Professional Documents
Culture Documents
ARAMCO Standard For Cathodic Protection of Buried Pipelines
ARAMCO Standard For Cathodic Protection of Buried Pipelines
1 Scope............................................................. 2
2 Conflicts and Deviations................................ 2
3 References..................................................... 2
4 Definitions...................................................... 5
5 Design............................................................ 6
6 Installation.................................................... 23
7 Commissioning and Inspection.................... 30
8 Records........................................................ 30
1 Scope
This standard prescribes the minimum mandatory requirements governing the design
and installation of cathodic protection systems for onshore pressurized buried metallic
pipelines outside of plant facilities. This standard does not address subsea pipelines or
pipelines operated by Saudi Aramco Community Maintenance Departments
2.1 Resolve any conflicts between this standard and other applicable Saudi Aramco
Engineering Standards (SAESs), Materials System Specifications (SAMSSs),
Standard Drawings (SASDs), or industry standards, codes, and forms, in
writing, with the Company or Buyer Representative through the Manager,
Consulting Services Department (CSD) of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this standard in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, CSD, Saudi Aramco, Dhahran.
3 References
The Saudi Aramco Engineering Standards intranet web site contains the latest revisions
of all standards and standard drawings.
Page 2 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Page 3 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Page 4 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
4 Definitions
Cross-Country Pipeline: The pipeline and its appurtenances used to transport fluids
across the country between isolated plant areas.
Design Agency: The firm responsible for designing the piping system. It could be the
design Contractor, the Lump Sum Turn Key Contractor or in house design organization
of Saudi Aramco.
Flowlines: Production pipelines connected to oil, gas or water wells for production,
injection or well testing.
Off-Plot: Off-plot refers to any area outside of the plot limits. Off-plot can include
plant areas such as roads, pipeways and open lots between plant units.
Pipelines: When the term "pipeline" is used in this Standard it is meant to include both
buried Cross-Country pipelines and Production pipelines"
Plant-Area: The designated area engaged in the production, processing, storage and
transportation of crude oil, gas, refined products and their derivatives, typically inside a
perimeter fence.
Page 5 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Plot Limit: The plot limit is a boundary, within the plant area, which surrounds a
single plant or function. The plot limit may be physical such as a fence (not necessarily
an SSD fence), a wall, the edge of a road or pipe-way, chains and posts or a boundary
indicated on an approved plot plan.
Production Pipelines: Those pipelines engaged in transporting crude oil or gas from
the producing wells to the designated facility for processing. These include flowlines,
testlines, trunklines and transmission pipelines.
Testlines: Production pipelines that are used for testing an individual producing well
without affecting the operation of the trunklines.
5 Design
The design agency shall not issue drawings for construction that have
not been approved in writing by the proponent cathodic protection
organization and the Cathodic Protection & Coatings Unit of CSD.
Exception:
Page 6 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.1.4 The design package submitted for review shall contain at minimum:
a) The scope of work
b) Professionally drafted full size Index "X" CP drawings that:
• detail each CP item by description and stock number if
applicable;
• detail the proposed location for each piece of CP equipment
including but not limited to rectifiers, anodes, junction boxes,
bond stations, test stations, and bonds to structures;
• detail and specifically identify all cathodic protection cables
including all anode, structure, bond, and rectifier cables;
• clearly identify the specific and individual cable routing and
termination points within the respective test stations, junction
boxes, bond boxes, and rectifiers;
• detail all cathodic protection equipment using the cathodic
protection symbols as shown on standard drawing AD-
036785 "Symbols – Cathodic Protection";
• detail all existing CP installations in the area that could have
an effect on the new CP system, and also provide information
on spare current capacity of existing CP systems that will be
utilized by the project.
c) All calculations and applicable field data required to verify
design compliance with the Saudi Aramco Cathodic Protection
Engineering Standards.
d) Remote Monitoring for Cross-Country pipelines shall be installed
on Cross-Country pipeline rectifiers. It shall comply with 17-
SAMSS-018 and shall be constructed to interface with existing
Saudi Aramco Wireless Remote Monitoring System.
Commentary Notes:
Page 7 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.2 General
Page 8 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Commentary Note:
Galvanic anodes are not required for open cut paved or unpaved road
crossings on normally buried pipelines with ICCP systems.
2) At gas well sites, if the flare and blow-down lines are stainless
steel, coated and made continuous with the ICCP system, then
galvanic anodes will not be needed at their thrust anchors.
Page 9 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Commentary Note:
Page 10 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.3.2 The minimum design life of galvanic anode systems for electrically
isolated short pipeline sections shall be 20 years.
Page 11 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
* Note: This is for coatings approved for use on new pipelines per SAES-H-002.
Consult with CSD if any other type of coating is to be used.
5.5.2 Pipeline Valves and associated buried piping: The negative pipe-to-
soil ON potential shall be a minimum of 1.0 volt and a maximum of
3.0 volts, with reference to a copper/copper sulfate electrode.
