You are on page 1of 6

Structural Engineering International

ISSN: 1016-8664 (Print) 1683-0350 (Online) Journal homepage: https://www.tandfonline.com/loi/tsei20

Design of a Curved Incrementally Launched Bridge

Renaud Favre (Prof.), Marc Badoux (Prof.), Olivier Burdet (Dr. sc. techn.) &
Pierre Laurencet (Civil Eng.)

To cite this article: Renaud Favre (Prof.), Marc Badoux (Prof.), Olivier Burdet (Dr. sc. techn.) &
Pierre Laurencet (Civil Eng.) (1999) Design of a Curved Incrementally Launched Bridge, Structural
Engineering International, 9:2, 128-132, DOI: 10.2749/101686699780621064

To link to this article: https://doi.org/10.2749/101686699780621064

Published online: 23 Mar 2018.

Submit your article to this journal

Article views: 7

View related articles

Citing articles: 1 View citing articles

Full Terms & Conditions of access and use can be found at


https://www.tandfonline.com/action/journalInformation?journalCode=tsei20
Design of a Curved Incrementally Launched Bridge
Renaud Favre, Prof.
Marc Badoux, Prof.
Olivier Burdet, Dr. sc. techn.
Pierre Laurencet, Civil Eng.
Swiss Federal Institute of Technology. Lausanne. Switzerland

Summary

Using the example of the lie Falcon Bridge. it is shown that, given proper atten-
tion during design and rigorous quality control during construction, incremental
launching can be used successfully for the construction of a bridge with complex
geometry It is shown that acceptable longitudinal and transversal distortions can
be defined and accounted for in the design of the launching prestressing. The
effects of various systematic errors are considered. and rotation errors are shown
to compound despite match casting. Simple structural considerations are used to
make a preliminary estimate of the launching and guiding forces.

Background very similar in terms of design and


construction. Construction of the
Incremental launching has become north bridge started in spring 1997 and
a widely used bridge construction was completed in summer 1998. Com-
method. particularly in Europe. A de- pletion of the south bridge is sched-
scription of the advantages and limita- uled for summer 1999. The north
tions of incremental launching can be bridge is the subject of this article.
found in [1]. Recent findings have
shown that this construction technique The design of the lie Falcon Bridge was
is very versatile and has a wide range influenced strongly by the decision to Fig. I: lie Falcon Bridge under construction
of applications [2. 3]. Limited at first to use incremental launching for its con-
the construction of relatively simple struction. The superstructure consists of bridge's overall appearance of strength
bridges, incremental launching has a prestressed concrete box girder with and unity [7]. The bridge has expan-
since been used successfully for the 15 spans. The span length increases pro- sion joints at both abutments and is
construction of bridges with increas- gressively from 27.4 m at the abutments stabilised in the longitudinal direction
ingly complex geometry [4. 5]. The lie to 73 m in the central portion over the by fixed bearings at the middle pier.
Falcon Bridge under construction in river (Fig. 2). The girder depth increas-
es from 2.15 m at the abutments to a To prevent scouring, the piers located in
Switzerland exemplifies this trend. or near the Rhone river bed are found-
This long curved concrete bridge fea- maximum of 3.7 m in the middle of the
ed on hollow shafts. The piers are found-
tures varYing span lengths, girder bridge. A typical cross section of the
box girder is shown in Fig. 4. ed on spread footings west of the river
depths and top slab widths [6]. and on pier shafts east of the river. The
The first part of this article presents The girders are supported b' short cir- casting yard situated behind the eastern
the main elements of the structural de- cular piers with a diameter of 5 m. launching abutment is founded on pier
sign of the lie Falcon Bridge. It is fol- i.e. the same as the girder width. The shafts to prevent excessive settlements
lowed by a discussion of three prob- wide circular piers are hydraulically during fabrication and launching oper-
lems of general interest for the design favourable and provide lateral stability ations. The projected bridge cost, un-
of incrementally launched bridges, in to the curved girder during launching der USD 1000/rn2, is relatively low for
particular long curved bridges. and service. They also enhance the a bridge of this type in Switzerland.

