall be equal to Roadway width.
2. Location and span arrangements of the above culverts are indicative. Exact
location of these culverts may be decided in consultation with Authority
Engineer. The actual vent way/span arrangements of culverts shall be
determined on the basis of detailed investigations by the Contractor in
accordance with the Specifications and Standards. Any variations in vent
way/span arrangements specified in this Schedule-B shall not constitute a
Change of Scope, save and except any variations in the length arising out of
a Change of Scope expressly undertaken in accordance with the provisions of
Article 13.
3. Floor protection works shall be as specified in the relevant IRC Codes and
Specifications.
Floor protection works shall be as specified in the relevant IRC Codes and
Specifications.
Utility ducts in form of NP-4 Hume Pipe shall be provided across the Project
Highway and along with inspection chamber for crossing of underground
utilities in Built-up areas as per manual requirements. Location for such
utility crossing shall be finalized in consultation with Authority Engineer.
5. Bridges
Major Bridges:
Minor Bridges:
Existing
Sl. Design Details of Details of
No Chainage Structure Rehabilitation Repair
Span
Type
Nil
6. Rail-road bridges
Nil
Road under bridges (road under railway line) shall be provided at the
following level crossings, as per GAD drawings attached: Nil
Nil
9. List of Structures:
1 Nil
10.1 Traffic control devices and road safety works shall be provided in accordance
with Section 9 of the Manual.
Traffic signs include roadside signs, overhead signs and curb mounted signs
along the entire Project Highway.
Pavement markings shall cover road marking for the entire Project Highway.
No proposal
10.2 Reflective sheeting shall be provided in accordance with section 9.2.3 of the
Manual.
a) Pedestrian Guard Rail: Pedestrian guard rails shall be provided at each bus bay,
bus shelter location as specified in the manual.
c) Overhead Traffic Signs (excluding overhead signs at Toll Plaza): Location and
Size :
Design Chainage(Km)
Location No.
Overhead Gantry signs
Nil
Nil
Nil
The length of Structures and bridges specified herein above are minimum.
The proposed span arrangement of above structures may be changed based
on innovative design of structure, latest construction techniques and
aesthetics of structures and the actual lengths of Structures and bridges as
required on the basis of detailed investigations shall be determined by the
Contractor in accordance with the Specifications and Standards. Any
increase in the lengths specified in this Schedule-B shall not constitute a
Change of Scope, save and except any variations in the length arising out of
a Change of Scope expressly undertaken in accordance with the provisions of
Article 13.
SCHEDULE – C
(See Clause 2.1)
PROJECT FACILITIES
1 Project Facilities
2 Project Facilities
1 Traffic Sign
Traffic Sign includes the Road Side Signs and Kerb mounted signs along the
entire Project Highway in accordance with section 9 of IRC: SP:84-2014.
Number and location of such signs shall be finalized in consultation with
Authority Engineer.
2 Pavement Marking
Pavement Marking shall cover the road marking for the entire Project
Highway in accordance with section 9 of IRC: SP:84-2014.
3 a. Hectometer/km Stones
b. Pedestrian Facilities
1 Pedestrian Guard Rail: Pedestrian guard rails shall be provided at each bus
bay, bus shelter location as specified in the manual.
c. Bus Bays
2 nos. of bus bays are proposed at following chainages:
Location of Bus Bays:
SCHEDULE – D
(See Clause 2.1)
1 Construction
The Contractor shall comply with the Specifications and Standards set forth
in Annex-I of this Schedule-D for construction of the Project Highway.
2 Design Standards
Annex - I
(Schedule-D)
All Materials, works and construction operations shall conform to the Manual
of Specifications and Standards for Four-Laning of Highways (IRC:SP:84-
2014), referred to as the Manual, and MORTH Specifications for Road and
Bridge Works. Where the specification for a work is not given, Good Industry
Practice shall be adopted to the satisfaction of the Authority’s Engineer.