5.5.4 For all pipelines, cathodic protection must be achieved within 30 days
of pipeline burial. If this schedule cannot be met, provide temporary
cathodic protection as noted in 5.2.7 above.
5.6 Anodes
Page 12 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.6.1 Impressed current anode materials for soil applications shall be high
silicon cast iron according to materials specification 17-SAMSS-007.
Magnesium galvanic anodes for soil applications shall comply with
materials specification 17-SAMSS-006. Design parameters are detailed
in Table II, III and IV below.
Commentary Notes:
3) Consult with the Cathodic Protection & Coatings Unit of CSD for the use
of other types of impressed current anode materials such as mixed metal
oxide or polymer anodes, for use in special applications.
Commentary Note:
Page 13 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.6.3 The minimum anode bed distance from the buried pipeline or adjacent
underground structures shall be according to the rectifier rated output
as follows:
Page 14 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.6.4 Separate adjacent anode beds powered from separate power sources by
a minimum distance of 50 meters.
Page 15 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Page 16 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Page 17 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Commentary Note:
5.7.1 Use oil immersed rectifier units (Type OA enclosure) at all locations
inside hydrocarbon plant areas, within 30 meters of a hydrocarbon
plant perimeter fence (outside), or within 1 km of a coastline. Dry type
air cooled units (Type AA enclosure) may be used at all other
locations. Use rectifier units Type OA or Type AA, per 17-SAMSS-
004 or 17-SAMSS-005.
5.7.4 Do not use DC power supplies with a rated output voltage greater than
100 volts. The sizing of the rectifier shall be optimized and based on
the overall circuit resistance. Rectifier sizes other than those listed in
SAMSS category 17 can be used, but must be approved by the
Supervisor of the Cathodic Protection and Coatings Unit of CSD.
5.8 DC Cables
Page 18 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.8.1 NEC Table 310-16 (90°C rating column) shall be used to determine the
minimum size (allowable ampacity) for HMWPE/HDPE cables. The
cable size shall be corrected for an ambient temperature of 40°C.
5.9.2 Install soil access test stations at 20 meter intervals in paved areas,
directly over the pipeline. See Standard Drawing AB-036907 for soil
access test station details.
5.9.4 For distributed anode systems, install soil access test stations over the
pipeline midway between each pair of anodes, at a location over the
pipeline closest to the anode, and one at the beginning and one at the
end of each pipeline segment.
5.10 Bonding
5.10.1 Provide electrical continuity bonding for buried bolted pipeline fittings
(flanges, flanged valves, etc.).
5.10.3 Limit the minimum bond conductor size to 16 mm² (#6 AWG).
Page 19 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
See Section 5.9.1, 6.4.6, 6.4.9 and 6.6.6 for other negative cable
connection and test station requirements at CP power supply locations.
If the conditions of 5.10.4 overlap, eliminate bonds less than 100m
apart.
5.10.8 Bonding is only required between a crossing pipeline and the outer
pipelines in multiple pipeline corridor. The pipeline corridor must
comply with section 5.10.4.
5.11.1 Electrical isolation of pipelines is required at, but not limited to, the
following locations:
Page 20 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.11.4 Provide bond boxes for all isolating devices. Bonding to piping on the
non-Saudi Aramco plant side of an isolating device shall be through a
variable resistor installed inside the bond box.
Exception:
Bond boxes are not required for isolation devices installed for short
sections of buried piping protected by galvanic anodes (as specified in
5.2.1 above).
5.11.5 Bond wires from adjacent isolating devices at plant terminations may
be terminated in a common bond box.
Page 21 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
Buried portions of all flowlines, trunklines, and testlines shall comply with the
protection criteria detailed in Section 5.5.
Page 22 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
5.12.3.1 Install two magnesium anodes for each inner and outer
patrol road at SSD fence crossings, where bare copper
grounding wires or copper or copper jacketed steel ground
rods are connected to the fence. Install anodes according to
Standard Drawing AA-036352, with the anodes located on
each side of the pipeline and as close to the center of the
patrol road as possible. Locate the galvanic anode 3-pin
test station on the opposite side of the patrol road from the
SSD fence.
Commentary Note:
5.12.3.2 Tie-in the flow lines, trunk lines and test lines to the GOSP
CP system, with the written permission of CP Operations.
Cathodic Protection & Coatings Unit of CSD shall approve
the design. Additional distributed impressed current anodes
and/or an additional CP power source may be required.
Separate negative leads are required for each line.
5.12.3.3 Flow lines, trunk lines, and test lines, inside GOSPs must
comply with Sections 5.6.3, 5.12.1, and 5.12.2 of this
document.
5.12.3.4 Install a one-pin test station for buried pipelines, outside the
GOSP SSD fence on the opposite side of the patrol road.
This one-pin test station is not required if a 3-pin test station
is installed as specified in 5.12.3.1 above.