LONGITUDINAL SECTION
N1ORTF-I BRIDGE
Design and Launching of the I UNNELS -

lie Falcon Bridge ---- —fl-— - -


-
- —
U --U- H
The LIe Falcon highway bridge crosses
the Rhone river in the mountainous 3i AN
Valais region of Switzerland (Fig A
1—3). The project consists of two paral-
lel curved bridges, which are approxi-
mately 720 m long. Both bridges are -4 -

RHO E
Peer-reviewed by international
experts and accepted by the LABSE
Publications Committee
Fig. 2: Plan viet and elevation of the lie Falcon Bridge

128 Reports Structural Engineering International 2/99


CROSS SECTION A-A

556 - - 52 537

:r5

3oo

Fig. 3: Permanent and temporary piers of the north bridge Fig. 4: Cross section A-A oft/ic north bridge girder

Geometry of the Box Girder curvature. An elegant technique has construction load (1 kN/m2). It was
been developed that uses a casting verified that the tensile stresses do not
The project requirements resulted in a form that can be rotated horizontally exceed 3 MPa when the effects of
girder geometry that is unusually com- to create an angle between two casting launching tolerances (Fig. 6) are added.
plex for an incrementally launched stages. The angle can be used to vary The post-launching prestressing con-
bridge. Vertically. the top slab is the effective curvature over the length sists of parabolic cables placed in the
curved to match the curvature of the of the bridge. (This illustrates the con- girder webs. All longitudinal cables are
roadline (r = 24 900 m). Variable gird- trolled use of the phenomenon dis- comprised of conventional prestress-
er depth was obtained by selecting a cussed below; Fig. 8.) This technique ing bonded with the section through
larger vertical radius of curvature was used at the Schnaittach Bridge. injection. The use of exterior cables
for the intrados of the bottom slab Germany. to launch a section of a with a trapeze trajectory. which could
(r = 60 000 m). Horizontally, the road- bridge girder combining segments of a have served both for the launching and
line consists of a circular middle seg- straight line and of a clothoid [5]. permanent prestressing, was consid-
ment and clothoidal (spiral) end However, variable girder curvature ered. However, this possibility was re-
segments. Because of these clothoidal substantially complicates launching jected because bonded interior pre-
end segments, the roadline does not operations. and launching saddles are stressing has superior behaviour in the
have a constant curvature. The hori- required that can be shifted transver-
zontal girder curvature was neverthe- sally during launching to accommo-
less kept constant in order to avoid date the variable position of the girder.
complicated casting and launching Also. the piers must allow the trans- It
-- is
operations (r = 850 m). The vertical

versal sliding of these launching sad-


and horizontal curvature of the girder dles, and temporary widening of the
result in an intrados shaped as a helix pier caps might be required.
—-

inscribed on a cylinder with an axis


slightly inclined from the vertical [8]. .t

The variable eccentricity between the Longitudinal Prestressing


I3t5-—--——————————' —

alignment of the constant curvature


1
box girder and the roadline was ac- At the Ile Falcon Bridge. the longitudi-
lmL
commodated by allowing the top slab nal prestressing consists of a set of ca-
position to slide laterally with respect bles tensioned prior to launching. aug-
to the box girder. Fig. 5 shows that the mented by cables installed once the
horizontal eccentricity exceeds 1 m in bridge has been launched in its final
some sections. It also shows the longi- position. The centroidal launching pre-
tudinal variations of the top slab width, stressing. consisting of linear cables lo-
the cantilever width. and the girder cated in the top and bottom slabs, cre-
depth. The top slab width varies to ates a uniform state of compression in
accommodate an additional highway the sections. This compression ranges
lane at one end of the bridge. The from 1.8 MPa in the deeper sections to
resulting girder section is. therefore, over 4 MPa in the shallower sections.
very asymmetrical. The geometrical As the girder moves during launching,
complexity of the bridge is atypical for the moments vary, alternating from
incremental launching and demanded positive to negative in each section. 2 t5

an exceptional level of attention at the The launching prestressing is designed 720 96


design and construction stages to define such that the tensile stress would not
and implement the correct geometry. exceed 1 MPa in any point of any
It is possible to build incrementally section of the girder during launching Fig. 5: Iai,, geometrical parameters of the
launched bridges with a variable girder under its self-weight and a nominal north bridge girder