Schedule - H
Weightage in % Percentage
Item Stage for Payment
of CP weightage
(1) (2) (3) (4)
A- Widening and strengthening of
56.27% existing road
Weightage in % Percentage
Item Stage for Payment
of CP weightage
(2) Earthwork in Shoulders 0.00%
(3) Sub-base Course 0.00%
(4) Dry Lean Concrete (DLC) Course 0.00%
(5) Pavement Quality Control 0.00%
(PQC) Course
C.1- Reconstruction/ New Service
Road/ Slip Road (Flexible
Pavement)
(1) Earthwork up to top of the sub- 0.00%
grade
(2) Earthwork in Shoulders 0.00%
(3) Sub-base Course 0.00%
(4) Non bituminous Base course 0.00%
(5) Bituminous Base course 0.00%
(6) Wearing Coat 0.00%
C.2- Reconstruction/New Service
road(Rigid Pavement)
(1) Earthwork up to top of the sub- 0.00%
grade
(2) Sub-base Course 0.00%
(3) Dry Lean Concrete (DLC) Course 0.00%
(4) Pavement Quality Control (PQC) 0.00%
Course
D- Reconstruction & New Culverts
on existing road, realignments,
bypasses Culverts (length <6m)` 1.90%
A.1- Widening and repairs of Minor
Bridges (length>6m & <60m)
Minor Bridges 0.00%
A.2- New Minor bridges (length >6
m and < 60 m)
(1) Foundation: On completion of 39.40%
the foundation work including
Minor bridge/ foundations for wing and return
6.05% walls, abutments, piers.
Underpasses/
Overpasses (2) Sub-structure: On completion of 20.83%
abutments, piers upto the
abutment/ pier cap including
wing/ return/ retaining wall upto
Weightage in % Percentage
Item Stage for Payment
of CP weightage
top
(3) Super-structure: On completion 30.83%
of the super-structure in all
respects including Girder, Deck
slab, bearings
(4) Approaches: On completion 7.69%
of approaches including Retaining
walls, stone pitching, protection
works complete in all respect,
tests on completion in all respect
and fit for use
(5) Guide Bunds and River Training
Works: On completion of Guide
0.00%
Bunds and river training works
complete in all respects
(6) Other Ancillary Works: On
completion of wearing coat,
expansion joints, hand rails, crash 1.25%
barriers, road signs & markings,
tests on completion in all respect.
B.1- Widening and repairs of
underpasses/overpasses 0.00%
Underpasses/ Overpasses
B.2- New Underpasses/Overpasses
(1) Foundation: On completion of
the foundation work including
0.00%
foundations for wing and return
walls, abutments, piers.
(2) Sub-structure: On completion of
abutments, piers upto the
abutment/ pier cap including 0.00%
wing/ return/ retaining wall upto
top
(3) Super-structure: On completion 0.00%
of the super-structure in all
respects including Girder, Deck
slab, bearings.
(4) On completion of Retaining 0.00%
/ Reinforced earth walls, complete
in all respect and fit for use
(5) Approaches and Other Ancillary 0.00%
Works: On completion of wearing
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh
Page No.: | 54 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
Weightage in % Percentage
Item Stage for Payment
of CP weightage
coat, expansion joints, hand rails,
crash barriers, stone pitching,
protection works, road signs &
markings, tests on completion in
all respect.
Wearing Coat (a) in case of
Overpass- wearing coat including
0.00%
expansion joints complete in all
respects as specified and
(b) in case of underpass-rigid
pavement including drainage
0.00%
facility complete in all respects as
specified
A.1- Widening and repairs of Major
Bridges
(1) Foundation: On completion of
the foundation work including
0.00%
foundations for return walls,
abutments, piers.
(2) Sub-structure: On completion of
abutments, piers upto the 0.00%
Major abutment/ pier cap
bridge(length> (3) Super-structure: On completion
60 m) works of the super-structure in all
0.00%
and respects including Girder, Deck
ROB/RUB/elev slab, bearings.
0.00% (4) Wearing Coat including
ated 0.00%
sections/flyov expansion joints
ers including (5) Miscellaneous Items like hand
viaducts, if rails, crash barrier, road markings 0.00%
any etc.
(6) Wing walls/return walls upto 0.00%
top
(7) Guide bunds, River Training 0.00%
works etc.
(8) Approaches(including Retaining 0.00%
works)walls, stone pitching and
protection
A.2- New Major Bridges
Weightage in % Percentage
Item Stage for Payment
of CP weightage
Weightage in % Percentage
Item Stage for Payment
of CP weightage
rails, crash barrier, road markings
etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth
0.00%
walls
(8) Approaches and Other Ancillary
Works (wearing coat, expansion
joints, hand rails, crash barriers, 0.00%
road signs & markings, stone
pitching, protection works etc.)
