Professional Documents
Culture Documents
MS Legok Nangka Booklet PDF
MS Legok Nangka Booklet PDF
Provincial Government
Market Sounding of
Waste to Energy PPP Project
Legok Nangka Regional Final Waste
Treatment and Processing Site
Supported by:
Table of Contents
Table of Contents............................................................................................................. 1
Preface ............................................................................................................................ 2
Glossary .......................................................................................................................... 3
1. Project Background, Objective, and Profile ........................................................................... 5
1.1. Background ..............................................................................................................................................5
1.2. Objectives ................................................................................................................................................5
1.3. Profile.......................................................................................................................................................6
1.4. Project Organization ................................................................................................................................6
2. Site Information and Permits ................................................................................................ 7
2.1. Site Location ............................................................................................................................................7
2.2. Water Supply ...........................................................................................................................................8
2.3. Transmission Line ....................................................................................................................................8
2.4. EIA/AMDAL and SIPPA .............................................................................................................................9
2.5. Fly Ash and Bottom Ash (FABA) treatment .............................................................................................9
3. Project Scheme .................................................................................................................. 10
3.1. Project Scope ........................................................................................................................................ 10
3.2. Contractual Structure ........................................................................................................................... 11
3.3. Commercial Structure ........................................................................................................................... 11
3.4. Revenue Stream ................................................................................................................................... 12
4. Risk Allocation and Government Support ............................................................................ 13
4.1. Risk Allocation ...................................................................................................................................... 13
4.2. Government Support ............................................................................................................................ 14
5. MSW Information............................................................................................................... 14
5.1. MSW Supply Commitment ................................................................................................................... 14
5.2. MSW Quality ......................................................................................................................................... 15
5.3. MSW Logistics ....................................................................................................................................... 15
5.4. Unsuitable Waste ................................................................................................................................. 16
6. General Technical Requirement .......................................................................................... 16
6.1. Open Technology .................................................................................................................................. 16
6.2. Output Specification ............................................................................................................................. 17
6.3. Technology Block Diagram ................................................................................................................... 19
7. Schedule ............................................................................................................................ 20
7.1. Overall Schedule ................................................................................................................................... 20
7.2. Procurement Process............................................................................................................................ 20
7.3. PQ Timeline........................................................................................................................................... 21
Appendix: Questionnaire Feedback Form ............................................................................... 22
Preface
This Market Sounding Booklet provides the information necessary to introduce the market
regarding “Legok Nangka Regional Final Waste Treatment and Processing Site PPP Project” (“the
Project”) in West Java Province.
The market sounding was conducted based on LKPP Regulation No. 29/2018 on Procurement
Procedures of Business Entities for Cooperation between the Government and Business Entities.
The market sounding is held with the purpose of 1) providing information to the market, 2)
assessing market interest, and 3) obtaining input and feedback from the potential investors on the
feasibility of the project.
The booklet provides facts and analysis regarding the project which are as follows:
• Project Background, Objective, and Profile
• Site Information and Permits
• Project Scheme
• Risk Allocation and Government Support
• MSW Information
• General Technical Requirement
• Schedule
Feedback are expected from the market as provided in the Questionnaire Feedback Form attached
to Appendix of this document.
Term Definition
CP Condition Precedent
EU European Union
PQ Pre-Qualification
1.1. Background
The Province of West Java has a large and increasingly urbanized population. It is expected
to grow from 46 million to over 57 million by 20351. Population growth, combined with growing
per capita incomes and associated changes in consumption patterns, will result in much
greater demand for Municipal Solid Waste (MSW) management services. This will represent
a major challenge for the Province as current final disposal site at Sarimukti will not be
available beyond 2023/2024.
To address the urgent challenges associated with MSW management, the West Java
Provincial Government plans to develop the Legok Nangka Regional Final Waste Treatment
and Processing Facility through a Public Private Partnership procurement (“The Project”). The
project will provide a facility for the final treatment and processing of MSW from six
Participating Municipalities, which are Bandung City, Bandung Regency, Sumedang
Regency, Cimahi City, Garut Regency and West Bandung Regency.
The project will be implemented by West Java Provincial Government as the Government
Contracting Agency (“The GCA”) under Perpres No. 35/2018 on Acceleration of Development
of Environmentally Friendly Waste to Energy Power Plant and Perpres No. 38/2015 on
Cooperation between the Government and Business Entity. Other relevant legal basis
includes, but not limited to:
• West Java Provincial Local Government Regulation Number 12 of 2010 as
amended with West Java Provincial Local Government Regulation Number 1 of
2016 on Waste Management in West Java Province.
