CHINA CONSTRUCTION (S.E.

A)
(CAMBODIA) CORPORATION Ltd
#86, Street Nakry, Sangkat Terk Tla,
Khan Sen Sok, Phnom Penh, Cambodia.

FTB PROJECT

METHOD STATEMENT
BRICK WALL
RETAIL
RC COLUMN Metal strap @1200 RC COLUMN
FFL
240, ANINA Building, St.271, Sangkat Beoung
Tumpun,Khan Meanchey, Phnom Penh
www.chipmong.com
Vary

33th FL.RS TOWER, 121/92 RATCHADAPHISEK RD.


BANGKOK 10400, THAILAND
TEL. 0-2642-3330[7Lines] , FAX. 0-2642-2138
Website:http://www.ma-ar.com
Max. 7000

Qbic Engineers & Architects Co.,Ltd.


8 Soi KALONG 4 SANAMBINNAM RD.
NONTABURI Tel.0-2950-4374-5
Fax: 0-2580-3231
E-Mail : qbic@qbic.co.th

MEP FRAME

Ø10@400

RC STIFFENER
FOR WALL
1168/8 12th FLOOR, LUMPINI TOWER BUILDING,

FFL RAMA IV RD. THUNGMAHAMEK, SATHORN,


BANGKOK 10120, THAILAND TEL:0-2679-9079-84
FAX:0-2679-9085 E-mail:mitr_dd@mitr.com.

SFL

≤5000 VARY

max. 8000

CHINA CONSTRUCTION (S.E.A)


TYPICAL ELEVATION OF STIFFENER & LINTEL FOR BRICK WALL 200 (H=max 7m) TYPICAL of Brick wall at Secure area (Grout Unit masonry) TYPICAL of Brick wall elevation at Secure area (Grout Unit masonry) (CAMBODIA) CORPORATION Ltd
#86, Street Nakry, Sangkat Terk Tla,
Khan Sen Sok, Phnom Penh, Cambodia.
(FOR OUTER WALL WITH THICKNESS 200mm) (Wall thickness 150mm) (Wall thickness 150mm)

D' D C B

Metal strap @1200 RC COLUMN


FFL
Vary
Max. 7000

DOOR HEIGHT

MEP FRAME MEP FRAME

Ø10@400

FFL

SFL

TYPICAL ELEVATION OF STIFFENER & LINTEL FOR BRICK WALL 200 (H=max 7m)
(FOR INNER SIDE WALL WITH THICKNESS 200mm)
CHINA CONSTRUCTION (S.E.A)
(CAMBODIA) CORPORATION Ltd
#86, Street Nakry, Sangkat Terk Tla,
Khan Sen Sok, Phnom Penh, Cambodia.

FTB PROJECT

METHOD STATEMENT
CELLING
RETAIL

240, ANINA Building, St.271, Sangkat Beoung

NOTE: TYPICAL DETAIL FOR GRILLE CEILING OF T-BAR (C113)


Tumpun,Khan Meanchey, Phnom Penh
www.chipmong.com

33th FL.RS TOWER, 121/92 RATCHADAPHISEK RD.


BANGKOK 10400, THAILAND
TEL. 0-2642-3330[7Lines] , FAX. 0-2642-2138
Website:http://www.ma-ar.com

Qbic Engineers & Architects Co.,Ltd.


8 Soi KALONG 4 SANAMBINNAM RD.
NONTABURI Tel.0-2950-4374-5
Fax: 0-2580-3231
E-Mail : qbic@qbic.co.th

1168/8 12th FLOOR, LUMPINI TOWER BUILDING,


RAMA IV RD. THUNGMAHAMEK, SATHORN,
BANGKOK 10120, THAILAND TEL:0-2679-9079-84
FAX:0-2679-9085 E-mail:mitr_dd@mitr.com.

CHINA CONSTRUCTION (S.E.A)


(CAMBODIA) CORPORATION Ltd
#86, Street Nakry, Sangkat Terk Tla,
Khan Sen Sok, Phnom Penh, Cambodia.

TYPICAL SECTION

WALL ANGLE

WALL

CONNECT WALL ANGEL WITH BRICK WALL DETAIL SKETCHUP FRAME SYSTEM CEILING T-BAR (C113)
NOTE: TYPICAL DETAIL FOR MOISTURE-PROOF GYPSUM BOARD CEILING OF C-BAR RETAIL

240, ANINA Building, St.271, Sangkat Beoung


Tumpun,Khan Meanchey, Phnom Penh
www.chipmong.com

33th FL.RS TOWER, 121/92 RATCHADAPHISEK RD.