B.2- New ROB/RUB
(1) Foundations 0.00%
(2) Sub-Structure 0.00%
(3) Super-Structure (Including
0.00%
bearings)
(4) Wearing Coat (a) in case of
ROB- wearing coat including
expansion joints complete in all
respects as specified and in case
0.00%
of RUB-rigid pavement under RUB
including drainage facility
complete in all respects as
specified.
(5) Miscellaneous items like hand
rails, crash barrier, road markings 0.00%
etc.
(6) Wing Walls / Return Walls 0.00%
(7) Retaining / Reinforced earth
0.00%
walls
(8) Approaches and Other Ancillary
Works (wearing coat, expansion
joints, hand rails, crash barriers, 0.00%
road signs & markings, stone
pitching, protection works etc.)
C.1- Widening and repair of
Elevated Section/Flyovers/Grade
Separators
(1) Foundations 0.00%
(2) Sub-Structure 0.00%
(3) Super-Structure(Including
0.00%
bearings)
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh
Page No.: | 57 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
Weightage in % Percentage
Item Stage for Payment
of CP weightage
(4) Wearing Coat including
0.00%
expansion joints
(5) Miscellaneous Items like hand
rails, crash barrier, road markings 0.00%
etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth
0.00%
walls
(8) Approaches and Other Ancillary
Works (wearing coat, expansion
joints, hand rails, crash barriers, 0.00%
road signs & markings, stone
pitching, protection works etc.
C.2- New Elevated
Section/Flyovers/Grade Separators
(1) Foundation: On completion of
the foundation work including
0.00%
foundations for wing and return
walls, abutments, piers.
(2) Sub-structure: On completion of
abutments, piers upto the
abutment/ pier cap including 0.00%
wing/ return/ retaining wall upto
top
(3) Super-structure: On completion
of the super-structure in all
respects including Girder, Deck 0.00%
slab, bearings
Weightage in % Percentage
Item Stage for Payment
of CP weightage
(i) Toll Plaza
(ii) Road side drains
Lined Drain 82.72%
Unlined Drain 0.00%
(iii) Road signs, safety Devices,
37.68% 9.00%
Road Furnitures etc.
(iv) Road markings & Studs 0.00%
(v) Crash Barrier 0.00%
(vi) Project facilities
a) Bus Bays 4.60%
b) Wayside Amenities excluding Slip
Roads & but including all
0.00%
internal roads (Service areas
including Truck Lay-Byes)
c) Others (to be specified) 0.00%
(vii) Retaining Wall 0.00%
Other Works
(viii) RE Wall 0.00%
(ix) Street Lighting 0.00%
(x) Utility Ducts 0.00%
(xi) Boundary wall 0.00%
(xii) ATMS 0.00%
(xiii) Rain Water Harvesting 0.00%
(xiv) Road side Plantation including
Horticulture in Wayside Amenities 0.00%
(xv) Protection Works other than
approaches to the bridges, elevated
0.00%
sections/ flyover/ grade
separators and ROBs/ RUBs
(xvi) Safety & Traffic
Management during const. 0.00%
(xvii) Other miscellaneous works
including Connecting road &
Junction under Grade separator 3.68%
Road works
Procedure for estimating the value of road work done shall be as follows:
Table 1.3.1
For calculation of payment stage for main-carriageway the project length shall
be converted into equivalent 2 lane length. For example, if the total length of 4
lane main carriageway is 100 km, then the equivalent length for calculation of
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh Page No.: | 61 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
payment stage will be 2 x 100 km. Now, if the total length of bituminous work to
be done is 100 km, the cost per km of bituminous work shall be determined as
follows:
Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)
Where
P = Contract Price
Similarly, the rates per km for other stages shall be worked out accordingly.
Note: The length affected due to law and order problems or litigation during
execution including the length not handed over to the Contractor under
clause 8.3 of this Contract Agreement due to which the Contractor is
unable to execute the work, may be deducted from the total project
length for payment purposes. The total length calculated here is only for
payment purposes and will not affect and referred in other clauses of the
Contract Agreement
Table 1.3.2
Stage of Payment Weightage Payment Procedure
(1) (2) (3)
A.1- Widening and repairs of 0.00% Cost of each minor bridge shall
Minor Bridges (length>6m be determined on pro rata basis
&<60m) with respect to the total linear
length of the minor bridges.