6 Installation
Page 23 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
6.2.1 General
6.2.1.4 Mark the exact location of the anode bed with a wooden
stake(s) and verify the proper burial depth, before
construction starts. The designated Saudi Aramco design or
construction agency will mark and verify location and
depth, based on information given in the approved
construction drawings.
Page 24 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
6.2.3.4 Install the number one anode at the bottom of the bore hole.
Connect the number one anode to the farthest anode
terminal located on the right hand side of the anode lead
junction box, when facing the front of the box.
Page 25 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
6.3.2 Rectifiers
Page 26 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
6.4 DC Cables
6.4.2 Identify all buried DC cables (anode leads, bond, positive, and negative
cables) by cable route markers according to Standard Drawing AB-
036351.
6.4.3 Inspect all positive cables and lead wires for burial for insulation
damage immediately prior to installation. Inspect with a pulse type
holiday detector set at 18,000 volts DC. Check the holiday detector
according to the manufacturer's instructions and make sure that it has a
valid calibration sticker within six month before operation. Repair of
the insulation for buried positive cable by any method is prohibited.
Above-grade repair connections for anode bed positive cables in splice
boxes are acceptable. See Standard Drawing AA-036145 for cable
splice box details.
6.4.4 Limit buried main positive cable runs (e.g., between rectifier and anode
bed junction box) to 150 meters. Make splices at 150 meter intervals
in above-grade splice boxes. For sections of cable between 150 meters
and 300 meters in length, locate the splice box approximately at the
midpoint. See Standard Drawing AA-036145 for cable splice box
details.
6.4.5 Visually check negative cables and bond cables for buried service for
obvious insulation defects. Repair cables with visible insulation
damage with 3 half-lap layers of plastic vinyl tape over 3 half-lap
layers of rubber tape.
6.4.6 Use thermite welds for all negative drain cable and bond connections
to steel pipes and structures, according to Standard Drawing AB-
036381. Terminate the cable from the pipeline(s) in an individual
above-grade splice or junction box located as close to the connection
point as possible, but away from the pipeline berm. A multipurpose
junction box located in the corridor may be utilized for multiple
pipelines. An individual test lead with marker post is still required at
the negative connection.
Page 27 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
6.4.8 Install individual shunts for each multiple positive and negative cable
circuit, in all junction or bond boxes.
6.5.2 Do not use bare copper conductors when running parallel within 3
meters of a buried pipeline or piping.
6.6.1 Complete the installation of bond box wiring to the new pipeline,
including wire labeling for all bonding station installations, within 7
days from the date the pipeline is covered with backfill, and extend the
connected wiring above grade. Connect the bond wires from the new
pipeline to the crossing or parallel pipelines using temporary
connections, as soon as the wiring is installed on the new pipeline. The
bond station shall be installed and connected within 7 days from the
date the berm over the new pipeline is completed.
Page 28 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
6.6.2 Complete the installation of test lead wiring to the new pipeline,
including wire labeling for all test station installations, within 7 days
from the date the pipeline is covered with backfill. Extend the test
leads above grade, to facilitate CP potential measurements prior to the
installation of the test stations. The test station shall be installed and
connected within 7 days from the date the berm over the new pipeline
is completed.
6.6.3 Install test stations, bonding stations, and anode junction boxes in
accordance with the standard drawings listed in Section 3 of this
standard, and at the locations shown on the construction drawings.
Exception:
6.6.4 Identify all cables inside test stations, bonding stations and junction
boxes with durable tags according to Standard Drawing AD-036132.
Label the cable and the terminals (in accordance with the construction
drawings) to indicate the structures to which they are connected.
6.6.5 Provide all bond and junction boxes with an outside and an inside
nameplate indicating the identification number of the rectifier unit or
structure to which they are connected, or both. For positive and
negative junction boxes, this also includes a location schematic
engraved on the nameplate, when required by the proponent.
6.6.6 Install shunts for multiple positive or negative cables in each junction
box for each circuit.
Page 29 of 30
Document Responsibility: Cathodic Protection SAES-X-400
Issue Date: 30 March 2005
Next Planned Update: 1 April 2010 Cathodic Protection of Buried Pipelines
6.8.3 Include guardrail facilities for anode bed junction boxes and watering
pipes at sites where vehicular traffic or other conditions in the area
indicate a high probability of damage.
7.1 Commissioning
7.2 Inspection
Notify Project Inspection and/or the Proponent Operations Inspection before the
start of construction, so that full inspection coverage can be provided during
construction, and especially during anode installations. Provide test data sheets
to the inspection agency for review at least three days, but not more than one
week prior to the start of construction.
8 Records
Update all Construction drawings for any field modifications to the original design to
show the "as built" cathodic protection system. Show the type and location of all
cathodic protection equipment on the as-built drawings. Submit copies of these updated
drawings to the cathodic protection proponent department and the Consulting Services
Department within sixty (60) days of project completion. Complete reported
corrections (if any) within thirty days.
Revision Summary
30 March 2005 Major revision.
Page 30 of 30