BANGKOK 10400, THAILAND
TEL. 0-2642-3330[7Lines] , FAX. 0-2642-2138
Website:http://www.ma-ar.com

00 <=400
<=4
Qbic Engineers & Architects Co.,Ltd.
1000
8 Soi KALONG 4 SANAMBINNAM RD.
406 NONTABURI Tel.0-2950-4374-5
Fax: 0-2580-3231
1000 E-Mail : qbic@qbic.co.th

406

406

1168/8 12th FLOOR, LUMPINI TOWER BUILDING,


RAMA IV RD. THUNGMAHAMEK, SATHORN,
BANGKOK 10120, THAILAND TEL:0-2679-9079-84
FAX:0-2679-9085 E-mail:mitr_dd@mitr.com.

CHINA CONSTRUCTION (S.E.A)


(CAMBODIA) CORPORATION Ltd
#86, Street Nakry, Sangkat Terk Tla,
Khan Sen Sok, Phnom Penh, Cambodia.

SKETCHUP FRAME SYSTEM CEILING C-BAR (C110+C111)

Fix Spring Cross tee Main bar


Connect clip
Cross tee

Screw
Conection frame : L =100mm Main bar
Ceiling height

50mm wide dedicate adhesive


Gypsum board
Ceiling height
CONNECTION BETWEEN MAIN BAR Dedicate skimcoat
AND FURRING CROSS CHANNEL
GYPSUM BOARD CONNECTION DETAIL

WALL ANGLE Expasion Bolts R.C ceiling


or L-angle frame system
Bolt angle Ceiling concrete
Hanger wire

Hanger bolt Ø4 Suspension bolt Ø6


Fix Spring Main bar
Connection
(Connect clip) of main frame Fix Spring

WALL
Main bar
Ceiling height
Gypsum board Cross tee

MAIN FRAME CONNECTION DETAIL CONNECTION BETWEEN SUSPENSION


CONNECT WALL ANGEL WITH BRICK WALL DETAIL ROD WITH CEILING CONCRETE
STEP 1: LEVEL OF GYPSUM CEILING DETERMINATION
• REFERENCE POINT SETTING OUT BY ENGINEEER AND MARK
LOCATION OF CEIILING PLAN AT WALL AND COLMN
• NORMALLY MARK LEVEL AT THE BOTTOM OF CEILING PLAN
• NEXT, USING LASER LEVEL TO MEASURE AND CHECK GYPSUM
CEILING LEVEL

STEP 2: INSTALL WALL ANGLE


• WALL ANGLE FIXED TO WALL BY CHIRAL
• CHIRAL SPACING NOT EXCEED 300MM

GYPSUM CEILING
INSTALLATION METHOD

CHINA CONSTRUCTION CATEGORIES: TYPICAL CREATE BY: NGUYỄN TRUNG THẠCH


ENGINEERING CORPORATION CSCEC-F-09
CODE: CHECK BY: PHAN BÙI ANH TÀI
CSCEC BIM TEAM DRAWING NAME: GYPSUM CEILING INSTALLATION METHOD REVISION: 00 JUL 2021
STEP 3: SETTING OUT MAIN RUNNER
• CHOOSING COHERENCE MAIN RUNNER INSTALL DIRECTION
WITH SUSPENSION ROD LOCATION
• SPACING BETWEEN WALL AND SUSPENSION ROD IS 610MM
• MAXIMUM SPACING BETWEEN 2 SUSPENSION ROD IS
800-1000MM

STEP 4: INSTALL SUSPENSION ROD


• USING CONCRETE BREAKER DRILLING MACHINE TO DIRECT
DRILL INTO SLAB, CONNECT BY BOLT ANCHOR & ECU
• SUSPENSION ROD NEED TO PLUMP

GYPSUM CEILING
INSTALLATION METHOD

CHINA CONSTRUCTION CATEGORIES: TYPICAL CREATE BY: NGUYỄN TRUNG THẠCH


ENGINEERING CORPORATION CSCEC-F-09
CODE: CHECK BY: PHAN BÙI ANH TÀI
CSCEC BIM TEAM DRAWING NAME: GYPSUM CEILING INSTALLATION METHOD REVISION: 00 JUL 2021
STEP 5: INSTALL MAIN T
• ATTACH MAIN T INTO SUSPENSION ROD, ADJUST MAIN T
• USING GYPSUM BOARD 9.5MM THK, SPACING BETWEEN MAINT T
ABOUT 1000MM