Structural Engineering International 2/99 Reports 129


THEORETICAL AND ACTUAL INTRADOS
the initial frictional resistance at the
launching saddles is overcome. The
ACTUAL &
friction at the launching saddles was
THEORETICAL
INTRADOS THECRETICAL increased in the last launching stages
-J
INTRADOS
by using timber plates instead of
Teflon plates at some of the saddles.
The design of the launching installa-
0 ACTUAL& tion was based on a girder weight of
Z THEORETICAL
SADDLE 200 MN during the final launching
SADOLE = POSITIOR * W SETILEMENT stage. with an average downward slope
— of 2.7%. In the first design scenario
ACTUAL &
THEORETICAL (push mode). a global friction coeffi-
INTRADOS
cient of 4% was assumed and added to
the restraining force of a permanently
acting safety system with a force of
- •WOU
1000 kN. In the second scenario (hold
ACTUAL& - —-
z< THEORETICAL B mode). friction was assumed to he
SADDLE
THEORETICAL zero. The global friction coefficient can
INTRADOS
be evaluated on the basis of the push-
tw..=,, =w, ing and restraining forces measured
during launching. These measure-
Fig.6: Actual and theoretical positions of the inirados in the longitudinal and transversal ments indicate that the global friction
direction during launching did not exceed 5% (initial friction) and
decreased to 1% during movement
ultimate limit state, and requires sig- ing web depth. The specifications (cinematic friction). The global friction
nificantly less prestressing forces be- required a concrete with 360 kg/rn3 of includes the friction at the launching
cause of the higher sag of the cables. CEMI 42.5. and a water/cement ratio saddles and at the lateral guides. Addi-
of less than 0.43. The specified 3-day tional information on the thrust-brake
The parabolic prestressing is designed launching system and launching opera-
to limit long-term midspan deflections compression strength was 30 MPa to
allow tensioning of the transversal tions have been reported [10].
to a maximum of 100 mm. The degree
of compensation for the permanent prestressing in the top slab and of the
load defiections (factor f3) is about longitudinal launching prestressing.
55%. which is a reasonable value for Since the bridge is horizontally curved, Measures to Limit Cracking
an incrementally launched bridge. The a lateral guiding system was required during Construction
low value of f3 for incrementally for launching. Lateral guides were
launched bridges, compared with that placed on every permanent pile, but Incrementally launched bridges are of-
for bridges built by other construction only a limited number (placed about ten subjected during construction to
methods, is due to the important com- every 250 m) were activated. The other some of the most severe loading condi-
pression induced by the launching pre- guides would only have been activated tions that they will experience during
stressing. At the lie Falcon Bridge. the if the girder's alignment had been in- their lifetime [11. 12]. For durability
calculated long-term stresses exceed correct by more than 40 mm. which reasons. it is desirable to prevent, or at
1.5 MPa of compression under perma- was not the case for the north bridge. least limit, cracking of the girder dur-
nent loads. This high level of perma- ing fabrication and launching. Careful
nent compression should limit the Because the road passes directly into a
tunnel at the lower western abutment. attention was given to this issue during
opening of cracks, which are likely to design and construction of the lie Fal-
form during launching [6]. and in order to reduce the launching
forces. the girder was launched from con Bridge. Measures taken to reduce
the higher eastern abutment. Downhill tensile stresses during launching in-
launching requires a launching system cluded the use of a launching nose (26
Construction and Launching of ni long), launching prestressing cables.
that is able to push the bridge to initi-
the Superstructure ate movement and hold it back once and temporary piers. Temporary pre-
cast concrete or timber piers were in-
The launching of the bridge required stalled for spans of 45.6 m or longer.
41 weekly launching stages (38 full AUNCNG 0 RECON The girder's effective slenderness ratio
stages and 3 half stages). The spans 82 is exceptionally high (3.70 m/22.$ m =
were built on a 9.125-m module, and a 0.162) when the deeper portions of the
full launching stage was 18.25 rn long. girder are located in the shorter tem-
The casting sequence is illustrated in porary spans. A typical slenderness ra-
Fig. 7. The girder was cast in three tio for incrementally launched bridges
stages. Each week the U-shaped trough is approximately 0.067. Because of this
of a new stage was cast, together with /
., • SSCO'.CSEE VCV slenderness, the girder was particularly
the top slab of the previous stage and sensitive to differences between the
the parapet of the last-hut-one stage theoretical and actual positions of
PREVIOUS V .CVEE
[9]. Offset casting of the trough and top V

