Professional Documents
Culture Documents
Renaud Favre (Prof.), Marc Badoux (Prof.), Olivier Burdet (Dr. sc. techn.) &
Pierre Laurencet (Civil Eng.)
To cite this article: Renaud Favre (Prof.), Marc Badoux (Prof.), Olivier Burdet (Dr. sc. techn.) &
Pierre Laurencet (Civil Eng.) (1999) Design of a Curved Incrementally Launched Bridge, Structural
Engineering International, 9:2, 128-132, DOI: 10.2749/101686699780621064
Article views: 7
Summary
Using the example of the lie Falcon Bridge. it is shown that, given proper atten-
tion during design and rigorous quality control during construction, incremental
launching can be used successfully for the construction of a bridge with complex
geometry It is shown that acceptable longitudinal and transversal distortions can
be defined and accounted for in the design of the launching prestressing. The
effects of various systematic errors are considered. and rotation errors are shown
to compound despite match casting. Simple structural considerations are used to
make a preliminary estimate of the launching and guiding forces.
LONGITUDINAL SECTION
N1ORTF-I BRIDGE
Design and Launching of the I UNNELS -
RHO E
Peer-reviewed by international
experts and accepted by the LABSE
Publications Committee
Fig. 2: Plan viet and elevation of the lie Falcon Bridge
556 - - 52 537
:r5
3oo
Fig. 3: Permanent and temporary piers of the north bridge Fig. 4: Cross section A-A oft/ic north bridge girder
Geometry of the Box Girder curvature. An elegant technique has construction load (1 kN/m2). It was
been developed that uses a casting verified that the tensile stresses do not
The project requirements resulted in a form that can be rotated horizontally exceed 3 MPa when the effects of
girder geometry that is unusually com- to create an angle between two casting launching tolerances (Fig. 6) are added.
plex for an incrementally launched stages. The angle can be used to vary The post-launching prestressing con-
bridge. Vertically. the top slab is the effective curvature over the length sists of parabolic cables placed in the
curved to match the curvature of the of the bridge. (This illustrates the con- girder webs. All longitudinal cables are
roadline (r = 24 900 m). Variable gird- trolled use of the phenomenon dis- comprised of conventional prestress-
er depth was obtained by selecting a cussed below; Fig. 8.) This technique ing bonded with the section through
larger vertical radius of curvature was used at the Schnaittach Bridge. injection. The use of exterior cables
for the intrados of the bottom slab Germany. to launch a section of a with a trapeze trajectory. which could
(r = 60 000 m). Horizontally, the road- bridge girder combining segments of a have served both for the launching and
line consists of a circular middle seg- straight line and of a clothoid [5]. permanent prestressing, was consid-
ment and clothoidal (spiral) end However, variable girder curvature ered. However, this possibility was re-
segments. Because of these clothoidal substantially complicates launching jected because bonded interior pre-
end segments, the roadline does not operations. and launching saddles are stressing has superior behaviour in the
have a constant curvature. The hori- required that can be shifted transver-
zontal girder curvature was neverthe- sally during launching to accommo-
less kept constant in order to avoid date the variable position of the girder.
complicated casting and launching Also. the piers must allow the trans- It
-- is
operations (r = 850 m). The vertical
—
at the launching saddles were mea- tion is rationalised through the multi-
sured by means of load cells (Fig. 8) ple use of a fixed formwork. A metallic
and compared with calculated values. formwork similar to that used in pre-
Excessive differences indicated distor- cast plants is usually used. and ever' d
tions that could be corrected by the ad- new stage is match cast behind the pre-
dition or removal of stainless steel vious one. The repetition raises the
plates at the sliding interface of the question of the influence on the geom- Fig. 9: Influence of different systematic geo-
launching saddles and girder. The etry of the girder of a systematic cast- metrical errors at casting on the geometry of
largest correction during the launching ing error that is repeated many times. the girder of a in ate/i-cast launched bridge:
of the north bridge required the use of (a) no systematic casting error; (b) skew
Fig. 9 illustrates the influence of four error; (C) warping error: (d) rotation error
a 4-mm-thick shimming plate. types of systematic geometrical form-
In addition to limiting tensile stresses work errors. It shows which types of
due to the launching operations. it is error compound to produce a bridge
important to limit girder stresses gen- position that differs significantly from at the launching abutment tends to-
erated by the thermal shrinkage in the the theoretical position. The actual ward the angle of the systematic error
days following the concreting opera- shape and position of the girder in the (a). A systematic angle error leads to
tions. Of particular concern at the lIe horizontal plane are shown after six the fabrication of a girder with vari-
Falcon Bridge was the effect of the off- launching stages. A straight bridge able curvature. If this error is signifi-
set casting sequence (Fig. 7). The con- with match casting of each new stage cant. the girder's geometry will have to
traction of the top slab is restrained by against the previous one is considered. be corrected by the lateral guiding svs-
the previously cast U-shaped trough. For the sake of simplicity, it is assumed tern. Rigorous topographical control
that, throughout the launching, the lat- of the casting bed is therefore critical,
Self-equilibrating stresses are generat- eral guiding system keeps the girder in particularly for the launching of
ed in the girder that could lead to early its theoretical position at both ends. bridges with a large number of cast-
cracking of the top slab. These stresses but imposes no correction in-between. ing/launching stages.