STEP 6: INSTALL LONG CROSS T


• SPACING BETWEEN LONG CROSS IS 406MM
• MAIN T CONNECT WITH LONG CROSS T BY JOINT INTO MAIN T

GYPSUM CEILING
INSTALLATION METHOD

CHINA CONSTRUCTION CATEGORIES: TYPICAL CREATE BY: NGUYỄN TRUNG THẠCH


ENGINEERING CORPORATION CSCEC-F-09
CODE: CHECK BY: PHAN BÙI ANH TÀI
CSCEC BIM TEAM DRAWING NAME: GYPSUM CEILING INSTALLATION METHOD REVISION: 00 JUL 2021
STEP 7: ADJUST MAIN T AND LONG CROSS T
• AFTER INSTALLED, ADJUST MAIN T AND LONG CROSS T
CORRECT AND PLATERN
• CHECK LEVEL BY LASER LEVEL

STEP 8: INSTALL GYPSUM BOARD


• MAXIMUM SPACING BETWEEN CHIRAL IS 200MM AT EDGE
GYPSUM BOARD AND 300MM AT INTERNAL LOCATION GYPSUM
BOARD
• MAXIUMUN SPACING BETWEEN 2 GYPSUM BOARD IS 3-5MM

GYPSUM CEILING
INSTALLATION METHOD

CHINA CONSTRUCTION CATEGORIES: TYPICAL CREATE BY: NGUYỄN TRUNG THẠCH


ENGINEERING CORPORATION CSCEC-F-09
CODE: CHECK BY: PHAN BÙI ANH TÀI
CSCEC BIM TEAM DRAWING NAME: GYPSUM CEILING INSTALLATION METHOD REVISION: 00 JUL 2021
CHINA CONSTRUCTION (S.E.A)
(CAMBODIA) CORPORATION Ltd
#86, Street Nakry, Sangkat Terk Tla,
Khan Sen Sok, Phnom Penh, Cambodia.

FTB PROJECT

METHOD STATEMENT
TILING
1. MATERIAL FOR TILING WORKS: 2. EQUIPMENT FOR TILING WORKS:

No. Material Name Image Notes No. Equipment Name Image Unit

1 Tile Submit 1 Trowel Set

Rubber-hammer
2 Sand Submit 2 Set

Spirit level
3 Cement Submit 3 Set

Adhesive Submit 4 Saw Set


4

Tile grouting Spool of theard / Plumb


5 Submit 5 Set

- Materials arriving at the construction site must be checked and 6 Knife Set
accepted before being put into use.

- Transportation of materials shall be by lorry or trailer and Electric wire


7 Set
unloading by tower crane, fork lift and/or by manual as
appropriate
Rough-trowel
8 Set
- Store materials at designated location and adequately protected.

- Prevent flood by providing perimeter surface drainage if Little mechanical mixer


necessary 9 Set

- Boarded platform at least 75 mm off the ground and undercover Corner square-ruler
are recommended to protect contact from water and construction 10 Set
debris.
Measuring tape
- Materials shall be hoist up by tower crane and/or hoist. 11 Set

12 Kitbag Set

Laser device
14 Set

CHINA CONSTRUCTION CATEGORIES: FINISHING CREATE BY: NGUYEN TRUNG THACH


ENGINEERING CORPORATION CSCEC
CODE: CHECK BY: PHAN BUI ANH TAI
CSCEC BIM TEAM DRAWING NAME: MOS FOR TILING FLOOR WORK REVISION: 10.AUG/2021
STEP 1: SURVEYING WORKS
- CLEANING SCREED/NG SURFACE OFF DIRT AND DEBRIS

- MARKING PERPENDICULAR LINES ON FLOOR TO ENSURE THE SQUARENESS OF TILING

- IF ARIA WEET: CHECK & CONFIRM THAT WATERPROOFING WORKS DONE & MAKE SURE
THAT REPAIR WORK FOR CRACK LINES, HOLLOWNESS OR UNEVENNESS NOT EFFECTED
WATERPROOFING LAYERS BELOW.

STEP 2: TITLING WORKS ( FIRST TILE )

- FIRST TILE MUST BE IDENTIFIED ON SHOP DRAWINGS APPROVE

- ARRANGE FLOOR TILES FOR 2 STARTING ROWS WITH SPACERS TO CHEKC NUMBER OF
TILES IN EACH ROW & CUT TILE PIECES WITH ALLOWED THAN 1/2 TILE WIDE.

- CHECKING ACCURACY OF TWO FIRST COURSES

STEP 3: TITLING WORKS

- CONTINUE TILING

- CLEANING JOINTS OFF DIRT AND EXCESS ADHESIVE, GROUTING

- CLEANING AND PROTECTING TILED FLOOR

- AFTER COMPLETION OF CURING, CHECK HOLLOWNESS, UNEVENNESS, ALIGNMENT,


REMOVE LOOSE PARTS IN JOINT GAPS & DO RECTIFICATION FOR DEFECTS.