the launching saddles and inirados


slab was required because of the vary- Fig. 7: Casting sequence (Fig. 6). Rigorous requirements were
130 Reports Structural Engineering International 2/99
ELEvA1IO
therefore imposed on the accuracy of problems specific to incrementally
the positioning of the launching saddles launched bridges, three of which are
and on the fabrication of the girder. discussed in the following.
I
In addition, a monitoring system was Systematic Casting Errors
installed so that distortions would be
corrected during launching if they be- One of the key advantages of incre- I
PLAN
came significant. The vertical reactions mental launching is that the construc- VIEW

at the launching saddles were mea- tion is rationalised through the multi-
sured by means of load cells (Fig. 8) ple use of a fixed formwork. A metallic
and compared with calculated values. formwork similar to that used in pre-
Excessive differences indicated distor- cast plants is usually used. and ever' d
tions that could be corrected by the ad- new stage is match cast behind the pre-
dition or removal of stainless steel vious one. The repetition raises the
plates at the sliding interface of the question of the influence on the geom- Fig. 9: Influence of different systematic geo-
launching saddles and girder. The etry of the girder of a systematic cast- metrical errors at casting on the geometry of
largest correction during the launching ing error that is repeated many times. the girder of a in ate/i-cast launched bridge:
of the north bridge required the use of (a) no systematic casting error; (b) skew
Fig. 9 illustrates the influence of four error; (C) warping error: (d) rotation error
a 4-mm-thick shimming plate. types of systematic geometrical form-
In addition to limiting tensile stresses work errors. It shows which types of
due to the launching operations. it is error compound to produce a bridge
important to limit girder stresses gen- position that differs significantly from at the launching abutment tends to-
erated by the thermal shrinkage in the the theoretical position. The actual ward the angle of the systematic error
days following the concreting opera- shape and position of the girder in the (a). A systematic angle error leads to
tions. Of particular concern at the lIe horizontal plane are shown after six the fabrication of a girder with vari-
Falcon Bridge was the effect of the off- launching stages. A straight bridge able curvature. If this error is signifi-
set casting sequence (Fig. 7). The con- with match casting of each new stage cant. the girder's geometry will have to
traction of the top slab is restrained by against the previous one is considered. be corrected by the lateral guiding svs-
the previously cast U-shaped trough. For the sake of simplicity, it is assumed tern. Rigorous topographical control
that, throughout the launching, the lat- of the casting bed is therefore critical,
Self-equilibrating stresses are generat- eral guiding system keeps the girder in particularly for the launching of
ed in the girder that could lead to early its theoretical position at both ends. bridges with a large number of cast-
cracking of the top slab. These stresses but imposes no correction in-between. ing/launching stages.
depend on the heat generation during
the hydration of the cement and on the A skew error does not compound. and Launching Tolerances
temperature differential between the the overall position of the launched
old and the new concrete. Extensive girder is not affected by the systematic Inaccuracies in the positioning of the
numerical simulations of the stresses error. Similarly, a warping error, which launching saddles and in the shape of
generated by thermal shrinkage in the could be a permanent deformation of the girder intrados are a particular
days following concreting were used to the formwork or could result from in- problem for incrementally launched
evaluate the risk of cracking and to fluences such as different exposure of bridges [13]. As the intrados slides
compare possible thermal treatments. the sides of the metallic formwork to over the launching saddles. these inac-
It was decided to cool the formwork of the sun. affects the shape of the girder. curacies can generate undesirable
the top slab by water circulation and, but not its overall position. The errors stresses in the girder. In the case of
in cold weather conditions. to heat the are corrected at each cast, and the geo- concrete bridges, additional tensile
previously cast concrete (U-shaped metrical errors do not exceed that of stresses can increase the risk of girder
section) to between 15 and 25° C. an individual casting stage. cracking. Girders with low slenderness
ratios during launching. such as the lIe
The situation is different for a system- Falcon Bridge. are particularly sensi-
atic rotation error. In this case, the tive to these inaccuracies. Their struc-
Design Issues for Incrementally casting errors accumulate and the axis
Launched Bridges tural effect can be compared to the ef-
of the girder diverges from the its the- fect of differential foundation settle-
oretical position. The divergence in- ments. Because launching is not a slow
The launching of a bridge such as the creases as the number of casting! process. creep cannot reduce the effect
lIe Falcon Bridge raises a number of launching stages increases. The angle of these inaccuracies.
Inaccuracies in the launching saddles
are normall due to inaccuracies in the
implantation of the launching saddles
and to vertical deformations of the
piers (permanent and temporary) and
foundations. Formwork tolerances are
DATA
PROCESSING the primary cause of inaccuracies in
AND the shape of the intrados. Rigorous
CONTROL
CENTER
quality control can reduce the inaccu-
racies. but cannot eliminate them en-
Fig. 8: Monitoring of the bearing loads during launching tirely. A certain level of inaccuracy. i.e.

