You are on page 1of 8

12/4/2018 Balanced Cantilever Method of Bridge Construction

(https://theconstructor.org/)

Balanced Cantilever Method of Bridge Construction

Table of Contents
What is balanced Cantilever method of Bridge Construction?
Procedure for balanced cantilever method of cast-in-situ bridge Construction
Sequence of balanced cantilever method of precast bridge construction
Casting of precast segments
Cast-in-Place Segments Vs precast segments

What is balanced Cantilever method of Bridge Construction?


The balanced cantilever method of bridge construction used for bridges with few spans ranging from 50 to 250m.

×
Get Notifications
The bridge can be either cast-in-place or precast.

Moreover, the basic concept of balanced cantilever construction method is to attach the segments in an alternate
manner at opposite ends of cantilevers supported by piers.

Furthermore, this method is easily adaptable to irregular and long span lengths, congested project sites, rough
and water terrain, rail crossings, and environmentally sensitive areas.

Additionally, it is highly suitable for building cable-stayed bridges. This is because once segments are placed, they
will be supported by new cable-stays in each erection stage. Therefore, no auxiliary supports are required, and
hence it is both economical and practical method for long cable-stayed bridges.

Finally, this article presents balanced cantilever method of bridge construction.

Fig.1: details of cantilever method of bridge construction (Cast in situ segment)

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 1/8
12/4/2018 Balanced Cantilever Method of Bridge Construction

×
Get Notifications
Fig.2: details of cantilever method of bridge construction (precast segments)

Procedure for balanced cantilever method of cast-in-situ bridge


Construction
1- After the construction of lower infrastructure of the bridge is completed, fig.3. Bridge construction begins at
each pier. Special formwork is positioned and cast-in-situ pier segment is begun, fig.4. The complete pier segment
is then used as an erection platform to support a form traveler for cast-in-place segments.

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 2/8
12/4/2018 Balanced Cantilever Method of Bridge Construction

×
Fig.3: construction of lower infrastructure of bridge

Fig.4: Positioning of special formwork


Get Notifications

3- Thereafter, soffit shuttering, shuttering for web & deck shuttering is fixed on both sides of pier as shown in fig.5
and fig.6.

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 3/8
12/4/2018 Balanced Cantilever Method of Bridge Construction

Fig.5: Soffit, web, and Deck shuttering

×
Get Notifications
Fig.6: shuttering soffit, web, and decks

5- Then concreting is done on both sides of the pier as shown in fig.7 and fig.8. The segment production rate for
form travelers is usually one segment every 5 days per traveler.

Cast-in-situ segments range between 3m to 5m in length with formwork moving in tandem with each segment.
Segment construction is continued until a joining midpoint is reached where a balanced pair is closed as
demonstrated in fig.9. The construction of closer section of a bridge is shown in fig.10.

Fig.7: concrete placement

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 4/8
12/4/2018 Balanced Cantilever Method of Bridge Construction

Fig.8: Concrete placement

×
Get Notifications
Fig.9: bridge construction progression

Fig.10: Construction of closer section of the bridge

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 5/8
12/4/2018 Balanced Cantilever Method of Bridge Construction

Sequence of balanced cantilever method of precast bridge


construction
1- Foundations and pier shafts of all permanent piers in the main unit are constructed.

2- Once the piers are built, they are used as an erection platform for precast segments.

Fig.11: Pier construction

3- Assemble and install lifting frame

×
Get Notifications
Fig.12: lifting frame

4- Place first pair of precast segments.

5- Construct wet joints

6- Cure the wet joints

7- Then, install next pair of precast segments. After that, construct and cure joints. This procedure continues till
the end of construction process.

8- Finally, remove the lifting frame.

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 6/8
12/4/2018 Balanced Cantilever Method of Bridge Construction

Fig.13: End span segment o false work

Casting of precast segments


There are two methods for precast segment casting which include:

Short line method: In this rate of segment production is slow. Three or four segments cast at a time.

Long line method: In this rate of segment production is fast. Segments equal to one span cast at a time.

×
Get Notifications
Fig.14: Short line segment casting

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 7/8
12/4/2018 Balanced Cantilever Method of Bridge Construction

Fig.15: Long line segment casting

Cast-in-Place Segments Vs precast segments


Cast-in-place construction proves to be very beneficial when large, considerably heavy segments are
required to be constructed. So, instead of handling the segments, only materials have to be transported thus
influencing the type and size of required equipment.

Alignment variations and corrections are more easily accommodated in cast-in-place construction; but
more corrections will probably be necessary.The increase in alignment corrections for cast-in-place
construction compared to precast construction relates directly to the age of the concrete when loaded. By and
large, the concrete is much younger when loaded in cast-in-place construction.

Madeh Izat Hamakareem

Madeh is a Structural Engineer who works as Assistant Lecturer in Koya University. He is the author, editor and partner at
theconstructor.org.

×
Get Notifications
©2017 The Constructor

https://theconstructor.org/structures/balanced-cantilever-method-bridge-construction/6137/ 8/8

You might also like