REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 42000/-


Valikamam South :- PS Earlalai Sub Office
Owner Ship :- Pradeshiya Sabha, Chunnakam.
G.N.Division :-

1. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT THIDATPULAM CENTRE.

Item Qty Unit Description of Work Rate Amount


No.

01 Item Sum Allow for clearing well site outing


over hanging branches of trees eto. Sum 1050.00

02 3.00 Sqrs Demolistning the damaged portions of


well steining and debris cleared away. 530/- 1590.00

03 0.50 Cube Reconstructing cement concrete block


masonary well steining and parapet
in cement conc. 1:4:5(4/3”) built in
cement mortor 1:5 Rate to include
for scaffolding or adjustrable platform. 9000/- 4500.00

04 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 1500.00

05 3.00 Sqrs Cement plastering ½” thick in cement


Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2250/- 6750.00

06 02 NO Constructing R.C.C.Pillars 9” x 9”
8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00
07 Item Sum Allow for casting and fixing of a
Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00

08 1.00 Sqrs Apron 10 ft x 10 ft (12) 10000/- 10000.00


32390.00

Contingency 5% 1619.50
Price excalation 5% 1619.50
Supervision 1619.50
Vat 10% 3239.00
Others 1512.50
Total 42000.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 25’-0”
© Height of Parapet (From G/L) :- 3’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G., Jafanna.)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 15000/-


Valikamam South :- PS Chunnakam Sub
Owner Ship :- Pradeshiya Sabha, Chunnakam. Office.
G.N.Division :-

2. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT KANTHARODAY CEMETERY.

Item Qty Unit Description of Work Rate Amount


No.

01 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 1500.00

02 1.00 Sqrs Cement plastering ½” thick in cement


Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2000/- 2000.00

03 02 Nos Constructing R.C.C.Pillars 9” x 9”


8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

04 Item Sum Allow for opening up cracks in


existing pillars and repaired same with
ct.mor. 1:3 and making surface to a
good finish as directed. Sum 1500.00
05 Item Sum Allow for casting and fixing of a
Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00
12000.00
Contingency 5% 600.00
Price excalation 5% 600.00
Supervision 600.00
Vat 10% 1200.00

Total. 15000.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 15’-0”
© Height of Parapet (From G/L) :- 2’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G., Jafanna.)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 27500/-


Valikamam South :- PS Chunnakam Sub
Owner Ship :- Pradeshiya Sabha, Chunnakam. Office.
G.N.Division :-

3. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT KOTHIYALADY CEMETERY.

Item Qty Unit Description of Work Rate Amount


No.

01 Item Sum Allow for clearing well site outing


over hanging branches of trees etc. Sum 1000.00

02 0.50 Cube Demolistning the damaged portions of


well steining and debris cleared away. 800/- 400.00

03 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 2000.0

04 0.50 Sqrs Cement plastering ½” thick in cement


Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2000/- 1000.00

05 02 Nos Constructing R.C.C.Pillars 9” x 9”


8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

06 Item Sum Allow for casting and fixing of a


Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00
07 1.00 Sqrs Apron 10-0 ft. X 10-0 ft
in 3” thick ct.conc. 1:2 ½”:5(1”) on
4” thick rublle paving and cement
rendering ½” thick in cement mortor
1:3 finished smooth with cement
slurry. Rate to include for curb-wall
8” x 4” in ct.conc. 1:2 ½” :5(1”)
and necessary excavation for curb
wall. 100000/- 10000.00

21400.00

Contingency 5% 1070.00
Price excalation 5% 1070.00
Supervision 1070.00
Vat 10% 2140.00
Others 750.00
Total 27500.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as per
items embodied in the body of the estimate and as per instruction of Technical Personal
Supervising the work .
(2) (a) Diameter of the well :- 6’-6”
(b) Deptn .of well :- 20’-0”
© Height of Parapet (From G/L) :- 3’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G., Jafanna.)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 34000/-


Valikamam South :- PS Earlalai Sub
Owner Ship :- Pradeshiya Sabha, Chunnakam. Office.
G.N.Division :-

4. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT KADAKADAMBAI CEMETERY.