CHINA CONSTRUCTION CATEGORIES: FINISHING CREATE BY: NGUYEN TRUNG THACH


ENGINEERING CORPORATION CSCEC
CODE: CHECK BY: PHAN BUI ANH TAI
CSCEC BIM TEAM DRAWING NAME: MOS FOR TILING FLOOR WORK REVISION: 10.AUG/2021
CHINA CONSTRUCTION (S.E.A)
(CAMBODIA) CORPORATION Ltd
#86, Street Nakry, Sangkat Terk Tla,
Khan Sen Sok, Phnom Penh, Cambodia.

FTB PROJECT

METHOD STATEMENT
PAINTING
NO. MATERIAL NAME IMAGE LAYER NO. EQUIPMENT NAME IMAGE UNIT

1 1 SANDPAPER Set
PUTTY 2 Layer

2 PRIMING PAINT 1 Layer 2 FOAM TROWEL Set

3 MECHANICALLY DRIVEN Set


3 FINISHING PAINT 2 Layer AGITATOR

4 ROUGH-TROWEL Set

GENERAL STANDARD: 5 SCRAPER Set

• THE PAINT MUST BE FULL OF LABEL OF NAME, PRODUCER, TYPE, ITEM


CODE, COLOR CODE, EXP AND MFG
• PAINT MUST BE PRESERVED IN DRY COOL PLACE, AVOID HIGH ELECTRICAL Set
6
TEMPERATURE INSULATION PAPER
• MUST PLACED IN BALANCE AND UPRIGHT POSITION
• THE LID IS ALWAYS CLOSED, ADVOID EVAPORATED AND REDUCTION
PAINT QUALITY
• AFTER THE PAINT IS OVER, PRESERVE BY COVERING THE PAINT WITH 7 PAINT ROLLER Set
A LID WITH A PLASTIC BAG AND PLACED IT IN A DRY PLACE WHERE IT
IS NOT DAMP, ADOVID DIRECT SUNLIGHT
• DEPENDING ON THE REQUIREMENT OF EACH FLOOR OF TOWER,
PAINT MATERIALS ARE LIFTED USING THE ELEVATER OR HOIST OR 8 PAINT BRUSH Set
TOWER CRANE

9 A TYPE LADDER Set

10 HAND SPRAY GUN Set

CHINA CONSTRUCTION CATEGORIES: FINISHING CREATE BY: NGUYỄN TRUNG THẠCH


ENGINEERING CORPORATION CSCEC-F-08
CODE: CHECK BY: PHAN BUI ANH TAI
CSCEC BIM TEAM DRAWING NAME: EMULSION PAINTING METHOD REVISION: 00 AUG 2021
STEP 1: CHECK WALL SURFACE
• CLEANING UP WALL SURFACE
• CHECKING WALL FLATNESS
• CHECKING HUMIDITY OF WALL
• NEED TO UNROLL THE TARPAULIN TO PROTECT THE FLOOR FROM PAINT

STEP 2:PUTTY WORK


• USING RIGHT PUTTY TYPE FOR EACH TYPE WALL, USING MECHANICALLY
DRIVEN AGITATOR TO MIXING
• MASTIC NOT EXCEED THK 3MM
• SANDPAPER WORK FOR WALL SURFACE
• BEFORE PRIMER PAINTING WORK, CLEAN UP WALL SURFACE BY BRUSH
TO REMOVE THE DUST AFTER SANDPAPER

STEP 3: PAINT WORK


• AFTER 2 HOUR WHEN THE PRIMER COAT PAINTING IS DRY, CONDUCT TO
FINISH THE FIRST LAYER
• AFTER 2H, WHEN THE FIRST LAYER PAINT IS DRY, CONDUCT SECOND
FINISHING CLASS IS SIMILAR TO LAYER 1 CONSTRUCTION
• AT POSITION EASY BE DIRTY OR BE AFFECTED BY CONSTRUCTION NEED
THE NOTICE BOARD TO AVOID THE AFFECTION TO PAINTQUALITY

CHINA CONSTRUCTION CATEGORIES: FINISHING CREATE BY: NGUYỄN TRUNG THẠCH


ENGINEERING CORPORATION CSCEC-F-08
CODE: CHECK BY: PHAN BUI ANH TAI
CSCEC BIM TEAM DRAWING NAME: EMULSION PAINTING METHOD REVISION: 00 AUG 2021