Structural Engineering International 2/99 Reports 131


___--

tolerance, should therefore be allowed of the girder. In a hold mode (bridge


for in the calculation of the stresses launched downhill). however, the nor-
during launching. For the worst-case mal launching force in the girder
scenario, the inaccuracies in the changes from compression to traction.
launching saddles and intrados com-
bine to give a total inaccuracy (w) at a J 1i R1 and the direction of the guiding forces
is inverted. Lateral guides located on
given launching saddle (Fig. 6). From a the interior face of the girder are re-
structural point of view, it is the differ- quired. A transition from a push to a
ential inaccuracy .iv that matters. In THEORETICAL R1 hold mode is therefore linked with an
the structural model. .;v has a longitu- AXIS OF THE inversion of the direction of the guid-
SUPERSTRUCTURE
dinal component (L\liong) and a trans- ing forces. Such an inversion was ob-
versal component (1t'trans). Fig. 11: Equilibrium of the launching, fric- served at the lIe Falcon Bridge.
At the Ile Falcon Bridge. differential tion and guiding forces during launching of
a curved bridge
inaccuracies of 1VIong = 5 mm and References
L.Ittrans = mm were allowed for in
2
the structural calculations. These low [11 ROSIGNOLI. NI. Incremental Bridge
values are realistic, as confirmed indi- 10 and 11) for a simplified situation. It Launching. Concrete International. Febru-
rectly by the monitoring of the launch- is assumed that the piers are uniformly ary 1997. pp. 36—40.
ing saddle reactions. distributed over the length of the gird-
[2] NIETZLER. H.: HAVERESCH. K.-H.
er, that the saddles are in a horizontal Talbriicke 511/ic — Autobahnhrücke mit ver-
Forces during the Launching of a plane. that the value of the longitudi- starkba rem Langstragsvstem. Beton- und
Curved Bridge nal saddle friction forces is the same at Stahlbeton, Vol. 3. March 1998. pp. 61—o$.
every pier. and that perfectly stiff and
Fig. JO shows the main forces acting in frictionless lateral guides act at every [3] SKEET. J.. LESTER. W.B.. \IcCLARY.
the horizontal plane during the launch- pier. Under these assumptions. the fol- C. Incremental Launch: the Stoner Trail
ing of a curved bridge. Normally. the lowing applies. Bridge. Concrete International, February
1998. pp. 53—57.
launching force is applied along the
girder axis at the launching abutment. The vectorial sum of the longitudinal [4] BEYLOUNE. R. Les viaducs des Vaux.
The friction forces oppose the move- friction forces (R1) can be obtained by Routes et Trafic, Vol. 5. May 1998. pp.
ment at each launching saddle. For a analogy with the calculation of the 163—1 70.
curved bridge, guiding forces perpen- shear flow in an open section (Fig. JO).
The determination of the vectorial sum [5] RIEDMANN. E. Talbriicke Sclznaittach.
dicular to the girder axis are required Beton- und Stahlbeton. Vol. 4, April 1998.
to keep the girder on the right course. of the friction forces becomes a classic
pp. 98—102.