Item Qty Unit Description of Work Rate Amount


No

01 0.75 Cube Demolistning the damaged portions of


well steining and debris cleared away. 530/- 397.50

02 0.50 Cube Reconstructing cement concrete block


masonary well steining and parapet
in cement conc. 1:4:5(3/4”) built in
cement mortor 1:5 Rate to include
for scaffolding or adjustrable
platform. 9000/- 4500.00

03 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 2000.0
04 1.10 Sqrs Cement plastering ½” thick in cement
Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2000/- 2200.00

05 02 Nos Constructing R.C.C.Pillars 9” x 9”


8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

06 Item Sum Allow for casting and fixing of a


Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00
07 1.00 Sqrs Apro ft. 10-0 X 10-0 ft
in 3” thick ct.conc. 1:2 ½”:5(1”) on
4” thick rublle paving and cement
rendering ½” thick in cement mortor
1:3 finished smooth with cement
slurry. Rate to include for curb-wall
8” x 4” in ct.conc. 1:2 ½” :5(1”)
and necessary excavation for curb
wall. 10000/- 10000.00

26097.50

Contingency 5% 1304.87
Price excalation 5% 1304.87
Supervision 1304.87
Vat 10% 2609.75
Others 1378.14
Total 34000.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 6”-6”
(b) Deptn .of well :- 20’-0”
© Height of Parapet (From G/L) :- 3’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G., Jafanna.)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 47000/-


Valikamam South :- PS Earlalai Sub
Owner Ship :- Pradeshiya Sabha, Chunnakam. Office.
G.N.Division :-

5. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT EIVINAI CEMETERY.

Item Qty Unit Description of Work Rate Amount


No

01 Item Sum Allow for clearing well site outing


over hanging branches of trees etc. Sum 1500.00
02 0.50 Cube Demolistning the damaged portions of
well steining and debris cleared away. 800/- 400.00

03 1.20 Cube Reconstructing cement concrete block


masonary well steining and parapet
in cement conc. 1:4:5(3/4”) built in
cement mortor 1:5 Rate to include
for scaffolding or adjustrable
platform. 9000/- 10800.00

04 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 2500.00

05 2.00 Sqrs Cement plastering ½” thick in cement


Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2250/- 4500.00

06 02 Nos Constructing R.C.C.Pillars 9” x 9”


8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

07 Item Sum Allow for casting and fixing of a


Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00
08 1.00 Sqrs Apron ft. 10-0 X 10-0 ft
in 3” thick ct.conc. 1:2 ½”:5(1”) on
4” thick rublle paving and cement
rendering ½” thick in cement mortor
1:3 finished smooth with cement
slurry. Rate to include for curb-wall
8” x 4” in ct.conc. 1:2 ½” :5(1”)
and necessary excavation for curb
wall. 10000/- 10000.00

36700.00

Contingency 5% 1835.00
Price excalation 5% 1835.00
Supervision 1835.00
Vat 10% 3670.00
Others 1125.00
Total 47000.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 20’-0”
© Height of Parapet (From G/L) :- 3’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G, Jaffna)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 33000/-


Valikamam South :- PS Earlalai Sub
Owner Ship :- Pradeshiya Sabha, Chunnakam. Office.
G.N.Division :-

6. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT THIDATPULAM.

Item Qty Unit Description of Work Rate Amount


No

01 Item Sum Allow for clearing well site outing


over hanging branches of trees etc. Sum 1000.00
02 2.00 Sqrs Demolistning the damaged portions of
well steining and debris cleared away. 530/- 1060.00

03 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 1500.00

04 2.00 Sqrs Cement plastering ½” thick in cement


Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2250/- 4500.00

05 02 Nos Constructing R.C.C.Pillars 9” x 9”


8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

06 Item Sum Allow for casting and fixing of a


Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00
07 1.00 Sqrs Apron ft. 10-0 X 10-0 ft
in 3” thick ct.conc. 1:2 ½”:5(1”) on
4” thick rublle paving and cement
rendering ½” thick in cement mortor
1:3 finished smooth with cement
slurry. Rate to include for curb-wall
8” x 4” in ct.conc. 1:2 ½” :5(1”)
and necessary excavation for curb
wall. 10000/- 10000.00