1.2. Objectives
The GCA has developed Project objectives that align with wider sector regulations and
specific waste management needs of the Participating Municipalities. The objectives are as
follows:
1. Build facility for the final MSW treatment and processing for the City of Bandung,
Cimahi City, Bandung Regency, West Bandung Regency, Sumedang Regency and
Garut Regency;
2. Improve the sanitation and health conditions in the Participating Municipalities;
3. Support the concept of a circular economy and implement Waste to Energy (WtE)
operations.
Electricity
Min. 15 MW (gross)
Generation
From 6 Municipalities
Waste Supply (Bandung City, Cimahi City, Bandung Regency, Sumedang Regency, West
Bandung Regency, Garut Regency)
Funding Scheme PPP (Build-Operate-Transfer for 20 years concession period after COD)
Bandung City
Legend
TPPAS Legok Nangka
Boundary of Municipality
Major Road
Railway
Some supporting facilities have been built within the Legok Nangka WtE plant. These
supporting facilities include the landfill, the leachate treatment, and some auxiliary
infrastructure such as the road, gate, and fences. The landfill and the leachate treatment
facility were built by Ministry of Public Works and Housing (MPWH). The GCA is currently
undergoing asset transfer process from MPWH.
Around 20 ha of the land in the complex has been allocated as the WtE plant Plot, where SPC
would need to build the waste to energy plant. Project site map and several supporting
facilities can be further seen in the figure below:
GCA is currently in the process of building raw water intake facility from Mount Kareumbi
Masigit which is located approximately 10 km north of the Project Site. The detailed
engineering design (DED) is being developed by GCA and is aimed to be finished in 2019.
The facility is planned to be constructed starting from 2020 and completed in 2021.
1) EIA/AMDAL
• Environment Impact Assessment (EIA) and Public Consultation process has been
conducted and GCA is currently completing AMDAL process and applying for an
Environmental Permit for the purposes of the Project.
• EIA/AMDAL is prepared by the GCA based on reference technology and its
associated output analysis. The SPC shall amend the EIA/AMDAL and the
Environmental Permit if there are changes to the technology or output specification
that may have different environmental impact.
2) SIPPA
• The GCA is currently developing the DED for water supply facilities. Based on this
DED, GCA plans to obtain SIPPA permit. This permit will allow GCA to take raw
water up to 10 liter per seconds (860 m3) to be used for the Project. Water intake
facility itself is planned to be completed by 2021.
Design &
Financing Operation & Maintenance
Construction
1. Land acquisition for Project Site, transmission line 5. MSW supply to site and Unsuitable
and substation, water supply facility Materials removal prior to site delivery
GCA
2. Water supply pipping to TPPAS Legok Nangka site
3. Landfill and leachate treatment facility (incl. FABA transfer to Landfill)
4. Supporting infrastructure (road, rainwater drainage, etc.) in TPPAS complex but outside of WTE
plot
Note: 1) PLN may exercise its rights to take over the ownership of special facility (transmission line), in which,
the O&M responsibility will be borne by PLN.
Source: FBC of Legok Nangka Regional TPPAS PPP Project (2019)
After the concession period, SPC is obliged to handover the asset back to GCA in a sufficient
condition.
APBD
Guarantee
approval
2) FIT
FIT will be paid by PT PLN to SPC for electricity generation. In pursuant to Article 11 of
Presidential Regulation 35/2018, the price of electricity purchase by PT PLN will depend
upon the amount of WtE facility capacity for electricity sales to PT PLN under the terms
as follows:
a) For WtE facility with capacity up to 20 MW, the FIT will be US 13.35 cent/kWh;
b) For WtE facility with capacity more than 20 MW, the FIT will be calculated based
on the formula below:
The FIT paid by PT PLN is inclusive of all cost incurred for network procurement from
WtE facility to PT PLN and will be without escalation.
Aside from these two primary revenue streams, SPC is also permitted to receive
additional revenue from third party by selling its residual products. However, the
expected revenue depends on the choice of technology and market demand.
Note: *) General risk allocation direction shows which party has the most risk allocated to them within certain
category. Thus, this does not necessarily suggest that one party shall bear all risks within the category.
Source: FBC of Legok Nangka Regional TPPAS PPP Project (2019)
2) IIGF Guarantee
GCA is currently applying for government guarantee through IIGF. As next step, GCA will
need to submit Guarantee Application Package (GAP) to IIGF. If the application is
approved, IIGF will guarantee GCA’s breach of financial obligation.