These launching. friction and guiding problem of engineering mechanics.
with the girder corresponding to the [6] FAVRE. R.: LAURENCET. P Viaduc
forces need to be calculated prior to Ile Fa/con — Poussage cadence dun grand
construction in order to design the sub- section and the friction forces (I) to the
shear stresses. Vector R is on a line per- pont a géoinérrie variable. IBAP/ISS/ DGC/
structure and the launching system. EPF-Lausanne. Publication No. 146. June
pendicular to the bisecting line of angle
A preliminary estimate can be made a and passing through the torsion cen- 1998. 36 pp.
on the basis of simple reasoning (Figs. tre of the section. The value and posi- [7] NIANGEAT. V. Ccci ii 'e pas un pont.
tion of R1 are shown in Fig. JO. and the Bulletin Technique de Ia Suisse Romande.
value of the launching force is P = fcc,. Vol.21, October 1998. pp. 37 1—372.
a)
LAUNCHING
The vectorial sum of the lateral guid- [8] GILLET, G.: JACQUET. P. L'ouvrage
DIRECTION LAUNCHING
NOSE ing forces (R1) can be evaluated by ap- 33 sur l'autorouie A55 a Marseille. Annales
I Vol. 468. 1988. pp. 124—128.
plication of the principle of equilib-
• FRICTION
AT THE
rium (Fig. 11). Vector R1 is on a line [9] ROBYR. J.: FAVRE. J. ('onception ci
LAUNCHING
BEARINGS
passing through the centre of the circle construction de ía superstructure. Bulletin
and A (the intersection of the lines Technique de Ia Suisse Romande. Vol. 21.

GUIDING
FORCES
-- LAUNCHING
ABUTMENT
supporting vectors P and R1). The an-
gle between this line and the line pass-
October 1998. pp. 379—382.
[10] PRALONG. C. Le poussage cadence.
ing through the centre of the circle and Bulletin Technique de Ia Suisse Rornande,
the launching abutment is one third of Vol. 21. October 1998. pp. 382—387.
a. This is in agreement with the obser- [11] ROSIGNOLI. NI. Launched Bridges:
TOFSC vation that the lateral guiding forces Prestressed Concrete Bridges built on the
CENTER
are largest near the abutment and de- ground and launched into their final posi-
R1—2Ir-an
crease progressively along the girder tion. ASCE Press, New York. 1998.
toward the front guide. This decrease
matches the decrease of the launching [12] CALGARO. J.A.: VIRLOGEI'X. NI.
force in the girder. which is maximal at Projet et construction des pants — Analyse
sructurale des tabliers des pont. Presses de
the launching abutment and decreases l'Ecoles Nationales des Ponts et Chaussées.
Fig. 10: Qualitative representation of the main
at each launching saddle in proportion Paris. Tome 2. 1994.
ho rizontal plane forces during launching of a
to the saddle's frictional contribution.
[13] ROSIGNOLI. M. li.sJI/acc,nent of
curved bridge: (a) longirudinaifriction forces In the usual push mode (Fig. 10). the Launching Bearings in PC Launched
and transversal guiding forces: (b) vectorial guiding forces are exerted by the later- Bridges. Journal of Bridge Engineering,
sum of i/ic longitudinal friction forces al guides located on the exterior face Vol. 3, November 1998.

I'- R epor S Structural Engineenng International 2/99

You might also like