08 5.00 Lift Semi-circul;ar lead away drain 6”


inch dia in cement conc. 1:2 ½”:5(1”)
laid over 6” thick rubble paving
and ½” thick ct.rendering in cement
mortor 1:3 and finished smooth with
cement slurry. Rate provides for
3” thick curb as directed. 90/- 450.00
25510.00

Contingency 5% 1275.50
Price excalation 5% 1275.50
Supervision 1275.50
Vat 10% 2551.00
Others 1112.50
33000.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 25’-0”
© Height of Parapet (From G/L) :- 3’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G, Jaffna)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 12250/-


Valikamam South :- PS Earlalai Sub
Owner Ship :- Pradeshiya Sabha, Chunnakam. Office.
G.N.Division :-

7. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT THIDATPULAM CEMETERY WELLY.

Item Qty Unit Description of Work Rate Amount


No

01 Item Sum Allow for clearing well site outing


over hanging branches of trees etc. Sum 500.00

02 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 2000.00

03 02 Nos Constructing R.C.C.Pillars 9” x 9”


8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

04 Item Sum Allow for casting and fixing of a


Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00

9500.00

Contingency 5% 475.00
Price excalation 5% 475.00
Supervision 475.00
Vat 10% 950.00
Others 375.00
Total 12250.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred for
the repairs and reconstruction of open dugged well within Vali South PS area as per items
embodied in the body of the estimate and as per instruction of Technical Personal
Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 20’-0”
© Height of Parapet (From G/L) :- 2’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G, Jaffna)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 28000/-


Valikamam South :- PS Uduvil Sub
Owner Ship :- Pradeshiya Sabha, Chunnakam. Office.
G.N.Division :-

8. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT THAVADY HINDU CEMETERY.

Item Qty Unit Description of Work Rate Amount


No

01 Item Sum Allow for clearing well site outing


over hanging branches of trees etc. Sum 1000.00
02 2.00 Sqrs Demolistning the damaged portions of
well steining and debris cleared away. 800/- 200.00

03 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 1500.00

04 02 Nos Constructing R.C.C.Pillars 9” x 9”


8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

05 Item Sum Allow for opening up cracks in


existing pillars and repaired same with
ct.mor. 1:3 and making surface to a
good finish as directed. Sum 750.00

06 Item Sum Allow for casting and fixing of a


Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4200.00
07 1.00 Sqrs Apron ft. 10-0 X 10-0 ft
in 3” thick ct.conc. 1:2 ½”:5(1”) on
4” thick rublle paving and cement
rendering ½” thick in cement mortor
1:3 finished smooth with cement
slurry. Rate to include for curb-wall
8” x 4” in ct.conc. 1:2 ½” :5(1”)
and necessary excavation for curb
wall. 10000/- 10000.00

08 10.00 Lift Semi-circul;ar lead away drain 6”


inch dia in cement conc. 1:2 ½”:5(1”)
laid over 6” thick rubble paving
and ½” thick ct.rendering in cement
mortor 1:3 and finished smooth with
cement slurry. Rate provides for
3” thick curb as directed. 90/- 900.00
21550.00

Contingency 5% 1077.50
Price excalation 5% 1077.50
Supervision 1077.50
Vat 10% 2155.00
Others 1062.50

28000.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 25’-0”
© Height of Parapet (From G/L) :- 1’-6”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 0’-6”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G, Jaffna)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 61500/-


Valikamam South :- PS Uduvil Sub Office
Owner Ship :- Pradeshiya Sabha, Chunnakam.
G.N.Division :-

9. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT INUVIL MARKET (MARUTHANARMADAM )

Item Qty Unit Description of Work Rate Amount


No.