5. MSW Information
Sumedang Regency 28 – 32
54.07% 1400
60.97% 58%
Calorific Value
60% 1200
(kcal/kg)
1000
40% 800
29.09% 33.62% 31% 600
20% 400
0% 9.94% 12.31% 11% 200
0
Rainy Season Dry Season Average
Rainy Season Dry Season Average
Ash Volatile Moisture
Hazardous Textile , Rubber,
Waste , 4.80% 0.64%
Rubber, Hazardous Rubber, 0.12% Mineral,
Hazardous 0.71% Mineral, 0.58% Other, 1.15%
Mineral, Waste , 1.40%
Waste , Textile , Other, 1.48% 1.48% Textile , Other, 0.82%
1.32% 0.18% 4.29% Glass, 0.77%
0.06% 5.31%
Glass, 0.70%
Glass, 0.83% Metal,
Metal, 0.25%
Metal,
0.22% Paper, Paper,
0.27% Paper,
Kitchen 7.80% Disposal 7.03% Kitchen
6.25%
Disposal
Waste ;
Kitchen Nappies, Waste ;
35.56% Disposal 7.13% 40.00%
Nappies, Waste ;
Nappies, 44.44%
6.47%
7.78%
Non-
Non- Non-
Recyclable Recyclable Recyclable
Plastic , Plastic , Plastic ,
26.45% Leaves / 23.50% 24.97% Leaves /
Garden , Garden ,
13.53% 10.00%
Leaves /
Recyclable Recyclable Garden , Recyclable
Plastic, Plastic, 6.47% Plastic,
1.88% 1.60% 1.74%
Rainy Season Waste Composition Result Dry Season Waste Composition Result Combined Waste Composition Result
incombustible
Other/Unsuitable landfill
material
2
Waste Acceptance Unsuitable
and Sample Sorting
3
Off-taking
5
Emission Gas
Processing 6
System Waste Water
4 7
Electricity Stench, Noise,
Generation Vibration
8
FABA
On-Site
Landfill
Input / Output
The diagram above defines 8 types of key inputs and outputs of the project. For each of the 8
items, we define the general technical specification below in the table:
No Flow Requirement/Specification
1 MSW Daily average (calculated on monthly basis):
1,853 ton/day – 2,131 ton/day for 365 days/year
2 Unsuitable The Government has agreed not to deliver Unsuitable Waste to
Waste Legok Nangka. However, small amount of Unsuitable Material could
still get through and delivered to the site. Therefore, a “Sample
Sorting” is required.
3 Off-taking Off-taking is defined as by-product that does not go to the entire
Processing System and can be sold to external parties.
Consequently, this by-product does not go to Legok Nangka
Landfill.
4 Electricity Min. 15 MW (gross capacity). Transmission line of 11.8 km to PLN
Generation Parakan Muncang substation
5 Emission Gas The Emission Standards of the Waste to Energy Facility must be in
accordance to the EU emission standards.
6 Waste Water The Facility Waste Water disposal must be in accordance with the
relevant Indonesian Standards
7 Stench, Noise, The Stench, Noise, and Vibration generated by the facility must be
Vibration in accordance with relevant Indonesian Standards
It is expected that private investors will consider and propose the most suitable technology,
or combination of technologies, to fulfil this specification in a most reliable, sustainable and
cost-efficient way.
Further details of the specification will be provided in the RfP document including minimum
requirements and guidelines for design, construction, testing and commissioning, O&M and
asset handover at the end of concession period.
2 Ignition
Loss refers to the mass loss of a combustion residue whenever it is heated in an air or
oxygen atmosphere to high temperatures. The degree of Ignition Loss is expressed as % of mass
remains after the combustion process.
Market Sounding Booklet 18
Legok Nangka Regional Final Waste Treatment And Processing Site PPP Project
6.3. Technology Block Diagram
Since the project will conduct tender under open technology principles, bidders are required
to clearly indicate their technology selection in the form of Technology Block Diagram. This
will be required at PQ stage so that the track record can be assessed for the selected
technology.
Information to be provided include the block of technology, configurations of the blocks, and
information on material balance and expected electricity generation. Example of the diagram
is shown in the figure below:
Pattern 1 shows single technology block for WtE process. Bidder will need to provide the
processing technology to be used for this WtE process.
Pattern 2 shows example of technology block combination. In this example, we show a case
of MBT and off-taking of compost and RDF prior to WtE process.
In order to obtain market input and feedback on the Project, the GCA invites you to respond to the
questions described below. We sincerely request that your responses are received before the
end of day of 31st October 2019 by e-mail to pstrdlh@gmail.com with the subject “Legok Nangka
WtE PPP Project – Response to Market-Sounding Document”.
Upon receipt of all feedback, the GCA may invite some of the respondents for direct discussions,
if necessary, to clarify relevant contents in the feedback response.
All response documents and direct discussions will be treated as strictly confidential.
D. Other Comments/Feedback
Please feel free to provide any other comments/feedback not covered in above list of
questions.