depend on the heat generation during
the hydration of the cement and on the A skew error does not compound. and Launching Tolerances
temperature differential between the the overall position of the launched
old and the new concrete. Extensive girder is not affected by the systematic Inaccuracies in the positioning of the
numerical simulations of the stresses error. Similarly, a warping error, which launching saddles and in the shape of
generated by thermal shrinkage in the could be a permanent deformation of the girder intrados are a particular
days following concreting were used to the formwork or could result from in- problem for incrementally launched
evaluate the risk of cracking and to fluences such as different exposure of bridges [13]. As the intrados slides
compare possible thermal treatments. the sides of the metallic formwork to over the launching saddles. these inac-
It was decided to cool the formwork of the sun. affects the shape of the girder. curacies can generate undesirable
the top slab by water circulation and, but not its overall position. The errors stresses in the girder. In the case of
in cold weather conditions. to heat the are corrected at each cast, and the geo- concrete bridges, additional tensile
previously cast concrete (U-shaped metrical errors do not exceed that of stresses can increase the risk of girder
section) to between 15 and 25° C. an individual casting stage. cracking. Girders with low slenderness
ratios during launching. such as the lIe
The situation is different for a system- Falcon Bridge. are particularly sensi-
atic rotation error. In this case, the tive to these inaccuracies. Their struc-
Design Issues for Incrementally casting errors accumulate and the axis
Launched Bridges tural effect can be compared to the ef-
of the girder diverges from the its the- fect of differential foundation settle-
oretical position. The divergence in- ments. Because launching is not a slow
The launching of a bridge such as the creases as the number of casting! process. creep cannot reduce the effect
lIe Falcon Bridge raises a number of launching stages increases. The angle of these inaccuracies.
Inaccuracies in the launching saddles
are normall due to inaccuracies in the
implantation of the launching saddles
and to vertical deformations of the
piers (permanent and temporary) and
foundations. Formwork tolerances are
DATA
PROCESSING the primary cause of inaccuracies in
AND the shape of the intrados. Rigorous
CONTROL
CENTER
quality control can reduce the inaccu-
racies. but cannot eliminate them en-
Fig. 8: Monitoring of the bearing loads during launching tirely. A certain level of inaccuracy. i.e.
GUIDING
FORCES
-- LAUNCHING
ABUTMENT
supporting vectors P and R1). The an-
gle between this line and the line pass-
October 1998. pp. 379—382.
[10] PRALONG. C. Le poussage cadence.
ing through the centre of the circle and Bulletin Technique de Ia Suisse Rornande,
the launching abutment is one third of Vol. 21. October 1998. pp. 382—387.
a. This is in agreement with the obser- [11] ROSIGNOLI. NI. Launched Bridges:
TOFSC vation that the lateral guiding forces Prestressed Concrete Bridges built on the
CENTER
are largest near the abutment and de- ground and launched into their final posi-
R1—2Ir-an
crease progressively along the girder tion. ASCE Press, New York. 1998.
toward the front guide. This decrease
matches the decrease of the launching [12] CALGARO. J.A.: VIRLOGEI'X. NI.
force in the girder. which is maximal at Projet et construction des pants — Analyse
sructurale des tabliers des pont. Presses de
the launching abutment and decreases l'Ecoles Nationales des Ponts et Chaussées.
Fig. 10: Qualitative representation of the main
at each launching saddle in proportion Paris. Tome 2. 1994.
ho rizontal plane forces during launching of a
to the saddle's frictional contribution.
[13] ROSIGNOLI. M. li.sJI/acc,nent of
curved bridge: (a) longirudinaifriction forces In the usual push mode (Fig. 10). the Launching Bearings in PC Launched
and transversal guiding forces: (b) vectorial guiding forces are exerted by the later- Bridges. Journal of Bridge Engineering,
sum of i/ic longitudinal friction forces al guides located on the exterior face Vol. 3, November 1998.