Payment shall be made on the
completion of widening &
repair works of a minor bridge
A.2- New Minor Bridges Foundation: Cost of each minor
(length>6m &<60m) bridge shall be determined on
pro- rata basis with respect to
(1) Foundation: On completion 39.40% the total linear length (m) of the
of the foundation work minor bridges. Payment against
including foundations for wing foundation shall be made on pro-
and return walls, abutments, rata basis on completion of a
piers stage i.e. not less than 25% of the
scope of foundation of each
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh Page No.: | 62 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
(5) Guide Bunds and River 0.00% Guide Bunds and River Training
Training Works: On Works:
completion of Guide Bunds
and river training works
complete in all respects
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh Page No.: | 63 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
Procedure for estimating the value of Major Bridge works, ROB/RUB and
Structures Work shall be as stated in table 1.3.3:
Table 1.3.3
(6) Wing walls/return walls upto 0.00% Wing walls/return walls: Payments
top shall be made on completion of all
wing walls/ return walls complete
in all respects as specified.
(7) Guide bunds, River Training 0.00% Guide Bunds, River Training works:
works etc. Payments shall be made on
completion of all guide bunds/river
training works etc. complete in all
respects as specified.
(8) Approaches(including) 0.00% Approaches: Payments shall be
Retaining walls, stone pitching made on pro rata basis on
and protection works) completion of 10% of the scope of
each stage.
(7) Guide bunds, River Training 0.00% Guide Bunds, River Training works:
works etc. Payments shall be made on
completion of all guide bunds/river
training works etc. complete in all
respects as specified.
(8) Approaches and Other Ancillary 0.00% Payment shall be made on pro-
Works: On completion of wearing rata basis on completion of a stage
coat, expansion joints, hand rails, in all respects as specified
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh Page No.: | 71 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
(8) Approaches and Other Ancillary 0.00% Payment shall be made on pro-
Works: On completion of wearing rata basis on completion of a stage
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh Page No.: | 74 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
Note: (1) In case of innovative Major Bridge projects like cable suspension/cable
stayed/ Extra Dozed and exceptionally long span bridges, the schedule
may be modified as per site requirements before bidding with due
approval of DG(RD)&SS, MoRT&H.
The Schedule for exclusive tunnel projects may be prepared as per site
requirements before bidding with due approval of DG(RD)&SS, MoRT&H.
Other Works.
Procedure for estimating the value of other works done shall be as stated in
Table 1.3.4:
Table 1.3.4
Stage of Payment Weightage Payment Procedure
(1) (2) (3)
(1) Toll Plaza 0.00% Unit of measurement is each
completed toll plaza. Payment
of each toll plaza shall be made
on pro rata basis with respect to
the total of all toll plaza.
(2) Road side drains
Lined Drain 82.72%
Unlined Drain 0.00% Unit of measurement is linear
Road signs, safety length in km. Payment shall be
Devices, Road Furniture’s made on pro rata basis on
(3) etc. 9.00% completion of a stage in a length
(4) Road markings & Studs 0.00% of not less than 10% (ten per
(5) Crash Barrier 0.00% cent) of the total length.
Payment shall be made on pro
rata basis for completed
(6) Project Facilities facilities.
a) Bus Bays 4.60%
Wayside Amenities 0.00%
excluding Slip Roads &
but including all internal
roads(Service areas
b) including Truck Lay-Byes)
Others (To be specified) 0.00%
c)
Consultancy Services For Feasibility Study and Preparation
of Detailed Project Report For Improvement and Upgradation
of NH-709B from km 10.500 To Km 18.050 in the state of
Uttar Pradesh Page No.: | 75 |
National Highways Authority of India Request for Proposal – Bid documents
Schedules
SCHEDULE - J
(See Clause 10.3.2)
2 Project Milestone-I
2.1 Project Milestone-I shall occur on the date falling on the 120th (One
Hundred twenty) day from the Appointed Date (the “Project Milestone-I”).
2.2 Prior to the occurrence of Project Milestone-I, the Contractor shall have
commenced construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an
amount not less than 30% (ten per cent) of the Contract Price.
3 Project Milestone-II
3.1 Project Milestone-II shall occur on the date falling on the 240th (Two
Hundred and Forty) day from the Appointed Date (the “Project Milestone-
II”).
3.2 Prior to the occurrence of Project Milestone-II, the Contractor shall have
continued with construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an
amount not less than 65% (thirty five per cent) of the Contract Price.
4.1 The Scheduled Completion Date shall occur on the 365th (Three Hundred and
Sixty five ) day from the Appointed Date.
4.2 On or before the Scheduled Completion Date, the Contractor shall have
completed construction in accordance with this Agreement.
5 Extension of time