Volume 1: Road

NO. Name Title Pages Size Remark


01 DL-00 Drawing Lists
02 DL-01 General Specification
03 DL-02 General Layout Plan
04 DL-03 Curve Summary
05 DL-04 Line Curve & Transaction Angle
06 DL-05 Flyover Plan
07 DL-06 Chainage Coordintes
08 DL-07 Road Vertical Section
09 DL-08 Road Typical Cross Section
10 DL-09 Excavation Cross Section
11 DL-10 Excavation and Backfilling
12 DL-11 Pavement Structure
13 DL-12 Pavement Quantity Summary
14 DL-13 Retaining Wall Elevation
15 DL-14 Retaining Wall Configuration
16 DL-15 Slope Stability Protection
17 DL-16 Protective Barrier Detail
18 DL-17 Flyover Control Line
Volume 2: Bridge Ramp C
No. Name Title Pages Size Remark
01 QL-00 Drawing Lists of Bridge Ramp C
02 QL-01 Design Specification of Bridge Ramp C
03 QL-02 Summary Table of Major Project Quantity of Bridge Ramp C
04 QL-03 Plan of Construction Site of Bridge Ramp C
05 QL-04 Bridge Ramp C Layout Plan
06 QL-05 Coordinate Plan of Pile Foundation of Bridge Ramp C
07 QL-06 General Arrangement of Abutment C0
08 QL-07 General Arrangement of Pier
09 QL-08 Rebar Arrangement of Pile Foundation
10 QL-09 Rebar Arrangement of Abutment
11 QL-10 Rebar Arrangement of Connection Beam
12 QL-11 Rebar Arrangement of Pile Cap
13 QL-12 Rebar Arrangement of Pier Column
14 QL-13 Rebar Arrangement of Bent Cap
15 QL-14 General Arrangement of 1st Section Box-girder
16 QL-15 General Arrangement of 2nd Section Box-girder
17 QL-16 Setting out Coordinate of Box-Girder
18 QL-17 Pre-stressed Rebar Arrangement of 2nd Section Box-girder
19 QL-18 Rebar Arrangement of 1st Section Box-girder
20 QL-19 Rebar Arrangement of 2nd Section Box-girder
21 QL-20 Rebar Arrangement of Beam Box-Girder
22 QL-21 Rebar Arrangement of Middle Diaphram
23 QL-22 Detail Notch and Anchorage of 2nd Section Box-Girder
24 QL-23 Bearing Support Arrangement of Bridge Ramp C
25 QL-24 Rebar Arrangement of Bottom Wedge And PadStone
26 QL-25 Rebar Arrangement of Restain Block of Bottom Box-Girder
27 QL-26 Structure and Rebar of Barrier and Steel Handrail on Box-girder
28 QL-27 Rebar Arrangement of Deck Pavement
29 QL-28 General Arrangement of Expansion Joints
30 QL-29 Detail Londitudinal Joints Between Bridge Ramp C And Exisiting Flyover Bridge
31 QL-30 Detail Drainage System of Bridge Ramp C
32 QL-31 Rebar Arrangement of Approach Slab
33 QL-32 Rebar Arrangement of Construction Opening
Volume 3: Drainage System
No. Name Title Pages Size Remark
01 GP-00 Drawing List of Drainage System
02 GP-01 Design Specification of Drainage Sytem
03 GP-02 Table Main Equipement and Material
04 GP-03 Road Standard Cross Section Piping Arrangement
05 GP-04 Existing and New Design Drainage System Layout plan
06 GP-05 Longitudinal Profile of New Design Drainage System
07 GP-06 Detail Manhole and Water pipe along Ramp E
08 GP-07 Detail Manhole and Water pipe Under Ramp C
09 GP-08 Detail Manhole and Water pipe along Ramp D
Volume 4: Lighting System
No. Name Title Pages Size Remark
01 DQ-00 Drawing List of Lighting System
02 DQ-01 Table Main Equipement and Material
03 DQ-02 Design Specification
04 DQ-03 General Lighting System Layout Plan
05 DQ-04 Detail Lighting Pole Component
06 DQ-05 Detail Lighting Pole Elevation
07 DQ-06 Detail Foundation of Lighting Pole
08 DQ-07 Detail Electricity Cabinet and Foundation
09 DQ-08 Diagram Lighting System for Electricity Cabinet
10 DQ-09 Wiring Diagram of Lighting System
Method Statement of Project MFI
NO. Name Title Pages Size Remark
01 MMS-00 Method Statement Lists
02 MMS-01 Method Bored Pile Foundation
03 MMS-02 Method Changing location of Cable Optic and Electric
04 MMS-03 Method Expand Temporary Road along Ramp E
05 MMS-04 Method Driving Sheet Pile for C1, C4, & C5
06 MMS-05 Method Formwork Support for Foundation
07 MMS-06 Method Formwork Support for Column
08 MMS-07 Method Formwork Support for Bent Cap
09 MMS-08 Method Formwork Support for 1st Section Box-Girder By Steel Tube
10 MMS-09 Method Formwork Support for 2nd Section Box-Girder By Steel H-Section
11 MMS-10 Method Bearing Support Installation
12 MMS-11 Method Coring Concrete Test
13 MMS-12 Method Pavement and Subgrade Capacity Test
14 MMS-13 Method Pre-stressed Installation
15 MMS-14 Method Repair Retaining Wall at Location C1
16 MMS-15 Method Parapet Formwork Support and Steel Handrail Installation
17 MMS-16 Method Construction Opening for Box-Girder
18 MMS-17 Method Expansion Joints Installation
19 MMS-18 Method Rubber Cushion Installation
20 MMS-19 Method Remove Formwork Support of Steel H-Section
21 MMS-20 Method Excavation for Drainage System along Ramp E
22 MMS-21 Method Repair Demaged Concrete for 2nd Section Box-girder
23 MMS-22 Method Coring Box-Girder and Exchange Steel Strain
24 MMS-23 Method Construction Work for Retaining Wall 1 & 2
25 MMS-24 Method General Pavement work and Improvement
26 MMS-25 Method Concrete Curb Installation
27 MMS-26 Method Load Test for Flyover Bridge Ramp C