01 Item Sum Allow for clearing well site outing


over hanging branches of trees eto. Sum 1500.00

02 1.00 Cube Demolistning the damaged portions of


well steining and debris cleared away. 800/- 800.00

03 2.25 Cube Reconstructing cement concrete block


masonary well steining and parapet
in cement conc. 1:4:5(4/3”) built in
cement mortor 1:5 Rate to include
for scaffolding or adjustrable platform. 9000/- 20250.00

04 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 1500.00

05 3.25 Sqrs Cement plastering ½” thick in cement


Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2100/- 6825.00

06 02 NO Constructing R.C.C.Pillars 9” x 9”
8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00
07 Item Sum Allow for casting and fixing of a
Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00

08 1.00 Sqrs Apron 10 ft x 10 ft (12) 10000/- 10000.00


47875.00

Contingency 5% 2393.75
Price excalation 5% 2393.75
Supervision 2393.75
Vat 10% 4787.50
Others 1656.25
Total 61500.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 20’-0”
© Height of Parapet (From G/L) :- 3’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G., Jafanna.)
REPAIRS OR RECONSTRUCTION OF OPEN WELLS – 2003

Source of Fund :- Neerp Amount:- 46000/-


Valikamam South :- PS Earlalai Sub Office
Owner Ship :- Pradeshiya Sabha, Chunnakam.
G.N.Division :-

10. ESTIMATE OF EXPENSES NECESSARY TO BE INCURRED FOR REPAIRS AND


RECONSTRUCTION OF A WELL AT MYLANKADU KUPPILAN SOUTH.

Item Qty Unit Description of Work Rate Amount


No.

01 1.50 Cube Demolistning the damaged portions of


well steining and debris cleared away. 800/- 1200.00

02 1.25 Cube Reconstructing cement concrete block


masonary well steining and parapet
in cement conc. 1:4:5(4/3”) built in
cement mortor 1:5 Rate to include
for scaffolding or adjustrable platform. 9000/- 11250.00

03 Item Sum Allow for bailing out water during


construction and after completion. Rate
also include for clanning well after
completion. Sum 1500.00

04 2.00 Sqrs Cement plastering ½” thick in cement


Mortor 1:3 to all exposed surface of
Steining and parapet. Rate includes
For scaffolding of platform. 2250/- 4500.00

05 02 No Constructing R.C.C.Pillars 9” x 9”
8’-0” ft .high above G.L.and 2’-6”
ft . below ground level reinforced with
5/8” 0 Tore steel at center. Rate to
include for excavation for pillars and
Ct. Conc.1:3:6-1 ½” –9” thick for
Foundation. Rate also include for
Cement plastering ½” thick in Ct.
Mtr, 1:3 to all exposed faces of
Pillars. 1500/- 3000.00

06 Item Sum Allow for casting and fixing of a


Pre-Cast R.C.C.beam in Ct. Conc
1:2:4 ¾” reinforced with 2 Nos 3/8”
0 T-Bars at bottom and 2 Nos ¼” 0
M.S.bars at top with ¼” 0 stirrups
At 12” CRS. Rate includes for ½”
Thick cement rendering in ct.mtr.1:3
Rate also include for supplying and
Fixing 9”0 appd. Heavy quality pully
Chain/Nylon rope and 10” dia GI
Bucket as directed. Sum 4000.00
07 1.00 Sqrs Apron 10 ft x 10 ft (12) 10000/- 10000.00

08 5.00 Lft Semi-Circular lead away drain 6”


inch dia an cement conc. 1:2 ½”:5(1”)
laid over 6” thick rubble paving
and ½” thick ct. rendering in cement
mortor 1:3 and finished smooth with
cement slurry. Rate provides for
3” thick curb as directed. 90/- 450.00

35900.00

Contingency 5% 1795.00
Price excalation 5% 1795.00
Supervision 1795.00
Vat 10% 3590.00
Others 1125.00
Total 46000.00

Specifications:-
(1) This Estimate provides for all materials labour and transport necessary to be incurred
for the repairs and reconstruction of open dugged well within Vali South PS area as
per items embodied in the body of the estimate and as per instruction of Technical
Personal Supervising the work .
(2) (a) Diameter of the well :- 8’-0”
(b) Deptn .of well :- 20’-0”
© Height of Parapet (From G/L) :- 3’-0”
(d) Height of pillars (From G/L) :- 8’-0”
(e) Thuekness of steining :- 1’-0”

Prepared By:-

Checked By:-

Approved By:

Recommended By:-

(R.A.C.L.G., Jafanna.)